Felicia Wing A

Certificate Signed

Hadapsar, Pune 411028 |Promoter: Anand Builders

Residential / Group HousingRERAP52100028478
4 Mar 2021Registered with MahaRERA
30 Dec 2024Promised completion
30 Jun 2026Revised completionPushed back 1 year and 6 months
1Building
88Units registered66 booked (75%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK, 3BHK88 units in all
Address
S. No.50/10/11/1, 50/10/11/2/1, Hadapsar - Handewadi Road, HadapsarPIN 411028
Designated bank account
86
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 1 year and 6 months

The latest completion date on record passed 4 months ago.

Registered
4 Mar 2021
Promised
30 Dec 2024
Revised
30 Jun 2026

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000284784 Mar 202130 Dec 202430 Jun 2026Anand BuildersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Wing A1188

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

66 of 88 units booked (75%), as the promoter reported to MahaRERA

2BHK · 45 units3BHK · 43 units
TypeCarpet areaUnitsBooked
2BHK53.8 sq m · 579 sq ft10
2BHK54.11 sq m · 582 sq ft53
2BHK54.51 sq m · 587 sq ft2518
2BHK54.75 sq m · 589 sq ft32
2BHK60.53 sq m · 652 sq ft108
2BHK61.01 sq m · 657 sq ft10
3BHK68.55 sq m · 738 sq ft55
3BHK68.95 sq m · 742 sq ft97
Show all 14 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
3BHK68.96 sq m · 742 sq ft55
3BHK69.24 sq m · 745 sq ft20
3BHK72.29 sq m · 778 sq ft108
3BHK72.53 sq m · 781 sq ft11
3BHK72.77 sq m · 783 sq ft108
3BHK73.19 sq m · 788 sq ft11

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 145 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPAN Card.pdf · uploaded 8 Jan 2021Source

Legal

  • Declaration Form BForm B.pdf · uploaded 8 Jan 2021Source
  • Legal Title reportTitle Search Report.pdf · uploaded 1 Mar 2021Source
  • Declaration Form BAFFIDAVIT CUM DECLARATION Form B.pdf · uploaded 30 Jan 2024Source
  • Disclosure of InterestDisclosure of Interest.pdf · uploaded 23 Sep 2024Source

Migrated

  • 1 PAN CardPAN Card.pdf · uploaded 8 Jan 2021Source
Show all 147 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumbrance Certificate.pdf · uploaded 8 Jan 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 8 Jan 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentPlan 1.pdf · uploaded 8 Jan 2021Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 8 Jan 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentPlan 3.pdf · uploaded 8 Jan 2021Source
  • 4 Building Plan Approval / NA Order for plotted developmentPlan 4.pdf · uploaded 8 Jan 2021Source
  • 5 Building Plan Approval / NA Order for plotted developmentPlan 5.pdf · uploaded 8 Jan 2021Source
  • 6 Building Plan Approval / NA Order for plotted developmentPlan 6.pdf · uploaded 8 Jan 2021Source
  • 7 Building Plan Approval / NA Order for plotted developmentPlan 7.pdf · uploaded 8 Jan 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 8 Jan 2021Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 8 Jan 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 20 Feb 2021Source
  • 1 Proforma of Allotment letterSample Agreement.pdf · uploaded 23 Feb 2021Source
  • 1 Copy of the legal title reportTitle Search Report.pdf · uploaded 1 Mar 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 Anand Builders A Wing 2021-22.pdf · uploaded 14 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Felicia Wing A.pdf · uploaded 11 Aug 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Felicia A Wing Q4.pdf · uploaded 11 Aug 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Felicia.pdf · uploaded 11 Aug 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Form 2A Felicia A Wing Q4.pdf · uploaded 11 Aug 2023Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Sold Inventory Felicia.pdf · uploaded 11 Aug 2023Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Sold Inventory Felicia.pdf · uploaded 11 Aug 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certificate 31-03-2023.pdf · uploaded 11 Aug 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Felicia Wing A.pdf · uploaded 11 Aug 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Form 5 Felicia A wing 2022-23.pdf · uploaded 29 Sep 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architecture Certificate.pdf · uploaded 6 Nov 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg certi_FELICIA WING A.pdf · uploaded 6 Nov 2023Source
  • 3 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD INVENTORY.pdf · uploaded 6 Nov 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Felicia Wing A.pdf · uploaded 6 Nov 2023Source
  • 8 Building Plan Approval / NA Order for plotted development1-10.pdf · uploaded 13 Dec 2023Source
  • 9 Building Plan Approval / NA Order for plotted development2-10.pdf · uploaded 13 Dec 2023Source
  • 10 Building Plan Approval / NA Order for plotted development3-10.pdf · uploaded 13 Dec 2023Source
  • 11 Building Plan Approval / NA Order for plotted development4-10.pdf · uploaded 13 Dec 2023Source
  • 12 Building Plan Approval / NA Order for plotted development5-10.pdf · uploaded 13 Dec 2023Source
  • 13 Building Plan Approval / NA Order for plotted development6-10.pdf · uploaded 13 Dec 2023Source
  • 14 Building Plan Approval / NA Order for plotted development7-10.pdf · uploaded 13 Dec 2023Source
  • 15 Building Plan Approval / NA Order for plotted development8-10.pdf · uploaded 13 Dec 2023Source
  • 16 Building Plan Approval / NA Order for plotted development9-10.pdf · uploaded 13 Dec 2023Source
  • 17 Building Plan Approval / NA Order for plotted development10-10.pdf · uploaded 13 Dec 2023Source
  • 2 Commencement Certificates / NA Order for plotted developmentCC-1946-23 (DATE - 07-11-2023).pdf · uploaded 13 Dec 2023Source
  • 1 Declaration about Commencement CertificateDECLARATION OF COMMENCEMENT.pdf · uploaded 13 Dec 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architech Certificate - Felicia.pdf · uploaded 24 Jan 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate fELICIA.pdf · uploaded 24 Jan 2024Source
  • 4 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY FELICIA.pdf · uploaded 24 Jan 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A Certifiacate A Wing Felicia_Final.pdf · uploaded 24 Jan 2024Source
  • 2 Declaration in FORM BAFFIDAVIT CUM DECLARATION Form B.pdf · uploaded 30 Jan 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A Felicia A Wing Q4.pdf · uploaded 30 Jan 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSEPARATE BANK ACCOUNT DECLARATION.pdf · uploaded 30 Jan 2024Source
  • 2 a Details of encumbrances concerned to Finance1 Details of encumbrances.pdf · uploaded 31 Jan 2024Source
  • 1 b Details of encumbrances concerned to Legal1 Details of encumbrances.pdf · uploaded 31 Jan 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDEVENDRA RATHI - DISCLOSURE.pdf · uploaded 2 Feb 2024Source
  • 2 Disclosure of Interest in Other Real Estate OrganizationsKAMLESH KHATOD - DISCLOSURE.pdf · uploaded 2 Feb 2024Source
  • 3 Disclosure of Interest in Other Real Estate OrganizationsNITIN MALPANI - DISCLOSURE.pdf · uploaded 2 Feb 2024Source
  • 4 Disclosure of Interest in Other Real Estate OrganizationsRISHIKESH BAHETI - DISCLOSURE.pdf · uploaded 2 Feb 2024Source
  • 5 Disclosure of Interest in Other Real Estate OrganizationsSANJAY MAHESHWARI - DISCLOSURE.pdf · uploaded 2 Feb 2024Source
  • 6 Disclosure of Interest in Other Real Estate OrganizationsSHRIKANT MANDHANA - DISCLOSURE.pdf · uploaded 2 Feb 2024Source
  • 1 Proforma of Agreement for saleAGREEMENT TO SELL.pdf · uploaded 2 Feb 2024Source
  • 2 Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 2 Feb 2024Source
  • 1 Deviation Report with respect to Allotment letterDEVIATION REPORT OF ALLOTMENT LETTER.pdf · uploaded 2 Feb 2024Source
  • 1 Deviation Report with respect to model copy of AgreementDEVIATION REPORT OF ATS.pdf · uploaded 2 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Anand Builder Arch Certificate.pdf · uploaded 7 May 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Anand Builder Engg Certificate.pdf · uploaded 7 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Anand Builder Engg Certificate Form 2A.pdf · uploaded 7 May 2024Source
  • 5 Disclosure of sold/ booked inventoryDiscloser Of Sold Inventry Anand Builders.pdf · uploaded 7 May 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate ( Form 3 ) - Anand Builders.pdf · uploaded 7 May 2024Source
  • 2 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION OF SEPARATE BANK ACCOUNT-Felicia Wing A.pdf · uploaded 7 May 2024Source
  • 2 Copy of Layout Approval (in case of layout)1-10.pdf · uploaded 15 May 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Felicia Wing A final.pdf · uploaded 18 Jun 2024Source
  • 3 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDECLARATION ABOUT SEPARATE BANK ACCOUNT.pdf · uploaded 18 Jun 2024Source
  • 6 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD INVENTORY_Felicia Wing A_ OK.pdf · uploaded 2 Jul 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)A Builders Form 5 2023-24.pdf · uploaded 10 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)A Builders Form 5 2023-24.pdf · uploaded 10 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Felicia Arch Certificate.pdf · uploaded 20 Jan 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Anand Builders 30 September.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate_Felicia A Wing.pdf · uploaded 20 Jan 2025Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Felicia Wing A.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Felicia Engg Certificate.pdf · uploaded 20 Jan 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engg Certificate Felicia September 30.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDISCLOSURE OF SOLD INVENTORY Felicia A wing.pdf · uploaded 20 Jan 2025Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of sold Inventry Felicia Wing A.pdf · uploaded 20 Jan 2025Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Anand Builders Arch Certificate 31 December 2024.pdf · uploaded 25 Jan 2025Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Felicia CA Certificate Dec 2024.pdf · uploaded 25 Jan 2025Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Anand Builders Engg Certificate Dec 2024.pdf · uploaded 25 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate Anand Builders 31 march 2025.pdf · uploaded 21 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate Anand Builders March 2025.pdf · uploaded 21 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Anand Builders Engg Certificate March 2025.pdf · uploaded 21 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryFelicia Sold Unsold Inventry Dec 2024.pdf · uploaded 21 Apr 2025Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Sold Unsold Inventry Felicia March 2025.pdf · uploaded 21 Apr 2025Source
  • Form 1Architect Certificate Anand Builders 31 march 2025.pdf · uploaded 27 May 2025Source
  • Form 2Anand Builders Engg Certificate March 2025.pdf · uploaded 27 May 2025Source
  • Form 3CA Certificate Anand Builders March 2025.pdf · uploaded 27 May 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Sold Unsold Inventry Felicia March 2025.pdf · uploaded 27 May 2025Source
  • Withdrawal Update Form 1Anand Builders Arch Certificate June 2025.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 1Anand Builders Arch Certificate June 2025.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 2883f92a6-df2a-43ae-9e65-cdf56596d63a.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 2Anand Builders Engg Certificate June 2025.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 3CA certificate (Form 3)_FELICIA WING A_.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 3CA certificate (Form 3)_FELICIA WING A_.pdf · uploaded 1 Aug 2025Source
  • Withdrawal Update Form 1Arch Certificate.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 2Engineering Certificate.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 3CA Certificate.pdf · uploaded 6 Nov 2025Source
  • Form 5 (FY 2024-2025)Felicia Audit Report 2024-25.pdf · uploaded 19 Nov 2025Source
  • Withdrawal Update Form 1Architect Certificate Felicia Form 1.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 2Engineer Certificate Felicia Form 2.pdf · uploaded 20 Jan 2026Source
  • Withdrawal Update Form 3CA Certificate Felicia Form3.pdf · uploaded 20 Jan 2026Source
  • Occupational CertificateFULL COMPLETION CERTIFICATE.pdf · uploaded 16 Mar 2026Source
  • Occupational CertificateMail CC Verification screenshot.pdf · uploaded 16 Mar 2026Source
  • Form 2A (FY 2024-2025)Felicia_FY_2024-25.pdf · uploaded 30 Apr 2026Source
  • Form 2A (FY 2025-2026)Felicia_FY_2025-26.pdf · uploaded 30 Apr 2026Source
  • Form 5 (FY 2025-2026)Felicia F Y 2025-26 Form F.pdf · uploaded 30 Sep 2026Source

