Basil Park C and D Wing
Certificate SignedBhosari, Pune 411039 |Promoter: M/s Yogesh Enterprises
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 2
- Unit types
- 1BHK, 2BHK, Shop81 units in all
- Address
- Survey No-222/5B, 221/2, Dighi Road, BhosariPIN 411039
- Designated bank account
- 171
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 2 years and 3 months
The latest completion date on record passed 4 years and 7 months ago.
- Registered
- 31 Aug 2017
- Promised
- 31 Dec 2019
- Revised
- 30 Mar 2022
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52100011415 | 31 Aug 2017 | 31 Dec 2019 | 30 Mar 2022 | M/s Yogesh Enterprises | Project page |
2 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| C | 8 | 35 |
| D | 8 | 46 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
72 of 81 units booked (89%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| C | 1BHK | 43.09 sq m · 464 sq ft | 5 | 5 |
| C | 1BHK | 46.51 sq m · 501 sq ft | 3 | 3 |
| C | 1BHK | 46.71 sq m · 503 sq ft | 3 | 3 |
| C | 2BHK | 60.54 sq m · 652 sq ft | 3 | 3 |
| C | 2BHK | 61 sq m · 657 sq ft | 3 | 3 |
| C | 2BHK | 61.9 sq m · 666 sq ft | 3 | 3 |
| C | 2BHK | 62.95 sq m · 678 sq ft | 3 | 3 |
| C | 2BHK | 65.85 sq m · 709 sq ft | 3 | 3 |
Show all 23 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| C | 2BHK | 65.91 sq m · 709 sq ft | 3 | 3 |
| C | 2BHK | 66.13 sq m · 712 sq ft | 3 | 3 |
| C | 2BHK | 66.19 sq m · 712 sq ft | 3 | 3 |
| D | 1BHK | 43.39 sq m · 467 sq ft | 7 | 7 |
| D | 1BHK | 44.03 sq m · 474 sq ft | 6 | 6 |
| D | 1BHK | 44.52 sq m · 479 sq ft | 14 | 12 |
| D | 1BHK | 44.87 sq m · 483 sq ft | 4 | 2 |
| D | 1BHK | 45.94 sq m · 494 sq ft | 2 | 2 |
| D | 1BHK | 54.88 sq m · 591 sq ft | 1 | 0 |
| D | 2BHK | 65.14 sq m · 701 sq ft | 5 | 5 |
| D | 2BHK | 77.68 sq m · 836 sq ft | 1 | 1 |
| D | Shop | 17.19 sq m · 185 sq ft | 3 | 0 |
| D | Shop | 18.77 sq m · 202 sq ft | 1 | 1 |
| D | Shop | 18.95 sq m · 204 sq ft | 1 | 1 |
| D | Shop | 14.86 sq m · 160 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 67 filings listed on MahaRERA's project page
Finance
- PAN CardYogesh Enterprises Pan Card.pdf · uploaded 27 Jul 2017Source
Legal
Show all 69 documentsShow fewer documents
Migrated
- 1 Declaration in FORM Byogeshgavali.pdf · uploaded 28 Jul 2017Source
- 1 Copy of the legal title reportsearchreport.pdf · uploaded 30 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)layout.pdf · uploaded 30 Jul 2017Source
- 1 Building Plan Approval (IOD)plan1.pdf · uploaded 30 Jul 2017Source
- 2 Building Plan Approval (IOD)plan2.pdf · uploaded 30 Jul 2017Source
- 3 Building Plan Approval (IOD)plan3.pdf · uploaded 30 Jul 2017Source
- 4 Building Plan Approval (IOD)plan4.pdf · uploaded 30 Jul 2017Source
- 5 Building Plan Approval (IOD)plan5.pdf · uploaded 30 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENTCER.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECTCERTIFICATE.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of CA (Form 3)CACERTIFICATE.pdf · uploaded 30 Jul 2017Source
- 1 Proforma of Allotment letterDRAFT.pdf · uploaded 30 Jul 2017Source
- 6 Building Plan Approval (IOD)proposedplan.pdf · uploaded 31 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)EnggCertificate.pdf · uploaded 31 Jul 2017Source
- 7 Building Plan Approval (IOD)6.pdf · uploaded 14 Mar 2018Source
- 8 Building Plan Approval (IOD)7.pdf · uploaded 14 Mar 2018Source
- 9 Building Plan Approval (IOD)8.pdf · uploaded 14 Mar 2018Source
- 10 Building Plan Approval (IOD)5.pdf · uploaded 14 Mar 2018Source
- 11 Building Plan Approval (IOD)4.pdf · uploaded 14 Mar 2018Source
- 12 Building Plan Approval (IOD)3.pdf · uploaded 14 Mar 2018Source
- 13 Building Plan Approval (IOD)2.pdf · uploaded 14 Mar 2018Source
- 14 Building Plan Approval (IOD)1.pdf · uploaded 14 Mar 2018Source
- 2 Commencement Certificates / NA Order for plotted developmentcommencement.pdf · uploaded 14 Mar 2018Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arc_certificate2.pdf · uploaded 14 Mar 2018Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engg_certificate2.pdf · uploaded 14 Mar 2018Source
- 2 Certificates of CA (Form 3)ca-certificate2.pdf · uploaded 14 Mar 2018Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)engg_sept18.pdf · uploaded 8 Oct 2018Source
- 3 Certificates of CA (Form 3)ca_cert_sept2018.pdf · uploaded 8 Oct 2018Source
- 1 Certificates of CA (Form 5)YOGESH ENTERPRISES FORM 5 P-2.pdf · uploaded 15 Oct 2018Source
- 3 Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT_.pdf · uploaded 24 Sep 2019Source
- 3 Architect’s Certificate on Completion of Project (Form 4)form4_cwing.pdf · uploaded 24 Sep 2019Source
- 1 OtherCC_CWING.pdf · uploaded 24 Sep 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Form_2A_1920.pdf · uploaded 11 Dec 2019Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompletion_cwing_1.pdf · uploaded 11 Dec 2019Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)YOGESH ENTERPRISE P-2 COM.pdf · uploaded 16 Dec 2019Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FORM2A_2021.pdf · uploaded 26 Jun 2021Source
- 1 Disclosure of sold/ booked inventoryc_wing.pdf · uploaded 26 Jun 2021Source
- 2 Disclosure of sold/ booked inventoryd_wing.pdf · uploaded 26 Jun 2021Source
- 4 Commencement Certificates / NA Order for plotted developmentcommencement_2019.pdf · uploaded 1 Jul 2021Source
- 1 Declaration about Commencement CertificateCOMMENCEMENT_DECLARATION.pdf · uploaded 1 Jul 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)form5_FY2019_2020.pdf · uploaded 5 Jul 2021Source
- 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentcompletion_dwing.pdf · uploaded 25 Jan 2022Source
- 1 Status of Formation of Legal Entity (Society/Co Op etc.)phase2_society_registration.pdf · uploaded 25 Jan 2022Source
- 4 Architect’s Certificate on Completion of Project (Form 4)Architect Certificate D-Wing .pdf · uploaded 15 Feb 2022Source
Technical
- Documentplan4.pdf · uploaded 30 Jul 2017Source
- Documentplan5.pdf · uploaded 30 Jul 2017Source
- Documentplan1.pdf · uploaded 30 Jul 2017Source
- Documentplan2.pdf · uploaded 30 Jul 2017Source
- Documentplan3.pdf · uploaded 30 Jul 2017Source
- Documentlayout.pdf · uploaded 30 Jul 2017Source
- Documentproposedplan.pdf · uploaded 31 Jul 2017Source
- Document6.pdf · uploaded 14 Mar 2018Source
- Document7.pdf · uploaded 14 Mar 2018Source
- Document8.pdf · uploaded 14 Mar 2018Source
- Document5.pdf · uploaded 14 Mar 2018Source
- Document4.pdf · uploaded 14 Mar 2018Source
- Document3.pdf · uploaded 14 Mar 2018Source
- Document2.pdf · uploaded 14 Mar 2018Source
- Document1.pdf · uploaded 14 Mar 2018Source
Technical (Architect)
- Documentarc_certificate2.pdf · uploaded 14 Mar 2018Source
Technical (Engineer)
- Documentengg_sept18.pdf · uploaded 8 Oct 2018Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Bhosari, Haveli taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Land of Vijaya Bhongale
- South
- Land of Pandit Gavali
- East
- Induban Residency
- West
- Land of Yogesh Enterprises
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Yojana Architects | — |
| Engineer | Avinash H Hole | — |
| Other | Skyline MEP Consultant | — |
Source: MahaRERA project page. Contact details are not shown.