Sai Velocity II

Certificate Signed

Bavadhan Bk, Pune 411021 |Promoter: Prakash Pandurang Chavan

5 Aug 2017Registered with MahaRERA
25 Dec 2019Promised completion
30 Dec 2027Revised completionPushed back 8 years
6Buildings
396Units registered137 booked (35%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
6
Unit types
1BHK02, 1BHK03, 1BHK04, 2BHK01, 2BHK02, 2BHK03, 2BHK04, 2BHK05, 2BHK06, 2BHK07, 2BHK08, 2BHK09, 2BHK10, 2BHK11, 2BHK12, IBHK01, Shop01, Shop02, Shop03, Shop04, Shop05, Shop06, Shop07, Shop08, Shop09, 1BHK01, 1BHK05, 1BHK06, 1BHK07, 1BHK08, Rowhouse396 units in all
Address
77 And 78PIN 411021
Designated bank account
220
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.51010, 73.76484
Sai Velocity II is at latitude 18.51010, longitude 73.76484.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 8 years

Registered
5 Aug 2017
Promised
25 Dec 2019
Revised
30 Dec 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000034105 Aug 201725 Dec 201930 Dec 2027Prakash Pandurang ChavanProject page

6 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
A Building1498
B Building1490
C Building1490
D Building1489
E Building26
F Building423

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

137 of 396 units booked (35%), as the promoter reported to MahaRERA

1BHK02 · 36 units1BHK03 · 24 units1BHK04 · 22 units2BHK01 · 14 units2BHK02 · 16 units2BHK03 · 15 units2BHK04 · 12 units2BHK05 · 12 units2BHK06 · 10 units2BHK07 · 12 units2BHK08 · 12 units2BHK09 · 10 units2BHK10 · 12 units2BHK11 · 12 units2BHK12 · 10 unitsIBHK01 · 5 unitsShop01 · 1 unitShop02 · 1 unitShop03 · 1 unitShop04 · 1 unitShop05 · 1 unitShop06 · 1 unitShop07 · 1 unitShop08 · 1 unitShop09 · 1 unit1BHK01 · 81 units1BHK05 · 12 units1BHK06 · 12 units1BHK07 · 22 units1BHK08 · 20 unitsRowhouse · 6 units
BuildingTypeCarpet areaUnitsBooked
A Building1BHK0232.78 sq m · 353 sq ft64
A Building1BHK0333.52 sq m · 361 sq ft54
A Building1BHK0433.66 sq m · 362 sq ft54
A Building2BHK0146.65 sq m · 502 sq ft51
A Building2BHK0247.15 sq m · 508 sq ft61
A Building2BHK0347.17 sq m · 508 sq ft60
A Building2BHK0448.67 sq m · 524 sq ft62
A Building2BHK0549.82 sq m · 536 sq ft62
Show all 64 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
A Building2BHK0651.36 sq m · 553 sq ft51
A Building2BHK0751.38 sq m · 553 sq ft62
A Building2BHK0851.4 sq m · 553 sq ft64
A Building2BHK0952.86 sq m · 569 sq ft53
A Building2BHK1052.89 sq m · 569 sq ft61
A Building2BHK1152.9 sq m · 569 sq ft64
A Building2BHK1253.01 sq m · 571 sq ft52
A BuildingIBHK0132.76 sq m · 353 sq ft54
A BuildingShop0116.25 sq m · 175 sq ft10
A BuildingShop0216.35 sq m · 176 sq ft10
A BuildingShop0316.8 sq m · 181 sq ft10
A BuildingShop0415.94 sq m · 172 sq ft10
A BuildingShop0515.8 sq m · 170 sq ft10
A BuildingShop0615.97 sq m · 172 sq ft10
A BuildingShop0716.77 sq m · 181 sq ft10
A BuildingShop0816.38 sq m · 176 sq ft10
A BuildingShop0916.25 sq m · 175 sq ft10
B Building1BHK0123.75 sq m · 256 sq ft367
B Building1BHK0224.38 sq m · 262 sq ft103
B Building1BHK0328.94 sq m · 312 sq ft51
B Building1BHK0429.81 sq m · 321 sq ft62
B Building1BHK0529.87 sq m · 322 sq ft63
B Building1BHK0629.9 sq m · 322 sq ft62
B Building1BHK0732.39 sq m · 349 sq ft114
B Building1BHK0832.66 sq m · 352 sq ft105
C Building1BHK0123.75 sq m · 256 sq ft367
C Building1BHK0224.38 sq m · 262 sq ft102
C Building1BHK0328.94 sq m · 312 sq ft51
C Building1BHK0429.81 sq m · 321 sq ft61
C Building1BHK0529.87 sq m · 322 sq ft62
C Building1BHK0629.9 sq m · 322 sq ft61
C Building1BHK0732.39 sq m · 349 sq ft112
C Building1BHK0832.66 sq m · 352 sq ft106
D Building1BHK0132.76 sq m · 353 sq ft53
D Building1BHK0232.78 sq m · 353 sq ft65
D Building1BHK0333.52 sq m · 361 sq ft55
D Building1BHK0433.66 sq m · 362 sq ft55
D Building2BHK0146.65 sq m · 502 sq ft51
D Building2BHK0247.15 sq m · 508 sq ft61
D Building2BHK0347.17 sq m · 508 sq ft60
D Building2BHK0448.67 sq m · 524 sq ft64
D Building2BHK0549.82 sq m · 536 sq ft63
D Building2BHK0651.36 sq m · 553 sq ft51
D Building2BHK0751.38 sq m · 553 sq ft61
D Building2BHK0851.4 sq m · 553 sq ft66
D Building2BHK0952.86 sq m · 569 sq ft53
D Building2BHK1052.89 sq m · 569 sq ft64
D Building2BHK1152.9 sq m · 569 sq ft63
D Building2BHK1253.01 sq m · 571 sq ft54
E BuildingRowhouse84.08 sq m · 905 sq ft60
F Building1BHK0129.23 sq m · 315 sq ft40
F Building1BHK0229.31 sq m · 315 sq ft40
F Building1BHK0329.37 sq m · 316 sq ft40
F Building2BHK0138.42 sq m · 414 sq ft40
F Building2BHK0238.65 sq m · 416 sq ft40
F Building2BHK0339.05 sq m · 420 sq ft30

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 54 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN CARD.pdf · uploaded 27 Jul 2017Source

Legal

  • Legal Title reportSearch Title Report.pdf · uploaded 27 Jul 2017Source
  • Declaration Form BDeclaration From B.pdf · uploaded 27 Jul 2017Source
  • OtherMaha Rera.pdf · uploaded 21 Jul 2021Source

Migrated

  • 1 PAN CardPAN CARD.pdf · uploaded 27 Jul 2017Source
  • 1 Copy of the legal title reportSearch Title Report.pdf · uploaded 27 Jul 2017Source
Show all 56 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesEncumbrances Letter.pdf · uploaded 27 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan.pdf · uploaded 27 Jul 2017Source
  • 1 Building Plan Approval (IOD)2 to 4.pdf · uploaded 27 Jul 2017Source
  • 2 Building Plan Approval (IOD)5 to 7.pdf · uploaded 27 Jul 2017Source
  • 3 Building Plan Approval (IOD)8 to 10.pdf · uploaded 27 Jul 2017Source
  • 4 Building Plan Approval (IOD)11 to 15.pdf · uploaded 27 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificates.pdf · uploaded 27 Jul 2017Source
  • 1 Declaration in FORM BDeclaration From B.pdf · uploaded 27 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect form 1 28072017.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEERS CERTIFICATE New.pdf · uploaded 28 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA FORM 3.pdf · uploaded 28 Jul 2017Source
  • 2 Certificates of CA (Form 3)CA Sold Flat.pdf · uploaded 28 Jul 2017Source
  • 3 Certificates of CA (Form 3)CA Unsold Flat Land Owner.pdf · uploaded 28 Jul 2017Source
  • 4 Certificates of CA (Form 3)CA Unsold Flat Prithvi Shelters.pdf · uploaded 28 Jul 2017Source
  • 1 Proforma of Allotment letterAgreement 28072017.pdf · uploaded 28 Jul 2017Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate_.pdf · uploaded 9 Jul 2021Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2_.pdf · uploaded 9 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)PRITHVI SHELTER RERA 2021_1.pdf · uploaded 9 Jul 2021Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)PRITHVI SHELTER RERA 2021_1.pdf · uploaded 9 Jul 2021Source
  • 1 Declaration about Commencement CertificateDeclaration.pdf · uploaded 10 Jul 2021Source
  • 1 Disclosure of sold/ booked inventorysai velocity sold unsold 1.pdf · uploaded 20 Jul 2021Source
  • 2 Disclosure of sold/ booked inventorysai velocity sold unsold 2.pdf · uploaded 20 Jul 2021Source
  • 3 Disclosure of sold/ booked inventorysai velocity sold unsold 3.pdf · uploaded 20 Jul 2021Source
  • 1 OtherMaha Rera.pdf · uploaded 21 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FROM 2A (1).pdf · uploaded 26 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Engineer Certificate.pdf · uploaded 27 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2017-18)Form 5 2017-18.pdf · uploaded 27 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 2018-19.pdf · uploaded 27 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 2019-20.pdf · uploaded 27 Jul 2021Source
  • 3 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 2020-21.pdf · uploaded 27 Jul 2021Source
  • 2 a Details of encumbrances concerned to Financeencumbrances.pdf · uploaded 29 May 2024Source
  • 1 b Details of encumbrances concerned to Legalencumbrances.pdf · uploaded 29 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Engineers Certificate.pdf · uploaded 29 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Engineers Certificate.pdf · uploaded 29 May 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Engineers Certificate.pdf · uploaded 29 May 2024Source
  • 1 CERSAI detailsclear tile.pdf · uploaded 29 May 2024Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsOther Real Estate.pdf · uploaded 29 May 2024Source
  • 1 Proforma of Agreement for saleAgreement For Sale.pdf · uploaded 29 May 2024Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameaccount details.pdf · uploaded 29 May 2024Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report.pdf · uploaded 29 May 2024Source
  • 1 Deviation Report with respect to model copy of AgreementAgreement For Sale.pdf · uploaded 29 May 2024Source

Technical

  • Document2 to 4.pdf · uploaded 27 Jul 2017Source
  • Document5 to 7.pdf · uploaded 27 Jul 2017Source
  • Document8 to 10.pdf · uploaded 27 Jul 2017Source
  • DocumentLayout Plan.pdf · uploaded 27 Jul 2017Source
  • Document11 to 15.pdf · uploaded 27 Jul 2017Source

Technical (Architect)

  • DocumentArchitect Certificate_.pdf · uploaded 9 Jul 2021Source

Technical (Engineer)

  • DocumentForm 2_.pdf · uploaded 9 Jul 2021Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Bavadhan BK, Mulshi taluka

Survey, CTS, gat or plot numbers

7778

Boundaries

North
15 M Wide Road
South
S No 77 Part
East
15 M Wide Road
West
S No 78 Part

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAjit Vishwas Thakur—
EngineerHemant Vishnu Nimbkar—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology