Oriana

Certificate Signed

Baner, Pune 411045 |Promoter: M/S.Kishor Builders Promoters And Developers

Residential / Group HousingRERAP52100002537
1 Aug 2017Registered with MahaRERA
31 Mar 2018Promised completion
1Building
16Units registered16 booked (100%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
2BHK16 units in all
Address
35/2/1/3 35/2/1/4PIN 411045
Designated bank account
28
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.27155, 72.96377
Oriana is at latitude 19.27155, longitude 72.96377.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2018

The latest completion date on record passed 8 years and 7 months ago.

Registered
1 Aug 2017
Promised
31 Mar 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000025371 Aug 201731 Mar 201831 Mar 2018M/S.Kishor Builders Promoters And DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Oriana516

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

16 of 16 units booked (100%), as the promoter reported to MahaRERA

2BHK · 16 units
TypeCarpet areaUnitsBooked
2BHK50.82 sq m · 547 sq ft44
2BHK50.94 sq m · 548 sq ft11
2BHK50.95 sq m · 548 sq ft33
2BHK51.11 sq m · 550 sq ft22
2BHK51.12 sq m · 550 sq ft22
2BHK51.41 sq m · 553 sq ft22
2BHK51.43 sq m · 554 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 35 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardKishor Builders-min.pdf · uploaded 11 Jul 2017Source

Legal

  • Legal Title reportNew Doc 2017-07-12-min.pdf · uploaded 12 Jul 2017Source
  • Declaration Form BB FORM.pdf · uploaded 12 Jul 2017Source
  • OtherOriana Complition.pdf · uploaded 13 Jul 2017Source
  • Otherproject complition certificate.pdf · uploaded 15 Mar 2018Source

Migrated

  • 1 PAN CardKishor Builders-min.pdf · uploaded 11 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentBaner Revised C C-min.pdf · uploaded 11 Jul 2017Source
Show all 36 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportNew Doc 2017-07-12-min.pdf · uploaded 12 Jul 2017Source
  • 1 Details of encumbrancesB FORM.pdf · uploaded 12 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)scan03915.pdf · uploaded 12 Jul 2017Source
  • 2 Copy of Layout Approval (in case of layout)scan03914.pdf · uploaded 12 Jul 2017Source
  • 1 Building Plan Approval (IOD)scan03915.pdf · uploaded 12 Jul 2017Source
  • 2 Building Plan Approval (IOD)scan03914.pdf · uploaded 12 Jul 2017Source
  • 1 Declaration in FORM BB FORM.pdf · uploaded 12 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Arcitectur certificate-min.pdf · uploaded 13 Jul 2017Source
  • 1 OtherOriana Complition.pdf · uploaded 13 Jul 2017Source
  • 1 Proforma of Allotment letteragreement.pdf · uploaded 18 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINER.pdf · uploaded 25 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA.pdf · uploaded 25 Jul 2017Source
  • 2 Otherproject complition certificate.pdf · uploaded 15 Mar 2018Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)New_Doc_2018-03-26_(2)[1].pdf · uploaded 28 Mar 2018Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)DEED OF DECLRATION.pdf · uploaded 25 Aug 2018Source
  • 1 Status of ConveyanceDEED OF DECLRATION.pdf · uploaded 25 Aug 2018Source
  • 1 Certificates of CA (Form 5)FORM 5.pdf · uploaded 26 Sep 2018Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLITION BANER.pdf · uploaded 13 Aug 2019Source
  • 4 Architect’s Certificate on Completion of Project (Form 4)baner complition.pdf · uploaded 30 Sep 2019Source
  • 2 Certificates of CA (Form 5)Form 5.pdf · uploaded 9 Oct 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)Annual report baner 2019.pdf · uploaded 22 Nov 2019Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Annual report baner 2019.pdf · uploaded 22 Nov 2019Source

Technical

  • Documentscan03915.pdf · uploaded 12 Jul 2017Source
  • Documentscan03914.pdf · uploaded 12 Jul 2017Source
  • Documentscan03915.pdf · uploaded 12 Jul 2017Source
  • Documentscan03914.pdf · uploaded 12 Jul 2017Source

Technical (Architect)

  • DocumentArcitectur certificate-min.pdf · uploaded 13 Jul 2017Source

Technical (Engineer)

  • DocumentNew_Doc_2018-03-26_(2)[1].pdf · uploaded 28 Mar 2018Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Baner, Haveli taluka

Survey, CTS, gat or plot numbers

35/2/1/3 35/2/1/4

Boundaries

North
9 Mtr Road
South
s n 35 part
East
open spcaes
West
plot no 1

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectDilip G Kale—
EngineerR K Randhave consultant—
OtherK L Infra—

Source: MahaRERA project page. Contact details are not shown.