The Midas Residences

Completion due Jun 2031

Balewadi, Pune 411045 |Promoter: Selenite Properties Private Limited

27 Mar 2023Registered with MahaRERAFirst of 4 registrations
30 Jun 2031Promised completionLatest across registrations
2Buildings4 phases
72Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
4
Phases
4
Buildings
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.58167, 73.77441
The Midas Residences is at latitude 18.58167, longitude 73.77441.

Also registered as

The Midas Residences Phase 2The Midas Residences Phase 3The Midas Residences Phase 6The Midas Residences Phase 5
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2029

P52100050257
Registered
27 Mar 2023
Promised
31 Dec 2029

Completion promised for 31 Dec 2029

P52100050581
Registered
21 Apr 2023
Promised
31 Dec 2029

Completion promised for 30 Jun 2030

PR1264042601471
Registered
7 Aug 2026
Promised
30 Jun 2030

Completion promised for 30 Jun 2031

PR1264042601729
Registered
1 Sep 2026
Promised
30 Jun 2031

4 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210005025727 Mar 202331 Dec 202931 Dec 2029Selenite Properties Private LimitedProject page
P5210005058121 Apr 202331 Dec 202931 Dec 2029Selenite Properties Private LimitedProject page
PR12640426014717 Aug 202630 Jun 2030—Selenite Properties Private LimitedProject page
PR12640426017291 Sep 202630 Jun 2031—Selenite Properties Private LimitedProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsFloors with CCUnits
Building A182370
Building A8162

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Documents

6 documents held by Deedo

Extension certificates

  • Extension certificateP52100050257 · 7 May 2025ViewSource
  • Extension certificateP52100050581 · 22 May 2025ViewSource

Registration certificates

  • Registration certificateP52100050257 · 13 Aug 2026ViewSource
  • Registration certificatePR1264042601729 · 1 Sep 2026ViewSource
  • Registration certificatePR1264042601471 · 24 Sep 2026ViewSource
  • Registration certificateP52100050581 · 6 Oct 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Balewadi

Survey, CTS, gat or plot numbers

44/6/144/6/1/2/5/7/1044/6/1/2/5/7/1144/6/1/2/5/7/1244/6/1/2/5/7/1344/6/1/2/5/7/2/Plot 244/6/1/2/5/7/3/Plot 344/6/1/2/5/7/4/Plot 444/6/1/2/5/7/5/Plot 544/6/1/2/5/7/6/Plot 644/6/1/2/5/7/744/6/1/2/5/7/844/6/1/2/5/7/944/6/1(P)44/6/244/6/2(P)44/7New Sr. No. 44/6/1/2/5/7/1/Plot 1Old Sr. No. 44/5/1S. No. 44/5/1S NO 44/5/1

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology