Skip to content

Ag Business Park

Certificate Signed

Baner, Pune 411005 |Promoter: A G Constructions

2 Dec 2022Registered with MahaRERA
31 Jan 2028Promised completion
31 May 2028Revised completionPushed back 4 months
1Building
7Units registered0 booked (0%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Commercial
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
Office space, Showroom7 units in all
Address
279/1 279/2 279/2/1 279/2/2 279/2/3 280/1 280/2 280/3, Baner, BanerPIN 411005
Designated bank account
154
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.55209, 73.79188
Ag Business Park is at latitude 18.55209, longitude 73.79188.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
2 Dec 2022
Promised
31 Jan 2028
Revised
31 May 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P521000479542 Dec 202231 Jan 202831 May 2028A G ConstructionsProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Ag Business Park157

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 of 7 units booked (0%), as the promoter reported to MahaRERA

Office space · 4 unitsShowroom · 3 units
TypeCarpet areaUnitsBooked
Office space1,215.98 sq m · 13,089 sq ft10
Office space1,546.64 sq m · 16,648 sq ft30
Showroom361.17 sq m · 3,888 sq ft10
Showroom371.05 sq m · 3,994 sq ft10
Showroom431.31 sq m · 4,643 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 207 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • PAN CardPAN Card-AG Constructions 07072006.pdf · uploaded 24 Oct 2022Source
  • Other – FinanceNo Encumbrance-Finance 01102022.pdf · uploaded 25 Oct 2022Source

Legal

  • Legal Title reportLegal Title Report 01102022.pdf · uploaded 24 Oct 2022Source
  • Other – LegalNo Encumbrance-Legal 01102022.pdf · uploaded 25 Oct 2022Source
  • Declaration Form BForm-B Affidavit 29072022.pdf · uploaded 25 Oct 2022Source

Migrated

  • 1 PAN CardPAN Card-AG Constructions 07072006.pdf · uploaded 24 Oct 2022Source
Show all 209 documentsShow fewer documents

