Completion date passed

Vasaivirar City (M Corp), Palghar 401208 |Promoter: S S Builders

9 Aug 2017Registered with MahaRERAFirst of 2 registrations
31 Dec 2019Promised completionLatest across registrations
30 Dec 2021Revised completion1 of 2 registrations pushed back, by up to 2 years
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
2
Phases
2

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.37348, 72.88699
SS Builders is at latitude 19.37348, longitude 72.88699.

Also registered as

Ss Builders Building No. 8SS Builders Building No.7
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years

P99000004466

The latest completion date on record passed 4 years and 10 months ago.

Registered
9 Aug 2017
Promised
31 Dec 2019
Revised
30 Dec 2021

Completion promised for 31 Dec 2019

P99000004734

The latest completion date on record passed 6 years and 10 months ago.

Registered
9 Aug 2017
Promised
31 Dec 2019

2 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000044669 Aug 201731 Dec 201930 Dec 2021S S BuildersProject page
P990000047349 Aug 201731 Dec 2019—S S BuildersProject page

Documents

3 documents held by Deedo

Registration certificates

  • Registration certificateP99000004466 · 9 Aug 2017ViewSource
  • Registration certificateP99000004734 · 9 Aug 2017ViewSource

Extension certificate

  • Extension certificateP99000004466 · 9 Sep 2021ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Vasaivirar City (M Corp)

Survey, CTS, gat or plot numbers

111112

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology