Skip to content

Building No 1,- Wing A And B · Merkez

Vasaivirar City (M Corp) · RERA P99000052992

IDBLD_06301923 floorsExtended 4 mo
23Sanctioned habitable floorsregistration certificate
30 Apr 2030Revised completionpromised 31 Dec 2029
169 of 324Units bookedMahaRERA project page

Floors

23 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P99000052992 · registered 10 Oct 2023
Promised completion
31 Dec 2029
Revised completion
30 Apr 2030
Sanctioned habitable floors
23
ProjectId
45,423
ProjectName
MERKEZ
TotalUnitCount
324
ProjectBuildingId
1,66,284
BuildingNameNumber
BUILDING NO 1,- WING A AND B
FsiWithSanctionSqmts
23
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
324
ProjectRegistartionNo
P99000052992
ProjectBuildingWingsId
1,69,741
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
BUILDING NO 1,- WING A AND B
NoOfBuildingWingFloorProposed
23
NoOfBuildingWingFloorHabitable
23
NoOfBuildingWingFloorSanctioned
23

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK38 m² (409 sq.ft)2211
1BHK40.7 m² (438 sq.ft)226
1BHK40.8 m² (439 sq.ft)189
1BHK41.6 m² (448 sq.ft)7041
1BHK43.1 m² (464 sq.ft)2211
1BHK43.6 m² (469 sq.ft)41
1BHK44.4 m² (478 sq.ft)41
1BHK44.4 m² (478 sq.ft)41
1BHK44.9 m² (483 sq.ft)40
1BHK62.2 m² (670 sq.ft)20
Show all 23 unit typesShow fewer unit types
TypeCarpet areaUnitsBooked
1BHK62.3 m² (671 sq.ft)11
2BHK54.2 m² (583 sq.ft)1812
2BHK54.2 m² (583 sq.ft)40
2BHK55.5 m² (597 sq.ft)1814
2BHK55.6 m² (598 sq.ft)1813
2BHK62.1 m² (669 sq.ft)40
2BHK62.2 m² (670 sq.ft)20
2BHK62.3 m² (671 sq.ft)179
2BHK62.9 m² (677 sq.ft)1810
2BHK65.8 m² (708 sq.ft)43
2BHK66.4 m² (715 sq.ft)41
2BHK67.5 m² (727 sq.ft)2213
3BHK87.4 m² (941 sq.ft)2212
Total324169
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology