Wing B · Twilight

Balewadi · RERA PM1260002501445

IDBLD_08430021 floorsExtended 4 mo
21Sanctioned habitable floorsregistration certificate
31 Jul 2029Revised completionpromised 31 Mar 2029

Floors

21 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
PM1260002501445 · registered 11 Nov 2025
Promised completion
31 Mar 2029
Revised completion
31 Jul 2029
Sanctioned habitable floors
21
ProjectId
60,103
ProjectName
TWILIGHT
TotalUnitCount
66
ProjectBuildingId
1,91,303
BuildingNameNumber
TWILIGHT
FsiWithSanctionSqmts
27
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
60
ProjectRegistartionNo
PM1260002501445
ProjectBuildingWingsId
1,96,809
BuildingWingsNameNumber
Wing B
NonResidentialUnitCount
6
AdvertisedBuildingNameNumber
TWILIGHT
NoOfBuildingWingFloorProposed
27
NoOfBuildingWingFloorHabitable
21
NoOfBuildingWingFloorSanctioned
27

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——66not published
Total66
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology