Tower A · Pelican Phase C
Ambadvet · RERA P52100033925
IDBLD_03277811 floorsExtended 4 mo
11Sanctioned habitable floorsregistration certificate
28 Jun 2028Revised completionpromised 28 Feb 2028
123 of 175Units bookedMahaRERA project page
Floors
11 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P52100033925 · registered 14 Mar 2022
- Promised completion
- 28 Feb 2028
- Revised completion
- 28 Jun 2028
- Sanctioned habitable floors
- 11
- ProjectId
- 31,462
- ProjectName
- Pelican Phase C
- TotalUnitCount
- 175
- ProjectBuildingId
- 1,57,350
- BuildingNameNumber
- Tower A
- FsiWithSanctionSqmts
- 11
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 175
- ProjectRegistartionNo
- P52100033925
- ProjectBuildingWingsId
- 1,60,775
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- Tower A
- NoOfBuildingWingFloorProposed
- 13
- NoOfBuildingWingFloorHabitable
- 11
- NoOfBuildingWingFloorSanctioned
- 13
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2BHK | 45 m² (484 sq.ft) | 69 | 63 |
| 2BHK | 50.3 m² (542 sq.ft) | 18 | 1 |
| 3BHK | 57 m² (614 sq.ft) | 72 | 58 |
| 3BHK | 59 m² (635 sq.ft) | 16 | 1 |
| Total | 175 | 123 |