Certificate SignedVasaivirar City (M Corp), Palghar 401209 |Promoter: Hemant Janu Chiplunkar
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Certificate Signed
- Buildings
- 3
- Unit types
- —24 units in all
- Address
- Survey No-13, Hissa Number 1, Near Dutt Mandir, Village MorePIN 401209
- Designated bank account
- 19
- Developed in phases
- Yes
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 4 months
The latest completion date on record passed 2 months ago.
- Registered
- 14 Jan 2022
- Promised
- 1 Apr 2026
- Revised
- 1 Aug 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P99000032608 | 14 Jan 2022 | 1 Apr 2026 | 1 Aug 2026 | Hemant Janu Chiplunkar | Project page |
3 buildings
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| A-Wing | 2 | 8 |
| B-Wing | 3 | 12 |
| C-Wing | 2 | 4 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
24 units registered
| Building | Type | Carpet area | Units |
|---|---|---|---|
| A-Wing | — | — | 8 |
| B-Wing | — | — | 12 |
| C-Wing | — | — | 4 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 82 filings listed on MahaRERA's project page
Finance
- PAN CardPAN CARD.pdf · uploaded 8 Dec 2021Source
Migrated
- 1 PAN CardPAN CARD.pdf · uploaded 8 Dec 2021Source
- 1 Details of encumbrancesENCRUMBABCES CERTIFICATE LETTER HEAD.pdf · uploaded 8 Dec 2021Source
- 1 Copy of Layout Approval (in case of layout)1 LAYOUT PLAN.pdf · uploaded 8 Dec 2021Source
- 1 Building Plan Approval / NA Order for plotted development2.pdf · uploaded 8 Dec 2021Source
- 2 Building Plan Approval / NA Order for plotted development3.pdf · uploaded 8 Dec 2021Source
- 3 Building Plan Approval / NA Order for plotted development4.pdf · uploaded 8 Dec 2021Source
Show all 83 documentsShow fewer documents
Migrated
- 4 Building Plan Approval / NA Order for plotted development5.pdf · uploaded 8 Dec 2021Source
- 5 Building Plan Approval / NA Order for plotted development6.pdf · uploaded 8 Dec 2021Source
- 1 Commencement Certificates / NA Order for plotted developmentScan _compressed.pdf · uploaded 8 Dec 2021Source
- 1 Declaration about Commencement CertificateDECLARATION REGARDING COMMENCEMENT CERTIFICATE.pdf · uploaded 8 Dec 2021Source
- 1 Declaration in FORM BFORM B.pdf · uploaded 8 Dec 2021Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT'S CERTIFICATE FILE.pdf · uploaded 8 Dec 2021Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER'S CERTIFICATE FILE.pdf · uploaded 8 Dec 2021Source
- 1 CERSAI detailsCERSAI DECLARATION new.pdf · uploaded 8 Dec 2021Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE COMPRESSED.pdf · uploaded 8 Dec 2021Source
- 1 Proforma of Allotment letterLETTER_OF_ALLOTMENT.pdf · uploaded 8 Dec 2021Source
- 1 Copy of the legal title reportlegal title report 1-8.pdf · uploaded 3 Jan 2022Source
- 2 Copy of the legal title reportlegal title report 9-14.pdf · uploaded 3 Jan 2022Source
- 3 Copy of the legal title reportlegal title report 15-25.pdf · uploaded 3 Jan 2022Source
- 4 Copy of the legal title reportlegal title report 26-34.pdf · uploaded 3 Jan 2022Source
- 2 Proforma of Allotment letterRERA-Blank_Draft_Agreement.pdf · uploaded 3 Jan 2022Source
- 2 CERSAI detailsCERSAI REPORT.pdf · uploaded 8 Jan 2022Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM_1_ARCHITECT-_ENGINEER_compressed.pdf · uploaded 15 Jul 2022Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)form 3 sai dutt land developers_compressed.pdf · uploaded 15 Jul 2022Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM_5_FY_2021-22.pdf · uploaded 28 Jan 2023Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM2 30 06 2022 FINAL.pdf · uploaded 20 Feb 2023Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM2 30 09 2022 FINAL.pdf · uploaded 20 Feb 2023Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM2 31 12 2022 FINAL.pdf · uploaded 20 Feb 2023Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)1FORM 1 30062022.pdf · uploaded 13 Feb 2024Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)2FORM 1 30092022.pdf · uploaded 13 Feb 2024Source
- 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)3FORM 1 31122022.pdf · uploaded 13 Feb 2024Source
- 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)4FORM 1 31032023.pdf · uploaded 13 Feb 2024Source
- 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)5FORM 1 30062023.pdf · uploaded 13 Feb 2024Source
- 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)6FORM 1 30092023.pdf · uploaded 13 Feb 2024Source
- 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)7FORM 1 31122023.pdf · uploaded 13 Feb 2024Source
- 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31032023.pdf · uploaded 13 Feb 2024Source
- 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30062023.pdf · uploaded 13 Feb 2024Source
- 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 30092023.pdf · uploaded 13 Feb 2024Source
- 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 31122023.pdf · uploaded 13 Feb 2024Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE_OF_SOLD UNSOLD.pdf · uploaded 13 Feb 2024Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)AFORM3 30092022.pdf · uploaded 13 Feb 2024Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)BFORM3 31122022.pdf · uploaded 13 Feb 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)CFORM3 31032023.pdf · uploaded 13 Feb 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)DFORM3 30062023.pdf · uploaded 13 Feb 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)EFORM3 30092023.pdf · uploaded 13 Feb 2024Source
- 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)FFORM3 31122023.pdf · uploaded 13 Feb 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM_5_FY_2022-23.pdf · uploaded 16 Feb 2024Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 (1).pdf · uploaded 18 Apr 2025Source
- 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 JUNE 24 (1).pdf · uploaded 18 Apr 2025Source
- 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 SEPT 24 (1).pdf · uploaded 18 Apr 2025Source
- 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 DEC 24 (1).pdf · uploaded 18 Apr 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3 JAN-MARCH-24.pdf · uploaded 18 Apr 2025Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3_APRIL-JUNE-24.pdf · uploaded 18 Apr 2025Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3_JULY-SEP-24.pdf · uploaded 18 Apr 2025Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM-3_OCT-DEC-24.pdf · uploaded 18 Apr 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 FINAL.pdf · uploaded 18 Apr 2025Source
- 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 JUNE 24 (1).pdf · uploaded 18 Apr 2025Source
- 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 1 SEPT 24 (1).pdf · uploaded 18 Apr 2025Source
- 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 DEC 24.pdf · uploaded 18 Apr 2025Source
- 1 Disclosure of sold/ booked inventorySOLD UNSOLD AS ON 311224.pdf · uploaded 18 Apr 2025Source
- 1 Disclosure of Interest in Other Real Estate OrganizationsINTEREST IN OTHER ORGANISATION.pdf · uploaded 18 Apr 2025Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)ANNUAL REPORT-23-24.pdf · uploaded 18 Apr 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM_2A-21-22.pdf · uploaded 20 May 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM_2A-22-23.pdf · uploaded 20 May 2025Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM_2A-23-24.pdf · uploaded 20 May 2025Source
- 1 Disclosure of sold/ booked inventoryDISCLOSURE_OF_SOLD_INVENTORY.pdf · uploaded 21 May 2025Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM_1_310325.pdf · uploaded 19 Jun 2025Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM_2_310325.pdf · uploaded 19 Jun 2025Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3 MAR 2025.pdf · uploaded 20 Jun 2025Source
Technical (Architect)
- Document7FORM 1 31122023.pdf · uploaded 13 Feb 2024Source
- DocumentFORM 1 (1).pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 JUNE 24 (1).pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 SEPT 24 (1).pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 DEC 24 (1).pdf · uploaded 18 Apr 2025Source
- DocumentFORM_1_310325.pdf · uploaded 19 Jun 2025Source
Technical (Engineer)
- DocumentFORM 2 31122023.pdf · uploaded 13 Feb 2024Source
- DocumentFORM 2 FINAL.pdf · uploaded 18 Apr 2025Source
- DocumentFORM 2 JUNE 24 (1).pdf · uploaded 18 Apr 2025Source
- DocumentFORM 1 SEPT 24 (1).pdf · uploaded 18 Apr 2025Source
- DocumentFORM 2 DEC 24.pdf · uploaded 18 Apr 2025Source
- DocumentFORM_2_310325.pdf · uploaded 19 Jun 2025Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Vasai-Virar City (M Corp), Vasai taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- S No 11 12
- South
- S No 90 92 94
- East
- 20 Mtr Wide Dp Road S No 28-95
- West
- S No 14 15 21
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | En Con | — |
Source: MahaRERA project page. Contact details are not shown.