Moreshwar Niwas
Certificate SignedVasaivirar City (M Corp), Palghar 401202 |Promoter: Shriya Builders & Land Developers
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 3
- Unit types
- 1, 2, 3, 4, 5, 6, 7, Shop 1, Shop 2, Shop 3, Shop 4, Shop 5, Shop 631 units in all
- Address
- 3A/5, Sakai Nagar, Umele Hanuman AliPIN 401202
- Designated bank account
- 19
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 years and 9 months
The latest completion date on record passed 10 months ago.
- Registered
- 1 Sep 2017
- Promised
- 30 Mar 2021
- Revised
- 31 Dec 2025
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000012305 | 1 Sep 2017 | 30 Mar 2021 | 31 Dec 2025 | Shriya Builders & Land Developers | Project page |
3 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Building No 1 | 4 | 19 |
| Building No 2 | 4 | 11 |
| Bungalow | 2 | 1 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
29 of 31 units booked (94%), as the promoter reported to MahaRERA
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1 | 1 | 21.12 sq m · 227 sq ft | 1 | 1 |
| Building No 1 | 2 | 24.03 sq m · 259 sq ft | 2 | 2 |
| Building No 1 | 3 | 24.24 sq m · 261 sq ft | 3 | 3 |
| Building No 1 | 4 | 24.95 sq m · 269 sq ft | 1 | 1 |
| Building No 1 | 5 | 35.97 sq m · 387 sq ft | 2 | 2 |
| Building No 1 | 5 | 37.33 sq m · 402 sq ft | 1 | 1 |
| Building No 1 | 6 | 37.47 sq m · 403 sq ft | 2 | 2 |
| Building No 1 | 7 | 38.97 sq m · 419 sq ft | 1 | 1 |
Show all 20 unit rowsShow fewer unit rows
| Building | Type | Carpet area | Units | Booked |
|---|---|---|---|---|
| Building No 1 | Shop 1 | 8.55 sq m · 92 sq ft | 1 | 1 |
| Building No 1 | Shop 2 | 7.05 sq m · 76 sq ft | 1 | 1 |
| Building No 1 | Shop 3 | 11.4 sq m · 123 sq ft | 1 | 1 |
| Building No 1 | Shop 4 | 10.22 sq m · 110 sq ft | 1 | 1 |
| Building No 1 | Shop 5 | 8.58 sq m · 92 sq ft | 1 | 0 |
| Building No 1 | Shop 6 | 13.92 sq m · 150 sq ft | 1 | 0 |
| Building No 2 | 1 | 24.93 sq m · 268 sq ft | 1 | 1 |
| Building No 2 | 2 | 24.94 sq m · 268 sq ft | 3 | 3 |
| Building No 2 | 3 | 25.25 sq m · 272 sq ft | 3 | 3 |
| Building No 2 | 4 | 33.99 sq m · 366 sq ft | 1 | 1 |
| Building No 2 | 5 | 34.86 sq m · 375 sq ft | 3 | 3 |
| Bungalow | 1 | 97.69 sq m · 1,052 sq ft | 1 | 1 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 77 filings listed on MahaRERA's project page
Finance
- PAN Cardshriya company pan.pdf · uploaded 30 Jul 2017Source
Legal
Show all 79 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesNO ENCUMBERENCE.pdf · uploaded 30 Jul 2017Source
- 1 Copy of Layout Approval (in case of layout)layout plan.pdf · uploaded 30 Jul 2017Source
- 1 Building Plan Approval (IOD)building plan 1 and 2.pdf · uploaded 30 Jul 2017Source
- 2 Building Plan Approval (IOD)bunglaw plan .pdf · uploaded 30 Jul 2017Source
- 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 30 Jul 2017Source
- 1 Declaration in FORM Baffidavit moreshwar.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch cer moreshwar niwas building no 1.pdf · uploaded 30 Jul 2017Source
- 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCH moreshwar building no 2.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng cer moreshwar niwas.pdf · uploaded 30 Jul 2017Source
- 1 Certificates of CA (Form 3)ca certificate moreshwar.pdf · uploaded 30 Jul 2017Source
- 1 Proforma of Allotment letterSHRIYA-MORESHWAR-NIWAS.pdf · uploaded 30 Jul 2017Source
- 1 Otherarch cer moreshwar niwas bunglow.pdf · uploaded 30 Jul 2017Source
- 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)moreshwar niwas building arch certificate.pdf · uploaded 31 Oct 2017Source
- 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)moreshwar bungalow arch certificate.pdf · uploaded 31 Oct 2017Source
- 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng certificate moreshwar.pdf · uploaded 31 Oct 2017Source
- 2 Certificates of CA (Form 3)ca certi moreshwar.pdf · uploaded 31 Oct 2017Source
- 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)moresh arch bldg 2.pdf · uploaded 29 Sep 2018Source
- 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch mores RH.pdf · uploaded 29 Sep 2018Source
- 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng certi moreshwar.pdf · uploaded 29 Sep 2018Source
- 3 Certificates of CA (Form 3)CA certificate moreshwar.pdf · uploaded 29 Sep 2018Source
- 4 Certificates of CA (Form 3)ca certi moreshwar april.pdf · uploaded 29 Sep 2018Source
- 1 Certificates of CA (Form 5)rera audit moreshwar niwas.pdf · uploaded 1 Oct 2018Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)moreshwar fy1819 audit.pdf · uploaded 2 Apr 2021Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)moreshwar fy1920 audit.pdf · uploaded 2 Apr 2021Source
- 1 Declaration about Commencement CertificateCC DECLERATION.pdf · uploaded 15 Aug 2021Source
- 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Engineer’s certificate Moreshwar nivas_compressed.pdf · uploaded 15 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)QAC 2021.pdf · uploaded 15 Aug 2021Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 15 Aug 2021Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)QAC 2020.pdf · uploaded 18 Aug 2021Source
- 1 CERSAI detailsCERSAI_Search_Report_200251006453_For_Asset_Based_Search_31_10_2022_17_28_08_787.pdf · uploaded 31 Oct 2022Source
- 2 CERSAI detailsCERSAI_Search_Report_200251006262_For_Asset_Based_Search_31_10_2022_17_27_32_241.pdf · uploaded 31 Oct 2022Source
- 3 CERSAI detailsCERSAI_Search_Report_200251006139_For_Asset_Based_Search_31_10_2022_17_27_10_464.pdf · uploaded 31 Oct 2022Source
- 5 Certificates of CA (Form 3)moreshwar niwas Ca certificate_compressed.pdf · uploaded 31 Oct 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)form 5 signed fy2021.pdf · uploaded 31 Oct 2022Source
- 1 Proforma of Agreement for sale1 Proforma of Allotment letter.pdf · uploaded 31 Oct 2022Source
- 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Adobe Scan 16 Nov 2022 (1)_compressed.pdf · uploaded 2 Dec 2022Source
- 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)MORESHWAR ENG FORM 212_compressed.pdf · uploaded 2 Dec 2022Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)Adobe Scan 07 Nov 2022 - Copy.pdf · uploaded 2 Dec 2022Source
- 2 Disclosure of sold/ booked inventoryAdobe Scan 26 Nov 2022 (1).pdf · uploaded 2 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Adobe Scan 16 Nov 2022 (1)_compressed.pdf · uploaded 2 Dec 2022Source
- 6 Certificates of CA (Form 3)CA Certificate FORM 3 SHRIYA.pdf · uploaded 27 Dec 2022Source
- 2 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)ca form 5 2122 (1).pdf · uploaded 27 Dec 2022Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)arch dec24.pdf · uploaded 11 Mar 2025Source
- 1 Certificates of CA (Form 3)ca dec24.pdf · uploaded 11 Mar 2025Source
- 2 Certificates of CA (Form 3)ca dec24.pdf · uploaded 11 Mar 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)eng dec24.pdf · uploaded 11 Mar 2025Source
- 1 Disclosure of sold/ booked inventorysold unsold.pdf · uploaded 15 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)qa 23.pdf · uploaded 15 Mar 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)qa 24.pdf · uploaded 15 Mar 2025Source
- 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)FORM 1.pdf · uploaded 19 Apr 2025Source
- 1 Certificates of CA (Form 3)FORM 3.pdf · uploaded 19 Apr 2025Source
- 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)FORM 2.pdf · uploaded 19 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD.pdf · uploaded 19 Apr 2025Source
- Withdrawal Update Form 1FORM 1.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 2FORM 2.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 3FORM 3.pdf · uploaded 19 Dec 2025Source
- Withdrawal Update Form 1form1.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 2form2.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 3form3.pdf · uploaded 20 Dec 2025Source
- Withdrawal Update Form 1FORM 1 DEC25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 2FORM 2 DEC25.pdf · uploaded 19 Jan 2026Source
- Withdrawal Update Form 3FORM 3 DEC25.pdf · uploaded 19 Jan 2026Source
Technical
Technical (Architect)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Vasai-Virar City (M Corp), Vasai taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Rauts Bungalow
- South
- Road
- East
- Lyans Bungalow
- West
- Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Ajay Wade & Associates | — |
| Engineer | Kush Jitendra Vartak | — |
Source: MahaRERA project page. Contact details are not shown.