Skip to content

New Smita Chs Ltd

Certificate Signed

Vasaivirar City (M Corp), Palghar 401203 |Promoter: Gsk Builders & Developers

31 Oct 2023Registered with MahaRERA
15 May 2028Promised completion
15 Sep 2028Revised completionPushed back 4 months
1Building
54Units registered5 booked (9%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 1RK, 2BHK, Shop54 units in all
Address
S. NO 83/A, Plot. NO. 63 OF VILLAGE NILEMORE, NILEMORE ROAD, NALLASOPARAPIN 401203
Designated bank account
76
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.41797, 72.81345
New Smita Chs Ltd is at latitude 19.41797, longitude 72.81345.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
31 Oct 2023
Promised
15 May 2028
Revised
15 Sep 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900005341631 Oct 202315 May 202815 Sep 2028Gsk Builders & DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
New Samita Chs Ltd754

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

5 of 54 units booked (9%), as the promoter reported to MahaRERA

1BHK · 14 units1RK · 5 units2BHK · 21 unitsShop · 14 units
TypeCarpet areaUnitsBooked
1BHK27.31 sq m · 294 sq ft10
1BHK28.33 sq m · 305 sq ft40
1BHK28.84 sq m · 310 sq ft10
1BHK28.98 sq m · 312 sq ft70
1BHK35.99 sq m · 387 sq ft11
1RK6.84 sq m · 74 sq ft10
1RK7.79 sq m · 84 sq ft10
1RK8.59 sq m · 92 sq ft10
Show all 24 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
1RK8.82 sq m · 95 sq ft10
1RK12.63 sq m · 136 sq ft10
2BHK39.51 sq m · 425 sq ft144
2BHK49.1 sq m · 529 sq ft70
Shop3.96 sq m · 43 sq ft10
Shop4.38 sq m · 47 sq ft10
Shop4.42 sq m · 48 sq ft10
Shop4.63 sq m · 50 sq ft10
Shop4.82 sq m · 52 sq ft10
Shop5 sq m · 54 sq ft10
Shop5.48 sq m · 59 sq ft10
Shop5.54 sq m · 60 sq ft30
Shop8.24 sq m · 89 sq ft10
Shop8.26 sq m · 89 sq ft10
Shop10.83 sq m · 117 sq ft10
Shop13.51 sq m · 145 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 66 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN Cardgsk pancard.pdf · uploaded 7 Aug 2023Source

Legal

  • Declaration Form BForm B GSK.pdf · uploaded 7 Aug 2023Source
  • Legal Title reportTITAL REPORT.pdf · uploaded 6 Sep 2023Source

Migrated

  • 1 PAN Cardgsk pancard.pdf · uploaded 7 Aug 2023Source
  • 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 7 Aug 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentplan 1.pdf · uploaded 7 Aug 2023Source
  • 2 Building Plan Approval / NA Order for plotted developmentPlan 2.pdf · uploaded 7 Aug 2023Source
Show all 67 documentsShow fewer documents

Migrated

  • 1 Declaration in FORM BForm B GSK.pdf · uploaded 7 Aug 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 7 Aug 2023Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 7 Aug 2023Source
  • 1 CERSAI detailsCERSAI_Search_Report.pdf · uploaded 7 Aug 2023Source
  • 1 a Details of encumbrances concerned to FinanceDeclaration of legal .pdf · uploaded 25 Aug 2023Source
  • 1 b Details of encumbrances concerned to LegalDeclaration of legal .pdf · uploaded 25 Aug 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC_compressed.pdf · uploaded 25 Aug 2023Source
  • 1 Declaration about Commencement CertificateDeclaration of CC.pdf · uploaded 25 Aug 2023Source
  • 1 Proforma of Allotment letterDraft Allotment Letter.pdf · uploaded 25 Aug 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the samedeclaration of Bank .pdf · uploaded 25 Aug 2023Source
  • 1 Deviation Report with respect to Allotment letterdeclaration of allotment letter .pdf · uploaded 25 Aug 2023Source
  • 1 Deviation Report with respect to model copy of Agreementmodel copy of agreement .pdf · uploaded 25 Aug 2023Source
  • 2 a Details of encumbrances concerned to FinanceDecleration of Finance.pdf · uploaded 30 Aug 2023Source
  • 2 b Details of encumbrances concerned to LegalDecleration of Finance.pdf · uploaded 30 Aug 2023Source
  • 1 Proforma of Agreement for saleModel_AFS.pdf · uploaded 30 Aug 2023Source
  • 1 Copy of the legal title reportTITAL REPORT.pdf · uploaded 6 Sep 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 6 Sep 2023Source
  • 2 CERSAI detailsUndertaking of Cersai.pdf · uploaded 17 Oct 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsDisclosure of Interest in Other Real Estate Organizations.pdf · uploaded 26 Oct 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 28 May 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 28 May 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 28 May 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 NEW.pdf · uploaded 30 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 30 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 30 Oct 2024Source
  • 1 Disclosure of sold/ booked inventoryMAHARERA CIR 29.pdf · uploaded 30 Oct 2024Source
  • 1 Other – TechnicalDECLARATION LETTER.pdf · uploaded 30 Oct 2024Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)QUALITY ASSURANCE CERTIFICATE.pdf · uploaded 30 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5.pdf · uploaded 30 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 17 Feb 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 17 Feb 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2.pdf · uploaded 17 Feb 2025Source
  • Form 1FORM 1.pdf · uploaded 29 May 2025Source
  • Form 2FORM 2.pdf · uploaded 29 May 2025Source
  • Form 3FORM 3.pdf · uploaded 29 May 2025Source
  • Disclosure of Sold and Booked InventorySOLD AND UNSOLD INVENTORY.pdf · uploaded 29 May 2025Source
  • Form 5 (FY 2024-2025)FORM 5 FY 24-25.pdf · uploaded 12 Jan 2026Source
  • Form 1Form1.pdf · uploaded 25 Mar 2026Source
  • Form 2Form2.pdf · uploaded 25 Mar 2026Source
  • Form 3FORM3JUNE2025.pdf · uploaded 25 Mar 2026Source
  • Disclosure of Sold and Booked InventorySOLDUNSOLD INVENTORY DETAILS JUNE2025.pdf · uploaded 25 Mar 2026Source
  • Form 1FORM1.pdf · uploaded 25 Mar 2026Source
  • Form 2FORM2.pdf · uploaded 25 Mar 2026Source
  • Form 3FORM3-SEPTEMBER2025.pdf · uploaded 25 Mar 2026Source
  • Disclosure of Sold and Booked InventorySOLD AND UNSOLD INVENTORY DETAILS SEPT2025.pdf · uploaded 25 Mar 2026Source
  • Form 1Form1.pdf · uploaded 25 Mar 2026Source
  • Form 2Form2.pdf · uploaded 25 Mar 2026Source
  • Form 3FORM3.pdf · uploaded 25 Mar 2026Source
  • Disclosure of Sold and Booked InventorySOLDUNSOLD INVENTORY DETAILS DEC2025.pdf · uploaded 25 Mar 2026Source

Technical

  • Documentplan 1.pdf · uploaded 7 Aug 2023Source
  • DocumentPlan 2.pdf · uploaded 7 Aug 2023Source
  • Documentlayout plan.pdf · uploaded 7 Aug 2023Source
  • Other – TechnicalDECLARATION LETTER.pdf · uploaded 30 Oct 2024Source

Technical (Architect)

  • DocumentForm 1.pdf · uploaded 28 May 2024Source
  • DocumentForm 1 NEW.pdf · uploaded 30 Oct 2024Source
  • DocumentFORM 1.pdf · uploaded 17 Feb 2025Source

Technical (Engineer)

  • DocumentForm 2.pdf · uploaded 28 May 2024Source
  • DocumentFORM 2.pdf · uploaded 30 Oct 2024Source
  • DocumentFORM-2.pdf · uploaded 17 Feb 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Vasai-Virar City (M Corp), Vasai taluka

Survey, CTS, gat or plot numbers

Plot. NO. 63 OFS. NO 83/A

Boundaries

North
D P Road
South
Residential Building
East
Residential Building
West
Internal Road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectKuldeep Patil—
Chartered accountantAbdul Bari & Co—
Chartered accountantAbdul Bari Shaikh—
Chartered accountantKumar V Mhatre—
EngineerGr Consultatnts—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology