addressOne
Completion date passedGahunje, Pune 412101 |Promoter: Peninsula Land Limited
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 30 Jun 2026
P52100018788The latest completion date on record passed 4 months ago.
- Registered
- 5 Dec 2018
- Promised
- 30 Jun 2026
Completion pushed back 1 year
P52100018855The latest completion date on record passed 1 year and 10 months ago.
- Registered
- 6 Dec 2018
- Promised
- 30 Dec 2023
- Revised
- 29 Dec 2024
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100018788 | 5 Dec 2018 | 30 Jun 2026 | — | Peninsula Land Limited | Project page |
| P52100018855 | 6 Dec 2018 | 30 Dec 2023 | 29 Dec 2024 | Peninsula Land Limited | Project page |
Documents
3 documents held by Deedo
Registration certificates
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Gahunje
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.