Skip to content

Tower 3 · Avinea Phase 1

Hadapsar · RERA P52100079047

IDBLD_04435028 floorsExtended 4 mo
28Sanctioned habitable floorsregistration certificate
30 Apr 2029Revised completionpromised 31 Dec 2028
25 of 86Units bookedMahaRERA project page

Floors

28 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100079047 · registered 31 Jan 2025
Promised completion
31 Dec 2028
Revised completion
30 Apr 2029
Sanctioned habitable floors
28
ProjectId
53,780
ProjectName
AVINEA PHASE 1
TotalUnitCount
161
ProjectBuildingId
1,75,063
BuildingNameNumber
Tower 3
FsiWithSanctionSqmts
35
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
161
ProjectRegistartionNo
P52100079047
ProjectBuildingWingsId
1,78,520
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Tower 3
NoOfBuildingWingFloorProposed
35
NoOfBuildingWingFloorHabitable
28
NoOfBuildingWingFloorSanctioned
35

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
3BHK106.3 m² (1,144 sq.ft)158
3BHK106.5 m² (1,147 sq.ft)154
3BHK107.1 m² (1,152 sq.ft)5211
4BHK153.8 m² (1,655 sq.ft)42
Total8625
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology