Building 56 · addressOne
Gahunje · RERA P52100018855
IDBLD_0434355 floorsExtended 12 mo
5Sanctioned habitable floorsregistration certificate
29 Dec 2024Revised completionpromised 30 Dec 2023
19 of 19Units bookedMahaRERA project page
Floors
5 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100018855 · registered 6 Dec 2018
- Promised completion
- 30 Dec 2023
- Revised completion
- 29 Dec 2024
- Sanctioned habitable floors
- 5
- ProjectId
- 21,410
- ProjectName
- addressOne - Phase 5
- TotalUnitCount
- 0
- ProjectBuildingId
- 1,83,640
- BuildingNameNumber
- Building 56
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100018855
- ProjectBuildingWingsId
- 1,88,214
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- Building 56
- NoOfBuildingWingFloorProposed
- 5
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 5
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK Type I | 49.4 m² (532 sq.ft) | 2 | 2 |
| 2BHK Type II | 43.5 m² (469 sq.ft) | 16 | 16 |
| 3BHK | 87.6 m² (943 sq.ft) | 1 | 1 |
| Total | 19 | 19 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology