Haveli, Maharashtra 412101 |Promoter: Godrej Skyline Developers Limited

2 Dec 2019Registered with MahaRERA
30 Sep 2027Promised completion
30 Jan 2028Revised completionPushed back 4 months
7Buildings
1,139Units registered871 booked (76%)
1MahaRERA listings and orders

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
7
Unit types
2 rhk, 3 rhk, 2rhk, 3rhk1,139 units in all
Address
PLOT NO 1 BEARING S NO 10/1A/3, 10/1B, 11/1A, 11/2A PART, 11/3, 11/4 PART, 11/4/2, 11/1B, 12/1, 12/2/1, 12/2/2, 12/2/3, 13/2, 13/1B PART PLOT 01 IN VILLAGE MAMURDI, Service road to Pune Mumbai Expressway, MAMURDI VILLAGEPIN 412101
Designated bank account
76
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.66000, 73.70000
Forest Grove At Godrej Park Greens is at latitude 18.66000, longitude 73.70000.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
2 Dec 2019
Promised
30 Sep 2027
Revised
30 Jan 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000231292 Dec 201930 Sep 202730 Jan 2028Godrej Skyline Developers LimitedProject page

7 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Tower A120154
Tower A217132
Tower A322173
Tower A422170
Tower A522170
Tower A622170
Tower A722170

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

871 of 1,139 units booked (76%), as the promoter reported to MahaRERA

2 rhk · 716 units3 rhk · 250 units2rhk · 129 units3rhk · 44 units
BuildingTypeCarpet areaUnitsBooked
Tower A12 rhk47.53 sq m · 512 sq ft5851
Tower A12 rhk48.03 sq m · 517 sq ft5644
Tower A13 rhk58.33 sq m · 628 sq ft2012
Tower A13 rhk58.83 sq m · 633 sq ft2018
Tower A22 rhk47.53 sq m · 512 sq ft4843
Tower A22 rhk48.03 sq m · 517 sq ft5040
Tower A23 rhk58.33 sq m · 628 sq ft166
Tower A23 rhk58.83 sq m · 633 sq ft1816
Show all 32 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Tower A32rhk47.53 sq m · 512 sq ft124
Tower A32rhk48.03 sq m · 517 sq ft184
Tower A32rhk50.19 sq m · 540 sq ft5246
Tower A32rhk50.87 sq m · 548 sq ft4747
Tower A33rhk58.33 sq m · 628 sq ft40
Tower A33rhk58.74 sq m · 632 sq ft184
Tower A33rhk58.83 sq m · 633 sq ft62
Tower A33rhk59.27 sq m · 638 sq ft1613
Tower A42 rhk47.53 sq m · 512 sq ft6448
Tower A42 rhk48.03 sq m · 517 sq ft6238
Tower A43 rhk58.33 sq m · 628 sq ft229
Tower A43 rhk58.83 sq m · 633 sq ft2217
Tower A52 rhk47.53 sq m · 512 sq ft6446
Tower A52 rhk48.03 sq m · 517 sq ft6238
Tower A53 rhk58.33 sq m · 628 sq ft225
Tower A53 rhk58.83 sq m · 633 sq ft2214
Tower A62 rhk47.53 sq m · 512 sq ft6459
Tower A62 rhk48.03 sq m · 517 sq ft6259
Tower A63 rhk58.33 sq m · 628 sq ft2212
Tower A63 rhk58.83 sq m · 633 sq ft2221
Tower A72 rhk47.53 sq m · 512 sq ft6461
Tower A72 rhk48.03 sq m · 517 sq ft6257
Tower A73 rhk58.33 sq m · 628 sq ft2215
Tower A73 rhk58.83 sq m · 633 sq ft2222

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 158 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN- SKYLINE.pdf · uploaded 13 Nov 2019Source
  • PAN CardPan Card New.pdf · uploaded 9 Oct 2024Source

