Building B1 · Park View Phase 2
Dhayari (Part) · RERA P52100016922
IDBLD_03472020 floorsPromised date passed
20Sanctioned habitable floorsregistration certificate
30 Dec 2024Revised completionpromised 30 Dec 2024
66 of 67Units bookedMahaRERA project page
Floors
20 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100016922 · registered 22 Jun 2018
- Promised completion
- 30 Dec 2024
- Revised completion
- 30 Dec 2024
- Sanctioned habitable floors
- 20
- ProjectId
- 20,723
- ProjectName
- PARK VIEW PHASE 2
- TotalUnitCount
- 0
- ProjectBuildingId
- 52,029
- BuildingNameNumber
- BUILDING B1
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P52100016922
- ProjectBuildingWingsId
- 52,029
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- BUILDING B1
- NoOfBuildingWingFloorProposed
- 20
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 20
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2 BHK | 58.7 m² (631 sq.ft) | 32 | 31 |
| 3 BHK | 77.2 m² (831 sq.ft) | 35 | 35 |
| Total | 67 | 66 |
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology