Skip to content

Vrindavan Heights Phase II

Certificate Signed

Hadapsar, Pune 411028 |Promoter: Kwality World Developers (Aop)

11 May 2018Registered with MahaRERA
30 Sep 2023Promised completion
1Building
77Units registered65 booked (84%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK, Restaurant, Shop77 units in all
Address
183/3, 183/4 P, 183/5a P, 183/5b, 183/7, Sade Satra Nali, HadapsarPIN 411028
Designated bank account
154
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.51988, 73.93848
Vrindavan Heights Phase II is at latitude 18.51988, longitude 73.93848.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 30 Sep 2023

The latest completion date on record passed 3 years and 1 month ago.

Registered
11 May 2018
Promised
30 Sep 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210001646611 May 201830 Sep 202330 Sep 2023Kwality World Developers (Aop)Project page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Vrindavan Heights Wing B1577

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

65 of 77 units booked (84%), as the promoter reported to MahaRERA

2BHK · 68 units3BHK · 1 unitRestaurant · 1 unitShop · 7 units
TypeCarpet areaUnitsBooked
2BHK3,900 sq m · 41,979 sq ft6864
3BHK79.72 sq m · 858 sq ft11
Restaurant21.89 sq m · 236 sq ft10
Shop177.48 sq m · 1,910 sq ft70

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 65 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN Kwality World Developers.pdf · uploaded 25 Apr 2018Source

Legal

  • Legal Title reportTitle Search Report.pdf · uploaded 30 Apr 2018Source
  • Declaration Form BForm B AOP.pdf · uploaded 9 May 2018Source
  • Declaration Form BRERA FORM-B AFFIDAVIT.pdf · uploaded 13 Dec 2019Source

Migrated

  • 1 PAN CardPAN Kwality World Developers.pdf · uploaded 25 Apr 2018Source
  • 1 Details of encumbrancesNon Encumbrance Certificate.pdf · uploaded 25 Apr 2018Source
  • 1 Copy of Layout Approval (in case of layout)1525- Layout Sanctioned.pdf · uploaded 25 Apr 2018Source
Show all 66 documentsShow fewer documents

Migrated

  • 1 Building Plan Approval (IOD)1525- Building Sanctioned.pdf · uploaded 25 Apr 2018Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC-Building Sanctioned compressed.pdf · uploaded 25 Apr 2018Source
  • 1 Certificates of CA (Form 3)Form 3 RERA Certificate.pdf · uploaded 25 Apr 2018Source
  • 1 Copy of the legal title reportTitle Search Report.pdf · uploaded 30 Apr 2018Source
  • 1 Declaration in FORM BForm B AOP.pdf · uploaded 9 May 2018Source
  • 1 Proforma of Allotment letterAgreement to Sale Draft.pdf · uploaded 10 May 2018Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate-compressed.pdf · uploaded 31 Dec 2018Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg Certificate-ilovepdf-compressed.pdf · uploaded 31 Dec 2018Source
  • 2 Certificates of CA (Form 3)Q2 KWD RERA Certificate(scanned copy)-ilovepdf-compressed.pdf · uploaded 31 Dec 2018Source
  • 2 Copy of Layout Approval (in case of layout)Revised Layout Plan.pdf · uploaded 5 Apr 2019Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised Comencement Certificate.pdf · uploaded 5 Apr 2019Source
  • 2 Proforma of Allotment letterRevised Agreement to Sale.pdf · uploaded 5 Apr 2019Source
  • 3 Certificates of CA (Form 3)RERA Certificate FORM 3-compressed.pdf · uploaded 9 Aug 2019Source
  • 4 Certificates of CA (Form 3)Vrindavan Heights Form 3_Q1_FY 2019-20_compressed.pdf · uploaded 28 Sep 2019Source
  • 2 Declaration in FORM BRERA FORM-B AFFIDAVIT.pdf · uploaded 13 Dec 2019Source
  • 5 Certificates of CA (Form 3)RERA Certificate Vrindavan Heights_compressed (1).pdf · uploaded 31 Dec 2019Source
  • 2 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 6 Jan 2020Source
  • 3 Proforma of Allotment letterAgreement Draft new.pdf · uploaded 24 Jan 2020Source
  • 4 Proforma of Allotment letterAgreement - Kwality World Developers - revised draft - 22-02-2020.pdf · uploaded 24 Feb 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)KWD FORM 5.pdf · uploaded 21 Apr 2020Source
  • 6 Certificates of CA (Form 3)RERA Certificate Form 3 Q 3.pdf · uploaded 20 May 2020Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)GTPL 02_compressed.pdf · uploaded 28 Jul 2020Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)GTPL 03_compressed.pdf · uploaded 28 Jul 2020Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)GTPL 04_compressed.pdf · uploaded 28 Jul 2020Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)GTPL 05_compressed.pdf · uploaded 28 Jul 2020Source
  • 7 Certificates of CA (Form 3)Form 3.pdf · uploaded 13 Aug 2020Source
  • 8 Certificates of CA (Form 3)Form 3- Certificate (Uploaded).pdf · uploaded 24 Sep 2020Source
  • 9 Certificates of CA (Form 3)Form 3 for Upload.pdf · uploaded 1 Oct 2020Source
  • 10 Certificates of CA (Form 3)FORM 3 Q2 FY 2020-21-compressed.pdf · uploaded 23 Dec 2020Source
  • 11 Certificates of CA (Form 3)FORM 3-c_compressed.pdf · uploaded 31 Mar 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 22042021.pdf · uploaded 23 Apr 2021Source
  • 12 Certificates of CA (Form 3)RERA Certificate Form-3_Q4 Kwality_compressed.pdf · uploaded 9 Aug 2021Source
  • 13 Certificates of CA (Form 3)Form 3 - FY 21-22 Q3_compressed (1).pdf · uploaded 25 Apr 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)From 5 certificate.pdf · uploaded 10 May 2022Source
  • 14 Certificates of CA (Form 3)Form-3_Q4 Kwality.pdf · uploaded 7 Oct 2022Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Kwality Rera Form 5 Certificate.pdf · uploaded 25 Nov 2022Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - 30-9-22.pdf · uploaded 20 Jan 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - 31-12-2022.pdf · uploaded 20 Jan 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 20 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Eng Quality Assurance Cert.pdf · uploaded 20 Jan 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Eng Quqlity assurance certificate.pdf · uploaded 20 Jan 2023Source
  • 3 a Details of encumbrances concerned to FinanceNo encumbrances concerned to legal.pdf · uploaded 30 Jan 2023Source
  • 1 b Details of encumbrances concerned to LegalNo encumbrances concerned to legal.pdf · uploaded 30 Jan 2023Source
  • 1 Declaration about Commencement CertificateDeclaration about commencement certificate.pdf · uploaded 30 Jan 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration of seperate bank account of real estate projects.pdf · uploaded 31 Jan 2023Source
  • 1 Deviation Report with respect to Allotment letterNo deviation copy of allotment.pdf · uploaded 31 Jan 2023Source
  • 1 Deviation Report with respect to model copy of AgreementNo deviation model copy of agreement.pdf · uploaded 31 Jan 2023Source
  • 1 Proforma of Agreement for saleModel form of agreement to sale_11zon.pdf · uploaded 27 Feb 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report_200261596827_For_Asset_Based_Search_28_02_2023_15_28_26_053.pdf · uploaded 1 Mar 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Int 01-Mar-2023.pdf · uploaded 1 Mar 2023Source
  • 15 Certificates of CA (Form 3)Form 3_11zon.pdf · uploaded 24 May 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPart Occupancy Certificate.pdf · uploaded 22 Jun 2023Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)Form 4 Completion Certificate.pdf · uploaded 18 Aug 2023Source

Technical

  • Document1525- Building Sanctioned.pdf · uploaded 25 Apr 2018Source
  • Document1525- Layout Sanctioned.pdf · uploaded 25 Apr 2018Source
  • DocumentRevised Layout Plan.pdf · uploaded 5 Apr 2019Source

Technical (Architect)

  • DocumentForm 1 - 31-12-2022.pdf · uploaded 20 Jan 2023Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 20 Jan 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hadapsar, Haveli taluka

Survey, CTS, gat or plot numbers

183/3183/4 P183/5A P183/5B183/7

Boundaries

North
18 31 12 68 N 75 56 19 07 E
South
18 31 10 07 N 73 56 19 37 E
East
18 31 11 40 N 73 56 22 28 E
West
18 31 11 85 N 73 56 16 10 E

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectHrishikesh Kulkarni—
Chartered accountantAditya Patil—
Chartered accountantBaban Dangale—

Source: MahaRERA project page. Contact details are not shown.