Aurum Icon

Certificate Signed

Baner, Pune 411045 |Promoter: Tomaso Constructions Pvt.Ltd.

7 Jul 2025Registered with MahaRERA
31 Mar 2027Promised completion
31 Jul 2027Revised completionPushed back 4 months
1Building
6Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
—6 units in all
Address
near pancard club road, banerPIN 411045
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.55249, 73.77798
Aurum Icon is at latitude 18.55249, longitude 73.77798.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
7 Jul 2025
Promised
31 Mar 2027
Revised
31 Jul 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
PC12600025002247 Jul 202531 Mar 202731 Jul 2027Tomaso Constructions Pvt.Ltd.Project page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Aurum Icon336

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

6 units registered

— · 6 units
TypeCarpet areaUnits
——6

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 29 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardTCPL Pan.pdf · uploaded 8 May 2025Source

Legal

  • Declaration Form BformB.pdf · uploaded 5 May 2025Source
  • Othersindexii.pdf · uploaded 13 May 2025Source
  • Declaration Form BSearch and Title.pdf · uploaded 13 May 2025Source
  • Otherssale deed.pdf · uploaded 18 Jun 2025Source
  • Othersdipin parkhe.pdf · uploaded 18 Jun 2025Source
  • Othersdipin thombare.pdf · uploaded 18 Jun 2025Source
Show all 30 documentsShow fewer documents

Legal

  • Declaration Form Bsale deed.pdf · uploaded 18 Jun 2025Source

Migrated

  • Withdrawal Update Form 1Arch form 1.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 3form 3 CA.pdf · uploaded 6 Nov 2025Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 3form 3_compressed.pdf · uploaded 11 Mar 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 30 Apr 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 30 Apr 2026Source
  • Form 5 (FY 2025-2026)form5.pdf · uploaded 2 May 2026Source
  • Form 2A (FY 2025-2026)2 A 25-26.pdf · uploaded 11 May 2026Source
  • Withdrawal Update Form 1form 1.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 2form 2.pdf · uploaded 20 Jul 2026Source
  • Withdrawal Update Form 3form 3.pdf · uploaded 20 Jul 2026Source

Technical

  • Document3-3-merged_compressed_compressed-compressed.pdf · uploaded 8 May 2025Source
  • DocumentNA order_compressed.pdf · uploaded 8 May 2025Source
  • Others1-3_compressed.pdf · uploaded 8 May 2025Source
  • DocumentAnnexure A order 50.pdf · uploaded 9 May 2025Source

Technical (Architect)

  • Documentform 1.pdf · uploaded 20 Jul 2026Source

Technical (Engineer)

  • Documentform 2.pdf · uploaded 6 Nov 2025Source
  • Documentform 2.pdf · uploaded 20 Jul 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Baner, Haveli taluka

Survey, CTS, gat or plot numbers

38/1 P

Boundaries

North
road
South
road
East
road
West
building

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Chartered accountantChadrakant Nanekar—
EngineerSachin Kudale—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology