Gagan Klara
Completion date passedHaveli, Maharashtra 411045 |Promoter: Gagan Housing And Landmarks LLP
Project summary
As registered with MahaRERA
MahaRERA's search listing gives this project's name, promoter and location only.
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 2 years
The latest completion date on record passed 7 months ago.
- Registered
- 5 Mar 2019
- Promised
- 30 Mar 2024
- Revised
- 30 Mar 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100019739 | 5 Mar 2019 | 30 Mar 2024 | 30 Mar 2026 | Gagan Housing And Landmarks LLP | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.
- Regulatory order19 May 2025Matched by RERA number
Regulatory order: PROJECT NAME: GAGAN KLARA (Regulatory Case No. 364 OF 2025) dated 19 May, 2025.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.