Varad Complex

Certificate Signed

Dhayari (Part), Pune 411041 |Promoter: Suprabhat Constructions

26 Apr 2021Registered with MahaRERA
28 Feb 2028Promised completion
28 Jun 2028Revised completionPushed back 4 months
4Buildings
92Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
4
Unit types
Amenity space, 1BHK, 2BHK92 units in all
Address
Cts No 799 And Survey No 5/5, 5/7/4 And 5/7/5, Dhayari, PunePIN 411041
Designated bank account
76
Developed in phases
Yes

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
26 Apr 2021
Promised
28 Feb 2028
Revised
28 Jun 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002910526 Apr 202128 Feb 202828 Jun 2028Suprabhat ConstructionsProject page

4 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Amenity Building44
Building A Wing A And B432
Building B432
Building C424

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 92 units booked (0%), as the promoter reported to MahaRERA

Amenity space · 4 units1BHK · 68 units2BHK · 20 units
BuildingTypeCarpet areaUnitsBooked
Amenity BuildingAmenity space161 sq m · 1,733 sq ft40
Building A Wing A And B1BHK37.93 sq m · 408 sq ft80
Building A Wing A And B1BHK38.74 sq m · 417 sq ft80
Building A Wing A And B1BHK39.34 sq m · 423 sq ft160
Building B1BHK38 sq m · 409 sq ft160
Building B2BHK48.64 sq m · 524 sq ft160
Building C1BHK41.23 sq m · 444 sq ft40
Building C1BHK41.37 sq m · 445 sq ft40
Show all 12 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Building C1BHK41.54 sq m · 447 sq ft40
Building C1BHK41.61 sq m · 448 sq ft40
Building C1BHK41.69 sq m · 449 sq ft40
Building C2BHK53.17 sq m · 572 sq ft40

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 132 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardFirm PAN.pdf · uploaded 12 Apr 2021Source
  • PAN CardPAN CARD - SUPRABHAT CUNSTRUCTIONS.pdf · uploaded 22 Oct 2024Source

Legal

  • Legal Title reportugam search report.pdf · uploaded 12 Apr 2021Source
  • Declaration Form BForm B Promoter.pdf · uploaded 15 Apr 2021Source
  • Declaration Form BForm B (1).pdf · uploaded 22 Oct 2024Source
  • Declaration Form BLegal Title Report.pdf · uploaded 9 Jun 2026Source
  • Declaration Form BDevelopers Form B.pdf · uploaded 9 Jun 2026Source
Show all 133 documentsShow fewer documents