Technical

  • DocumentLayout.pdf · uploaded 8 Jan 2021Source
  • DocumentPlan 1.pdf · uploaded 8 Jan 2021Source
  • DocumentPlan 2.pdf · uploaded 8 Jan 2021Source
  • DocumentPlan 3.pdf · uploaded 8 Jan 2021Source
  • DocumentPlan 4.pdf · uploaded 8 Jan 2021Source
  • DocumentPlan 5.pdf · uploaded 8 Jan 2021Source
  • DocumentPlan 6.pdf · uploaded 8 Jan 2021Source
  • DocumentPlan 7.pdf · uploaded 8 Jan 2021Source
  • Document1-10.pdf · uploaded 13 Dec 2023Source
  • Document2-10.pdf · uploaded 13 Dec 2023Source
  • Document3-10.pdf · uploaded 13 Dec 2023Source
  • Document4-10.pdf · uploaded 13 Dec 2023Source
  • Document5-10.pdf · uploaded 13 Dec 2023Source
  • Document6-10.pdf · uploaded 13 Dec 2023Source
  • Document7-10.pdf · uploaded 13 Dec 2023Source
  • Document8-10.pdf · uploaded 13 Dec 2023Source
  • Document9-10.pdf · uploaded 13 Dec 2023Source
  • Document10-10.pdf · uploaded 13 Dec 2023Source
  • Document1-10.pdf · uploaded 15 May 2024Source
  • Annexure-A as per order 50/2024Annexure A Order 50.pdf · uploaded 23 Sep 2024Source

Technical (Architect)

  • DocumentFelicia Arch Certificate.pdf · uploaded 20 Jan 2025Source
  • DocumentArchitect Certificate Anand Builders 30 September.pdf · uploaded 20 Jan 2025Source
  • DocumentAnand Builders Arch Certificate 31 December 2024.pdf · uploaded 25 Jan 2025Source
  • DocumentArchitect Certificate Anand Builders 31 march 2025.pdf · uploaded 21 Apr 2025Source
  • DocumentArchitect Certificate Felicia Form 1.pdf · uploaded 20 Jan 2026Source

Technical (Engineer)

  • DocumentFelicia Engg Certificate.pdf · uploaded 20 Jan 2025Source
  • DocumentEngg Certificate Felicia September 30.pdf · uploaded 20 Jan 2025Source
  • DocumentAnand Builders Engg Certificate Dec 2024.pdf · uploaded 25 Jan 2025Source
  • DocumentAnand Builders Engg Certificate March 2025.pdf · uploaded 21 Apr 2025Source
  • DocumentEngineer Certificate Felicia Form 2.pdf · uploaded 20 Jan 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Hadapsar, Haveli taluka

Survey, CTS, gat or plot numbers

50/10/11/2/1S. No.50/10/11/1

Boundaries

North
Adj S No 54
South
Adj S No 54
East
Amenity Space
West
Adj Wing B

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectParvez Maheboob Jamadar—
Chartered accountantPushpak Badrinarayanji Mundada—
Chartered accountantSunil Shamrao Nimbalkar—
EngineerNilesh Vijay Gund—
EngineerSwanpnil Raut—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology