M Baria Lake View
Certificate SignedVasaivirar City (M Corp), Palghar 401303 |Promoter: Moreshwar Krushna Baria
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK, 3BHK13 units in all
- Address
- 118 118a 119, M Baria Business House P P Marg, Virat NagarPIN 401303
- Designated bank account
- 19
- Developed in phases
- No
Location
Coordinates as published by MahaRERA
Registered transactions
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 1 year
The latest completion date on record passed 3 years and 5 months ago.
- Registered
- 26 Apr 2021
- Promised
- 31 May 2022
- Revised
- 31 May 2023
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000029111 | 26 Apr 2021 | 31 May 2022 | 31 May 2023 | Moreshwar Krushna Baria | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| M Baria Lake View | 7 | 13 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
1 of 13 units booked (8%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 32.98 sq m · 355 sq ft | 3 | 0 |
| 1BHK | 33.25 sq m · 358 sq ft | 3 | 0 |
| 2BHK | 48.46 sq m · 522 sq ft | 6 | 1 |
| 3BHK | 100 sq m · 1,076 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
2 documents held by Deedo, 58 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD M K BARIA.pdf · uploaded 20 Mar 2021Source
Legal
Show all 60 documentsShow fewer documents
Migrated
- 1 Details of encumbrancesENCUMBRANCES.pdf · uploaded 20 Mar 2021Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT PLAN date 3 11 2020.pdf · uploaded 21 Mar 2021Source
- 1 Building Plan Approval / NA Order for plotted developmentGr to 5 PLAN 3 11 2020.pdf · uploaded 21 Mar 2021Source
- 2 Building Plan Approval / NA Order for plotted development6th floor plan 3 11 2021.pdf · uploaded 21 Mar 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentRDP 03 11 2020.pdf · uploaded 21 Mar 2021Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 21 Mar 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1.pdf · uploaded 21 Mar 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 21 Mar 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 21 Mar 2021Source
- 1 Proforma of Allotment letterAGREEMENT FOR SALE.pdf · uploaded 21 Mar 2021Source
- 2 Copy of Layout Approval (in case of layout)LAYOUT C.pdf · uploaded 21 Jul 2021Source
- 3 Building Plan Approval / NA Order for plotted development6 AND 7 FLOOR C.pdf · uploaded 21 Jul 2021Source
- 4 Building Plan Approval / NA Order for plotted developmentGR TO 5TH FLOORS C.pdf · uploaded 21 Jul 2021Source
- 2 Commencement Certificates / NA Order for plotted developmentRDP 14 06 2021 B.pdf · uploaded 21 Jul 2021Source
- 1 Declaration about Commencement CertificateRDP 14 06 2021 B W.pdf · uploaded 21 Jul 2021Source
- 3 Copy of Layout Approval (in case of layout)LAYOUT PLAN 14 06 2021.pdf · uploaded 12 May 2022Source
- 5 Building Plan Approval / NA Order for plotted development1 TO 5 FLOORS 14 06 2021.pdf · uploaded 12 May 2022Source
- 6 Building Plan Approval / NA Order for plotted development6 and 7 FLOOR PLAN 14 06 2021.pdf · uploaded 12 May 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE M BARIA LAKE VIEW.pdf · uploaded 12 May 2022Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE 11 05 2022.pdf · uploaded 12 May 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)C A CERTIFICATE FORM NO 3.pdf · uploaded 12 May 2022Source
- 1 OtherRDP 14 06 2021.pdf · uploaded 12 May 2022Source
- 2 Declaration about Commencement Certificatedeclaration.pdf · uploaded 25 May 2022Source
- 1 Disclosure of sold/ booked inventorydisclosure of sold.pdf · uploaded 25 May 2022Source
- 3 Declaration about Commencement CertificateDECLARATION COMMENCEMENT CERTIFICATE.pdf · uploaded 27 Jun 2022Source
- 7 Building Plan Approval / NA Order for plotted developmentGROUND FLOOR PLAN (3).pdf · uploaded 5 Dec 2022Source
- 8 Building Plan Approval / NA Order for plotted development6TH FLOOR PLAN.pdf · uploaded 5 Dec 2022Source
- 1 CERSAI detailsMCHI CERTIFICATE.pdf · uploaded 5 Dec 2022Source
- 1 Proforma of Agreement for saleAGREEMENT FOR SALE FINAL.pdf · uploaded 5 Dec 2022Source
- 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentOC PERMISSION 27092022.pdf · uploaded 5 Dec 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 FY 2020-21.pdf · uploaded 28 Mar 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)Form 5 FY 2021-22.pdf · uploaded 28 Mar 2023Source
- 2 a Details of encumbrances concerned to FinanceENCUMBRANCES.pdf · uploaded 29 Mar 2023Source
- 1 b Details of encumbrances concerned to LegalENCUMBRANCES.pdf · uploaded 29 Mar 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)ENGINEERS FORM 2A 2021 22.pdf · uploaded 8 Apr 2023Source
- 2 Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)ENGINEERS FORM 2A 2019 20.pdf · uploaded 8 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)ENGINEERS FORM 2A 2020 21.pdf · uploaded 8 Apr 2023Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)ENGINEERS FORM 2A 2021 22.pdf · uploaded 8 Apr 2023Source
- 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 10 Apr 2023Source
Technical
- DocumentGr to 5 PLAN 3 11 2020.pdf · uploaded 21 Mar 2021Source
- Document6th floor plan 3 11 2021.pdf · uploaded 21 Mar 2021Source
- DocumentLAYOUT PLAN date 3 11 2020.pdf · uploaded 21 Mar 2021Source
- DocumentLAYOUT C.pdf · uploaded 21 Jul 2021Source
- Document6 AND 7 FLOOR C.pdf · uploaded 21 Jul 2021Source
- DocumentGR TO 5TH FLOORS C.pdf · uploaded 21 Jul 2021Source
- DocumentLAYOUT PLAN 14 06 2021.pdf · uploaded 12 May 2022Source
- Document1 TO 5 FLOORS 14 06 2021.pdf · uploaded 12 May 2022Source
- Document6 and 7 FLOOR PLAN 14 06 2021.pdf · uploaded 12 May 2022Source
- DocumentGROUND FLOOR PLAN (3).pdf · uploaded 5 Dec 2022Source
- Document6TH FLOOR PLAN.pdf · uploaded 5 Dec 2022Source
Technical (Architect)
- DocumentARCHITECT CERTIFICATE M BARIA LAKE VIEW.pdf · uploaded 12 May 2022Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE 11 05 2022.pdf · uploaded 12 May 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Vasai-Virar City (M Corp), Vasai taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Compound Wall
- South
- Dp Road
- East
- Compound Wall
- West
- Compound Wall And Thereafter Road
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Abahy Damodar Raut | — |
| Chartered accountant | Hbk & Associates | — |
| Engineer | Paresh Ramniklal Unnarkar | — |
| Other | Dipin Ratilal Patel | — |
Source: MahaRERA project page. Contact details are not shown.