Legal

  • Legal Title reportMamurdi_Supplemental title report.pdf · uploaded 13 Nov 2019Source
  • Declaration Form BForm B _compressed.pdf · uploaded 13 Nov 2019Source
  • OtherAnnexure- Amenities.pdf · uploaded 14 Nov 2019Source
  • OtherAnnexure- Development Work.pdf · uploaded 14 Nov 2019Source
  • Declaration Form BFOREST GROVE FORM B.pdf · uploaded 13 Aug 2024Source
Show all 159 documentsShow fewer documents

Migrated

  • 1 PAN CardPAN- SKYLINE.pdf · uploaded 13 Nov 2019Source
  • 1 Copy of the legal title reportMamurdi_Supplemental title report.pdf · uploaded 13 Nov 2019Source
  • 1 Copy of Layout Approval (in case of layout)Layout approval_compressed_2.pdf · uploaded 13 Nov 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout approval_compressed_2.pdf · uploaded 13 Nov 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 13 Nov 2019Source
  • 1 Declaration in FORM BForm B _compressed.pdf · uploaded 13 Nov 2019Source
  • 1 Details of encumbrancesEncumbrance.pdf · uploaded 14 Nov 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 14 Nov 2019Source
  • 1 Proforma of Allotment letterAllotment Letter N-2.pdf · uploaded 14 Nov 2019Source
  • 2 Proforma of Allotment letterAFS N2 HO proposed modification15-11-2019 - Clean.pdf · uploaded 14 Nov 2019Source
  • 1 OtherAnnexure- Amenities.pdf · uploaded 14 Nov 2019Source
  • 2 OtherAnnexure- Development Work.pdf · uploaded 14 Nov 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)20191231_architect certificate Godrej Forest Grove_rev -.pdf · uploaded 6 May 2020Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer's Certificate Forest Grove.pdf · uploaded 6 May 2020Source
  • 3 Proforma of Allotment letterForest Grove AFS-uploaded-converted.pdf · uploaded 20 Jul 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)QUALITY ASSURANCE CERTIFICATE -FORM 2A - PARK GREENS.PDF · uploaded 20 Aug 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 Forest Grove.pdf · uploaded 1 Oct 2020Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)20200930_architect certificate Godrej Forest Grove.pdf · uploaded 11 Oct 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers certificate for N2 Forest Grove Sep 2020.pdf · uploaded 11 Oct 2020Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)MAHARERA Quality Assurance Certificate Form 2A GForest Grove Sep 20.pdf · uploaded 11 Oct 2020Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Godrej Skyline Forest Grove RERA Cert Auditors Cert and Annexures I and II Y E 31 Mar 20.pdf · uploaded 11 Oct 2020Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest Grove sep 20 signed.pdf · uploaded 12 Apr 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)20210331 Architect Certificate Godrej Forest Grove.pdf · uploaded 10 May 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)MAHARERA Quality Assurance Certificate - Form 2A - GFG - March - 21.pdf · uploaded 10 May 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest Grove March 2021 signed.pdf · uploaded 10 May 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)20201231 architect certificate Godrej Forest Grove.pdf · uploaded 12 May 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)MAHARERA Quality Assurance Certificate - Form 2A - GFG - Dec - 20.pdf · uploaded 12 May 2021Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest Grove Dec 20 SIGNED.PDF · uploaded 12 May 2021Source
  • 1 Disclosure of sold/ booked inventoryForest Grove.pdf · uploaded 24 May 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Quarterly Update Q4 FY20-21 Engineers Certificate Grove.pdf · uploaded 25 May 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Forest Grove Q3.pdf · uploaded 25 May 2021Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)20210630 Architect Certificate Godrej Forest Grove.pdf · uploaded 10 Jul 2021Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Forest Grove Engineers Certificate June21.pdf · uploaded 10 Jul 2021Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Forest Grove Quality Assurance Certificate June21 compressed.pdf · uploaded 10 Jul 2021Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)MDD Forest Grove June 2021 Signed.pdf · uploaded 10 Jul 2021Source
  • 2 Disclosure of sold/ booked inventoryForest Grove compressed.pdf · uploaded 15 Jul 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentNew CC - Forest Grove.pdf · uploaded 8 Sep 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentNew Layout Mamurdi compressed.pdf · uploaded 9 Sep 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Forest Grove RERA Certificate 31 March 21-1-7.pdf · uploaded 30 Sep 2021Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)20210930 Architect Certificate Godrej Forest Grove.pdf · uploaded 11 Oct 2021Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA Quarterly Update FY21 22 Engineer Certificate FG Q2.pdf · uploaded 11 Oct 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance plan for FG Q2 FY 21-22.pdf · uploaded 11 Oct 2021Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)MDD_Forest Grove Sep_2021 Draft_Signed.pdf · uploaded 11 Oct 2021Source
  • 3 Disclosure of sold/ booked inventoryForest Grove at GPG Sep 21.pdf · uploaded 26 Oct 2021Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Forest Grove Architect Certificate 311221.pdf · uploaded 7 Jan 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)Forest Grove Eng Certificate 311221.pdf · uploaded 7 Jan 2022Source
  • 4 Disclosure of sold/ booked inventoryForest Grove Inventory 311221.pdf · uploaded 7 Jan 2022Source
  • 1 CERSAI detailsCERSAI Search Report 270122.pdf · uploaded 2 Feb 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)FOREST GROVE society registration certificate.PDF · uploaded 21 Feb 2022Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest grove CA Certificate 311221_compressed.pdf · uploaded 15 Mar 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate (Form 1).PDF · uploaded 11 Apr 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Engineer's Certificate for uploading.pdf · uploaded 11 Apr 2022Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Certificate (Form 2 A).pdf · uploaded 11 Apr 2022Source
  • 5 Disclosure of sold/ booked inventoryDisclosure of Inventory.pdf · uploaded 11 Apr 2022Source
  • 2 CERSAI detailsCERSAI Report.pdf · uploaded 11 Apr 2022Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 13 Apr 2022Source
  • 1 Declaration about Commencement CertificateDeclaration about Commencement Certifcate_Forest Grove.pdf · uploaded 7 Jul 2022Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate - Forest Grove.pdf · uploaded 9 Jul 2022Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate - Forest Grove.pdf · uploaded 9 Jul 2022Source
  • 3 CERSAI detailsCERSAI Search Report.pdf · uploaded 9 Jul 2022Source
  • 6 Disclosure of sold/ booked inventoryDisclosure of inventory.pdf · uploaded 9 Jul 2022Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_ Forest Grove Signed.pdf · uploaded 9 Jul 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FOREST GROVE.pdf · uploaded 30 Sep 2022Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Forest Grove.pdf · uploaded 14 Oct 2022Source
  • 7 Disclosure of sold/ booked inventoryDisclosure of inventory.pdf · uploaded 17 Oct 2022Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)FG_Sept22.pdf · uploaded 17 Oct 2022Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate_Forest Grove.pdf · uploaded 19 Oct 2022Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Forest Grove.pdf · uploaded 19 Jan 2023Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Forest grove.pdf · uploaded 19 Jan 2023Source
  • 8 Disclosure of sold/ booked inventoryDisclosure of Sold-Forest-Grove_Dec'22.pdf · uploaded 19 Jan 2023Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)Godrej Forest Grove.pdf · uploaded 20 Jan 2023Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Godrej Forest Grove.pdf · uploaded 15 Apr 2023Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Forest Grove.pdf · uploaded 15 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Quality Assuarance Certificate Forest Grove.pdf · uploaded 15 Apr 2023Source
  • 9 Disclosure of sold/ booked inventoryforest grove - disclosure of sold inventory.pdf · uploaded 15 Apr 2023Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)MDD_RERA certificate Forest Grove-OMD.PDF · uploaded 19 Apr 2023Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Godrej Park Greens_7_11zon.pdf · uploaded 20 Jul 2023Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Godrej Forest Grove_5_11zon.pdf · uploaded 20 Jul 2023Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineers Certificate Forest Groove.pdf · uploaded 20 Jul 2023Source
  • 10 Disclosure of sold/ booked inventoryDisclosure of Sold-Forest-Grove_Jul-23.pdf · uploaded 20 Jul 2023Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)MDD_RERA certificate Forest Grove-Signed.pdf · uploaded 20 Jul 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Skyline - Forest Grove at Godrej Skyline.pdf · uploaded 21 Sep 2023Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)Forest Grove Engg Cetificate.pdf · uploaded 19 Oct 2023Source
  • 11 Disclosure of sold/ booked inventoryDisclosure of Sold-Forest-Grove Sept23.pdf · uploaded 19 Oct 2023Source
  • 14 CA Certificate on Project Cost & Fund withdrawal (Form 3)MDD_RERA certificate Forest Grove-Signed.pdf · uploaded 19 Oct 2023Source
  • 2 Details of encumbrancesDeclaration _Forest Grove.pdf · uploaded 20 Oct 2023Source
  • 3 Details of encumbrancesEncumbrance_Forest Grove.pdf · uploaded 20 Oct 2023Source
  • 15 Architect’s Certificate of Percentage of Completion of Work (Form 1)Forest Grove - Architects Certificate.pdf · uploaded 20 Oct 2023Source
  • 16 Architect’s Certificate of Percentage of Completion of Work (Form 1)Forest Grove - Architect's Certificate.pdf · uploaded 12 Jan 2024Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)Forest Grove - Enggineer's Certificate.pdf · uploaded 12 Jan 2024Source
  • 4 CERSAI detailsCERSAI_Search_Report_200293339474_For_Debtor_Based_Search_12_01_2024_11_56_49_022.pdf · uploaded 12 Jan 2024Source
  • 12 Disclosure of sold/ booked inventoryDisclosure of Sold-Forest-Grove_Dec 23.pdf · uploaded 12 Jan 2024Source
  • 15 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest Grove Dec-23_Signed.pdf · uploaded 12 Jan 2024Source
  • 13 Disclosure of sold/ booked inventoryApril 24_Disclosure of Sold-Forest Grove signed.pdf · uploaded 12 Apr 2024Source
  • 17 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate Forest Grove March,2024.pdf · uploaded 15 Apr 2024Source
  • 16 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificat Forest Grove at Park Green - March,2024.pdf · uploaded 15 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality Certificat Forest Grove at Park Green - March,2024.pdf · uploaded 15 Apr 2024Source
  • 16 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest Grove_March 2024_Signed.pdf · uploaded 16 Apr 2024Source
  • 14 Disclosure of sold/ booked inventoryForest Grove at Godrej Park Greens.pdf · uploaded 19 Jul 2024Source
  • 18 Architect’s Certificate of Percentage of Completion of Work (Form 1)Forest Grove.pdf · uploaded 20 Jul 2024Source
  • 17 Engineer’s Certificate on Cost Incurred on Project (Form 2)MDD_FOREST GROVE_JUNE 24_Signed.pdf · uploaded 20 Jul 2024Source
  • 18 Engineer’s Certificate on Cost Incurred on Project (Form 2)Forest Grove.pdf · uploaded 20 Jul 2024Source
  • 2 Declaration in FORM BFOREST GROVE FORM B.pdf · uploaded 13 Aug 2024Source
  • 15 Disclosure of sold/ booked inventoryForest Grove Inventory Disclosure_compressed.pdf · uploaded 13 Aug 2024Source
  • 1 PAN CardPan Card New.pdf · uploaded 9 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Forest Grove Form 5_compressed.pdf · uploaded 9 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Godrej Forest Grove.pdf · uploaded 15 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Forest Grove.pdf · uploaded 15 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryForest Grove at Godrej Park Greens.pdf · uploaded 15 Oct 2024Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 15 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest Grove Form 3.pdf · uploaded 19 Oct 2024Source
  • 2 CERSAI detailsCERSAI Latest.pdf · uploaded 21 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Godrej Forest Grove.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest grove.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Godrej Forest Grove.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryForest Grove at Godrej Park Greens.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Godrej Forest Grove.pdf · uploaded 20 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Forest Grove CA Cert.pdf · uploaded 20 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Annexure B Forest Grove at Godrej Park Green.pdf · uploaded 20 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryForest Grove at Godrej Park Greens.pdf · uploaded 20 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Quality Assurance Certificate GFG.pdf · uploaded 20 Apr 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)GFG.pdf · uploaded 1 May 2025Source
  • Form 1Architect Certificate Godrej Forest Grove (1).pdf · uploaded 20 Jul 2025Source
  • Form 2Annexure B Forest grove.pdf · uploaded 20 Jul 2025Source
  • Form 3CA certificate Forest Grove June 25 Signed.pdf · uploaded 20 Jul 2025Source
  • Disclosure of Sold and Booked InventoryForest Grove at Godrej Park Greens.pdf · uploaded 20 Jul 2025Source
  • Form 5 (FY 2024-2025)Forest Grove Form5_compressed.pdf · uploaded 29 Aug 2025Source
  • Withdrawal Update Form 1Architect Certificate Godrej Forest Grove (1) Q2FY26.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 2Eng_certificate forest grove.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 3RERA certificate Forest Grove Sep25.pdf · uploaded 20 Oct 2025Source
  • Withdrawal Update Form 1Architect Certificate Godrej Forest Grove Q3FY26.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 2Engineers Certificate GFG Q3FY26.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 3RERA certificate Forest Grove December 25 Signed.pdf · uploaded 24 Jan 2026Source
  • Withdrawal Update Form 1Architect Certificate Godrej Forest Grove Q4FY26.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 2Eng_Certificate_GFG.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 3MDD_RERA certificate Forest Grove_March_26_Signed.pdf · uploaded 24 Apr 2026Source
  • Withdrawal Update Form 1Arch RERA Certificate GFG Q1FY27.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2Engg Certificate GFG Q1FY27.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3MDD_RERA certificate Forest Grove_June_26_Signed.pdf · uploaded 20 Jul 2026Source
  • Form 5 (FY 2025-2026)Forest Grove form 5 FY26.pdf · uploaded 29 Sep 2026Source

Technical

  • DocumentLayout approval_compressed_2.pdf · uploaded 13 Nov 2019Source
  • DocumentLayout approval_compressed_2.pdf · uploaded 13 Nov 2019Source
  • DocumentNew Layout Mamurdi compressed.pdf · uploaded 9 Sep 2021Source

Technical (Architect)

  • DocumentGodrej Forest Grove.pdf · uploaded 15 Oct 2024Source
  • DocumentArchitect Certificate Godrej Forest Grove.pdf · uploaded 20 Jan 2025Source
  • DocumentArchitect Certificate Godrej Forest Grove.pdf · uploaded 20 Apr 2025Source
  • DocumentArch RERA Certificate GFG Q1FY27.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • DocumentForest Grove.pdf · uploaded 15 Oct 2024Source
  • DocumentGodrej Forest Grove.pdf · uploaded 20 Jan 2025Source
  • DocumentAnnexure B Forest Grove at Godrej Park Green.pdf · uploaded 20 Apr 2025Source
  • DocumentEngg Certificate GFG Q1FY27.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Regulatory order16 Aug 2025Matched by RERA number

    Regulatory order: PROJECT NAME: FOREST GROVE AT GODREJ PARK GREENS (Regulatory Case No. 394 OF 2025) dated 16 Aug, 2025.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

Survey, CTS, gat or plot numbers

10/1B11/1A11/1B11/2A PART11/311/4/211/4 PART12/112/2/112/2/212/2/3PLOT NO 1 BEARING S NO 10/1A/3

Boundaries

North
18m Wide Dp Road And Part S No 13 Part
South
Adjoining Godrej Park Greens Project
East
18m Wide Proposed Dp Road
West
18m Wide Proposed Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
EngineerAnil Powar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project page · MahaRERA regulatory lists and ordersData through is when MahaRERA's project page was last read.Methodology