IDBLD_02970115 floorsPromised date passed
15Sanctioned habitable floorsregistration certificate
30 Apr 2022Revised completionpromised 30 Apr 2022
15 of 60Units bookedMahaRERA project page

Floors

15 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P52100005152 · registered 10 Aug 2017
Promised completion
30 Apr 2022
Revised completion
30 Apr 2022
Sanctioned habitable floors
15
ProjectId
9,276
ProjectName
DSK NABHANGAN
TotalUnitCount
0
ProjectBuildingId
47,352
BuildingNameNumber
E
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P52100005152
ProjectBuildingWingsId
47,352
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
E
NoOfBuildingWingFloorProposed
15
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
15

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK61.6 m² (663 sq.ft)61
2BHK61.7 m² (664 sq.ft)60
2BHK61.9 m² (666 sq.ft)60
2BHK61.9 m² (667 sq.ft)60
2BHK63.7 m² (686 sq.ft)64
2BHK64 m² (689 sq.ft)61
3BHK77.9 m² (838 sq.ft)62
3BHK78.2 m² (841 sq.ft)62
3BHK83 m² (894 sq.ft)63
3BHK83.7 m² (901 sq.ft)62
Total6015