Migrated

  • 1 PAN CardFirm PAN.pdf · uploaded 12 Apr 2021Source
  • 1 Copy of the legal title reportugam search report.pdf · uploaded 12 Apr 2021Source
  • 1 Copy of Layout Approval (in case of layout)Layout Approval.pdf · uploaded 12 Apr 2021Source
  • 1 Building Plan Approval / NA Order for plotted developmentLayout Approval.pdf · uploaded 12 Apr 2021Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate_compressed.pdf · uploaded 12 Apr 2021Source
  • 1 Proforma of Allotment letterAgreement to sell.pdf · uploaded 12 Apr 2021Source
  • 1 Details of encumbrancesugam search report.pdf · uploaded 15 Apr 2021Source
  • 1 Declaration in FORM BForm B Promoter.pdf · uploaded 15 Apr 2021Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 21 Apr 2021Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)10 Form1 sep 23.pdf · uploaded 10 Oct 2024Source
  • 14 Architect’s Certificate of Percentage of Completion of Work (Form 1)14 Form1 sep 24.pdf · uploaded 10 Oct 2024Source
  • 13 Architect’s Certificate of Percentage of Completion of Work (Form 1)13 Form1 jun 24.pdf · uploaded 10 Oct 2024Source
  • 12 Architect’s Certificate of Percentage of Completion of Work (Form 1)12 Form1 mar 24.pdf · uploaded 10 Oct 2024Source
  • 11 Architect’s Certificate of Percentage of Completion of Work (Form 1)11 Form1 dec 23.pdf · uploaded 10 Oct 2024Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)09 Form1 jun 23.pdf · uploaded 10 Oct 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)08 Form1 mar 23.pdf · uploaded 10 Oct 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)07 Form1 dec 22.pdf · uploaded 10 Oct 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)06 Form1 sep 22.pdf · uploaded 10 Oct 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)05 Form1 jun 22.pdf · uploaded 10 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)04 Form1 mar 22.pdf · uploaded 10 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)03 Form1 dec 21.pdf · uploaded 10 Oct 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)02 Form1 sep 21.pdf · uploaded 10 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)01 Form1 Jun 21.pdf · uploaded 10 Oct 2024Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)11 dec 23.pdf · uploaded 10 Oct 2024Source
  • 12 CA Certificate on Project Cost & Fund withdrawal (Form 3)13 jun 24.pdf · uploaded 10 Oct 2024Source
  • 11 CA Certificate on Project Cost & Fund withdrawal (Form 3)12 mar 24.pdf · uploaded 10 Oct 2024Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)10 sep 23.pdf · uploaded 10 Oct 2024Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)9 jun 23.pdf · uploaded 10 Oct 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)7 dec 22.pdf · uploaded 10 Oct 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)6 sep 22.pdf · uploaded 10 Oct 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)4 mar 22.pdf · uploaded 10 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)3 dec 21.pdf · uploaded 10 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)2 sep 21.pdf · uploaded 10 Oct 2024Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)1 jun 21.pdf · uploaded 10 Oct 2024Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)8 mar 23.pdf · uploaded 10 Oct 2024Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)8 march 23.pdf · uploaded 10 Oct 2024Source
  • 14 Engineer’s Certificate on Cost Incurred on Project (Form 2)13 June 2024.pdf · uploaded 10 Oct 2024Source
  • 13 Engineer’s Certificate on Cost Incurred on Project (Form 2)13 June 2024.pdf · uploaded 10 Oct 2024Source
  • 12 Engineer’s Certificate on Cost Incurred on Project (Form 2)12 march 24.pdf · uploaded 10 Oct 2024Source
  • 11 Engineer’s Certificate on Cost Incurred on Project (Form 2)11 Dec 23.pdf · uploaded 10 Oct 2024Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)10 sept 23.pdf · uploaded 10 Oct 2024Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)9 june23.pdf · uploaded 10 Oct 2024Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)7 Dec 22.pdf · uploaded 10 Oct 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)6 sept 22.pdf · uploaded 10 Oct 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)5 june22.pdf · uploaded 10 Oct 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)4 march 22.pdf · uploaded 10 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)3 Dec 21.pdf · uploaded 10 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)2 sept 21.pdf · uploaded 10 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)1 june21.pdf · uploaded 10 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Signed Form-5 Ugam Reality LLP 21-22 (1).pdf · uploaded 10 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)Signed Form-5 Ugam Reality LLP 22-23 (1).pdf · uploaded 10 Oct 2024Source
  • 1 PAN CardPAN CARD - SUPRABHAT CUNSTRUCTIONS.pdf · uploaded 22 Oct 2024Source
  • 1 Declaration in FORM BForm B (1).pdf · uploaded 22 Oct 2024Source
  • 13 CA Certificate on Project Cost & Fund withdrawal (Form 3)suprabhat constructions ca certificate sept 24_compressed.pdf · uploaded 22 Oct 2024Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 22 Oct 2024Source
  • 1 Building Plan Approval / NA Order for plotted developmentN A Order.pdf · uploaded 22 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryUgam -Sold Booking Inventory.pdf · uploaded 22 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryUgam -Sold Booking Inventory.pdf · uploaded 22 Oct 2024Source
  • 15 Engineer’s Certificate on Cost Incurred on Project (Form 2)14 Sep 2024.pdf · uploaded 6 Nov 2024Source
  • Withdrawal Update Form 1FM_1_25_26.PDF · uploaded 5 Jun 2026Source
  • Withdrawal Update Form 2FM_2_25_26June_25.pdf · uploaded 5 Jun 2026Source
  • Withdrawal Update Form 3FORM 3.pdf · uploaded 5 Jun 2026Source
  • Withdrawal Update Form 1FM_2_25_26.pdf · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 1FM_1_25_26.PDF · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 1March 26_05062026143017.PDF · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 2FM_2_25_26_Sep_25.pdf · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 2FM_2_25_26_Dec_25.pdf · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 2FM_2_25_26_March_26.pdf · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 3FM_3_25_26.PDF · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 3FM_3_25_26.PDF · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 3FM_3_25_26.PDF · uploaded 6 Jun 2026Source
  • Form 2A (FY 2025-2026)Form 2A FY-2025-2026 (1).PDF · uploaded 6 Jun 2026Source
  • Form 5 (FY 2023-2024)Audit 23_24_05062026145836.PDF · uploaded 6 Jun 2026Source
  • Form 5 (FY 2024-2025)Audit 24_25_05062026145814.PDF · uploaded 6 Jun 2026Source
  • Withdrawal Update Form 1March 26_05062026143017.PDF · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 2FM_2_25_26_March_26.pdf · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 3Form 3.PDF · uploaded 9 Jun 2026Source
  • Withdrawal Update Form 1Architect Certificate_VARAD COMPLEX_ For Q1 FY26-27.pdf · uploaded 7 Aug 2026Source
  • Withdrawal Update Form 2Engineer Certificate_VARAD COMPLEX_For Q1 FY26-27.pdf · uploaded 7 Aug 2026Source
  • Withdrawal Update Form 3Form 3_VARAD COMPLEX _For Q1 FY26-27.pdf · uploaded 7 Aug 2026Source

Technical

  • DocumentLayout Approval.pdf · uploaded 12 Apr 2021Source
  • DocumentLayout Approval.pdf · uploaded 12 Apr 2021Source
  • DocumentN A Order.pdf · uploaded 22 Oct 2024Source
  • DocumentPlan 01.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 01.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 02.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 03.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 04.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 05.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 06.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 07.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 08.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 09.pdf · uploaded 9 Jun 2026Source
  • DocumentPlan 10.pdf · uploaded 9 Jun 2026Source

Technical (Architect)

  • Document01 Form1 Jun 21.pdf · uploaded 10 Oct 2024Source
  • Document02 Form1 sep 21.pdf · uploaded 10 Oct 2024Source
  • Document03 Form1 dec 21.pdf · uploaded 10 Oct 2024Source
  • Document04 Form1 mar 22.pdf · uploaded 10 Oct 2024Source
  • Document05 Form1 jun 22.pdf · uploaded 10 Oct 2024Source
  • Document06 Form1 sep 22.pdf · uploaded 10 Oct 2024Source
  • Document07 Form1 dec 22.pdf · uploaded 10 Oct 2024Source
  • Document08 Form1 mar 23.pdf · uploaded 10 Oct 2024Source
  • Document09 Form1 jun 23.pdf · uploaded 10 Oct 2024Source
  • Document10 Form1 sep 23.pdf · uploaded 10 Oct 2024Source
  • Document11 Form1 dec 23.pdf · uploaded 10 Oct 2024Source
  • Document12 Form1 mar 24.pdf · uploaded 10 Oct 2024Source
  • Document13 Form1 jun 24.pdf · uploaded 10 Oct 2024Source
  • Document14 Form1 sep 24.pdf · uploaded 10 Oct 2024Source
  • DocumentArchitect Certificate_VARAD COMPLEX_ For Q1 FY26-27.pdf · uploaded 7 Aug 2026Source

Technical (Engineer)

  • Document1 june21.pdf · uploaded 10 Oct 2024Source
  • Document2 sept 21.pdf · uploaded 10 Oct 2024Source
  • Document3 Dec 21.pdf · uploaded 10 Oct 2024Source
  • Document4 march 22.pdf · uploaded 10 Oct 2024Source
  • Document5 june22.pdf · uploaded 10 Oct 2024Source
  • Document6 sept 22.pdf · uploaded 10 Oct 2024Source
  • Document7 Dec 22.pdf · uploaded 10 Oct 2024Source
  • Document8 march 23.pdf · uploaded 10 Oct 2024Source
  • Document9 june23.pdf · uploaded 10 Oct 2024Source
  • Document10 sept 23.pdf · uploaded 10 Oct 2024Source
  • Document11 Dec 23.pdf · uploaded 10 Oct 2024Source
  • Document12 march 24.pdf · uploaded 10 Oct 2024Source
  • Document13 June 2024.pdf · uploaded 10 Oct 2024Source
  • Document13 June 2024.pdf · uploaded 10 Oct 2024Source
  • Document14 Sep 2024.pdf · uploaded 6 Nov 2024Source
  • DocumentEngineer Certificate_VARAD COMPLEX_For Q1 FY26-27.pdf · uploaded 7 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Dhayari (Part), Haveli taluka

Survey, CTS, gat or plot numbers

5/7/45/7/5Survey No. 5/5

Boundaries

North
By Road And Property Of Nivruti Benkar
South
By Property Of Dnyanoba Kisan Benkar
East
S No 5-6 S No 5-8
West
S No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectOmkar Deorukhakar—
ArchitectTodkari Associates—
Chartered accountantCa Vaibhav Modi—
Chartered accountantNehali & Co—
Chartered accountantPravin Pise—
Chartered accountantVaibhav Bhise—
EngineerNathsinha Yuvraj Chavan—
EngineerRAHUL BODKE Kartik Parekh—

Source: MahaRERA project page. Contact details are not shown.