Migrated

  • 1 Copy of the legal title reportLegal Title Report 01102022.pdf · uploaded 24 Oct 2022Source
  • 1 a Details of encumbrances concerned to FinanceNo Encumbrance-Legal 01102022.pdf · uploaded 24 Oct 2022Source
  • 1 b Details of encumbrances concerned to LegalNo Encumbrance-Legal 01102022.pdf · uploaded 24 Oct 2022Source
  • 1 Copy of Layout Approval (in case of layout)Sanctioned Plan 01-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 02-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 03-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 3 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 04-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 4 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 05-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 5 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 06-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 6 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 07-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 7 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 08-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 8 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 09-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate 13102022.pdf · uploaded 25 Oct 2022Source
  • 1 Declaration about Commencement CertificateDeclaration About Commencement Certificate 29072022.pdf · uploaded 25 Oct 2022Source
  • 1 Declaration in FORM BForm-B Affidavit 29072022.pdf · uploaded 25 Oct 2022Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 07072022.pdf · uploaded 25 Oct 2022Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 21102022.pdf · uploaded 25 Oct 2022Source
  • 1 CERSAI detailsCERSAI Search Report 25102022.pdf · uploaded 25 Oct 2022Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 22102022.pdf · uploaded 25 Oct 2022Source
  • 1 Proforma of Agreement for saleAgreement to Sale-Draft.pdf · uploaded 25 Oct 2022Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation Report-Agreement for Sale 01102022.pdf · uploaded 25 Oct 2022Source
  • 1 Other – LegalNo Encumbrance-Legal 01102022.pdf · uploaded 25 Oct 2022Source
  • 1 Other – FinanceNo Encumbrance-Finance 01102022.pdf · uploaded 25 Oct 2022Source
  • 1 Other – TechnicalNo Encumbrance Certificate-Other 29072022.pdf · uploaded 25 Oct 2022Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameDeclaration About Separate Bank Account 29072022.pdf · uploaded 26 Oct 2022Source
  • 1 Deviation Report with respect to Allotment letterDeviation Report-Allotment Letter 01102022.pdf · uploaded 26 Oct 2022Source
  • 1 Proforma of Allotment letterProforma Allotment Letter Draft 25112022.pdf · uploaded 17 Nov 2022Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 31122022.pdf · uploaded 24 Mar 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 30012023.pdf · uploaded 24 Mar 2023Source
  • 1 Disclosure of sold/ booked inventorySold Booked Inventory 31122022.pdf · uploaded 24 Mar 2023Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 220320223 Q3 v1.pdf · uploaded 24 Mar 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)31032023-form-5-baner-ag constructions.pdf · uploaded 4 Sep 2023Source
  • 2 a Details of encumbrances concerned to FinanceNo Encumbrance-Finance 01102022.pdf · uploaded 15 Sep 2023Source
  • 3 a Details of encumbrances concerned to FinanceNo Encumbrance-Other 29072022.pdf · uploaded 15 Sep 2023Source
  • 2 b Details of encumbrances concerned to LegalNo Encumbrance-Finance 01102022.pdf · uploaded 15 Sep 2023Source
  • 3 b Details of encumbrances concerned to LegalNo Encumbrance-Other 29072022.pdf · uploaded 15 Sep 2023Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 31032023.pdf · uploaded 15 Sep 2023Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 30062023.pdf · uploaded 15 Sep 2023Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 31032023.pdf · uploaded 15 Sep 2023Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 30062023.pdf · uploaded 15 Sep 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form-2A Quality Assurance 31032023.pdf · uploaded 15 Sep 2023Source
  • 2 CERSAI detailsCERSAI Undertaking 31082023.pdf · uploaded 15 Sep 2023Source
  • 2 Disclosure of sold/ booked inventorySold Inventory 31032023.pdf · uploaded 15 Sep 2023Source
  • 3 Disclosure of sold/ booked inventorySold Inventory 30062023.pdf · uploaded 15 Sep 2023Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 31032023_compressed.pdf · uploaded 15 Sep 2023Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 30062023_compressed.pdf · uploaded 15 Sep 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest Ajit Gaikwad 31082023.pdf · uploaded 15 Sep 2023Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 30092023.pdf · uploaded 11 Mar 2024Source
  • 4 Disclosure of sold/ booked inventorySold Unsold Inventory 30092023.pdf · uploaded 11 Mar 2024Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 31122023.pdf · uploaded 30 Mar 2024Source
  • 5 Disclosure of sold/ booked inventorySold Booked Inventory 31122023.pdf · uploaded 30 Mar 2024Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 31032024.pdf · uploaded 16 Apr 2024Source
  • 6 Disclosure of sold/ booked inventorySold Booked Inventory 31032024.pdf · uploaded 16 Apr 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form-2A Engineer Certificate 31032024.pdf · uploaded 27 Jul 2024Source
  • 7 Disclosure of sold/ booked inventorySold Booked Inventory 30062024.pdf · uploaded 27 Jul 2024Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 30062024.pdf · uploaded 29 Jul 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 30092023.pdf · uploaded 23 Oct 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 31122023.pdf · uploaded 23 Oct 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 31032024.pdf · uploaded 23 Oct 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 30062024.pdf · uploaded 23 Oct 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 30062024.pdf · uploaded 5 Nov 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 31032024.pdf · uploaded 5 Nov 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 31122023.pdf · uploaded 5 Nov 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 30092023.pdf · uploaded 5 Nov 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 30092024.pdf · uploaded 27 Nov 2024Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Engineer Certificate 30092024.pdf · uploaded 27 Nov 2024Source
  • 2 Disclosure of sold/ booked inventorySold Unsold Inventory 30092024.pdf · uploaded 27 Nov 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Form-5 RERA Audit Report FY 2023-24.pdf · uploaded 27 Nov 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 30092024.pdf · uploaded 30 Nov 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form-1 Architect Certificate 31122024.pdf · uploaded 31 Jan 2025Source
  • 1 Disclosure of sold/ booked inventorySold Booked Inventory 31122024.pdf · uploaded 31 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form-3 CA Certificate 31122024.pdf · uploaded 3 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)scan_sign_copy_Form-2 Engineer Certificate 31122024.pdf · uploaded 3 Feb 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate 04022025.pdf · uploaded 12 Mar 2025Source
  • 1 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 01-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 2 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 02-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 3 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 03-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 4 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 04-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 5 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 05-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 6 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 06-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 7 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 07-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 8 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 08-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 9 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 09-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 10 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 10-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 11 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 11-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 12 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 12-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 13 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 13-14 04022025.pdf · uploaded 12 Mar 2025Source
  • 14 Building Plan Approval / NA Order for plotted developmentSanctioned Plan 14-14 04022025.pdf · uploaded 12 Mar 2025Source
  • Form 1Form-1 Architect Certificate 30062025.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 31032025.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 31122024.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 30092024.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 30062024.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 31032024.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 31122023.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 30092023.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 30062023.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 31032023.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 31122022.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 30062025.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 31032025.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 31122024.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 30092024.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 30062024.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 31032024.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 31122023.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 30092023.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 30062023.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 31032023.pdf · uploaded 8 Aug 2025Source
  • Form 2Form-2 Engineer Certificate 21102022.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 30062025 Sign.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 31032025 Sign.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 31122024.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 30092024.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 30062024.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 31032024.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 31122023.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 30092023.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 30062023.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 31032023.pdf · uploaded 8 Aug 2025Source
  • Form 3Form-3 CA Certificate 22102022.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Certificate 30062025.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventoryInventory Certificate 31032025.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 31122024.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory 30092024.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 30062024.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 31032024.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 31122023.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 30092023.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 30062023.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 31032023.pdf · uploaded 8 Aug 2025Source
  • Disclosure of Sold and Booked InventorySold Booked Inventory 31122022.pdf · uploaded 8 Aug 2025Source
  • Form 1Form-1 Architect Certificate 30092025.pdf · uploaded 21 Feb 2026Source
  • Form 1Form-1 Architect Certificate 31122025.pdf · uploaded 21 Feb 2026Source
  • Form 2Form-2 Engineer Certificate 30092025.pdf · uploaded 21 Feb 2026Source
  • Form 2Form-2 Engineer Certificate 31122025.pdf · uploaded 21 Feb 2026Source
  • Form 3Form-3 CA Certificate 30092025.pdf · uploaded 21 Feb 2026Source
  • Form 3Form-3 CA Certificate 31122025.pdf · uploaded 21 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory-30092025.pdf · uploaded 21 Feb 2026Source
  • Disclosure of Sold and Booked InventorySold Unsold Inventory-31122025.pdf · uploaded 21 Feb 2026Source
  • Withdrawal Update Form 1Form-1 Architect Certificate 31122025.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 2Form-2 Engineer Certificate 31122025.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 3Form-3 CA Certificate 31122025 v5.pdf · uploaded 6 May 2026Source
  • Form 2A (FY 2022-2023)Form-2A Quality Assurance FY 2022-23.pdf · uploaded 6 May 2026Source
  • Form 2A (FY 2023-2024)Form-2A Quality Assurance FY 2023-24.pdf · uploaded 6 May 2026Source
  • Withdrawal Update Form 1Form-1 Architect Certificate 31122025.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 2Form-2 Engineer Certificate 31122025.pdf · uploaded 7 May 2026Source
  • Withdrawal Update Form 3Form-3 CA Certificate 31122025 v5.pdf · uploaded 7 May 2026Source
  • Form 2A (FY 2024-2025)scan-sign-copy_Form-2A Engineer Certificate_31032025.pdf · uploaded 13 May 2026Source
  • Form 2A (FY 2025-2026)scan-sign-copy_Form-2A Engineer Certificate_31032026.pdf · uploaded 13 May 2026Source
  • Form 5 (FY 2024-2025)Form-5 RERA Audit Report FY 2024-25.pdf · uploaded 13 May 2026Source
  • Form 5 (FY 2025-2026)Form-5 RERA Audit Report FY 2025-26.pdf · uploaded 13 May 2026Source

Technical

  • DocumentSanctioned Plan 01-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 02-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 03-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 04-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 05-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 06-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 07-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 08-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 09-09 13102022_compressed.pdf · uploaded 25 Oct 2022Source
  • Other – TechnicalNo Encumbrance Certificate-Other 29072022.pdf · uploaded 25 Oct 2022Source
  • DocumentSanctioned Plan 01-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 02-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 03-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 04-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 05-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 06-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 07-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 08-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 09-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 10-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 11-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 12-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 13-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanctioned Plan 14-14 04022025.pdf · uploaded 12 Mar 2025Source
  • DocumentSanction plan 1-15 01042026 Hi.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 2-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 3-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 4-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 5-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 6-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 7-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 8-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 9-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 10-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 11-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 12-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 13-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 14-15 01042026.pdf · uploaded 30 May 2026Source
  • DocumentSanction plan 15-15 01042026.pdf · uploaded 30 May 2026Source

Technical (Architect)

  • DocumentForm-1 Architect Certificate 30092024.pdf · uploaded 30 Nov 2024Source
  • DocumentForm-1 Architect Certificate 31122024.pdf · uploaded 31 Jan 2025Source
  • DocumentForm-1 Architect Certificate 31122025.pdf · uploaded 7 May 2026Source

Technical (Engineer)

  • DocumentForm-2 Engineer Certificate 30092023.pdf · uploaded 5 Nov 2024Source
  • DocumentForm-2 Engineer Certificate 31122023.pdf · uploaded 5 Nov 2024Source
  • DocumentForm-2 Engineer Certificate 31032024.pdf · uploaded 5 Nov 2024Source
  • DocumentForm-2 Engineer Certificate 30062024.pdf · uploaded 5 Nov 2024Source
  • DocumentForm-2 Engineer Certificate 30092024.pdf · uploaded 27 Nov 2024Source
  • Documentscan_sign_copy_Form-2 Engineer Certificate 31122024.pdf · uploaded 3 Feb 2025Source
  • DocumentForm-2 Engineer Certificate 31122025.pdf · uploaded 7 May 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Baner, Haveli taluka

Survey, CTS, gat or plot numbers

279/1 279/2 279/2/1 279/2/2 279/2/3 280/1 280/2 280/3

Boundaries

North
Adj Nala
South
Internal Road S No 278 P S No 277 P
East
S no 279 P
West
12 M wide D P Road S No 280 P

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
Architectprojection studio—
Chartered accountantCA Priyesh Jain—
Chartered accountantM/S bhutada mundada & co—
Chartered accountantnilesh raut—
EngineerNitin Narayan Marne—
OtherAstha Construction—
OtherG A Bhilare consultants—
Othersiddhivinayak consultant—
Otherswami consulting services—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology