Completion due Dec 2028

Vasaivirar City (M Corp), Palghar 401303 |Promoter: Ekta Parksville Homes Pvt. Ltd.

3 Jul 2017Registered with MahaRERAFirst of 4 registrations
31 Dec 2028Promised completionLatest across registrations
30 Dec 2023Revised completion2 of 4 registrations pushed back, by up to 3 years and 7 months
3MahaRERA listings and orders

Project summary

As registered with MahaRERA

RERA registrations
4
Phases
4

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.47189, 72.80043
Ekta Parksville is at latitude 19.47189, longitude 72.80043.

Also registered as

Ekta Parksville Phase IEkta Parksville Phase IIEkta Parksville Phase IIIEkta Parksville Phase IV
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 3 years

P99000000109

The latest completion date on record passed 2 years and 10 months ago.

Registered
3 Jul 2017
Promised
30 Dec 2020
Revised
30 Dec 2023

Completion pushed back 3 years and 7 months

P99000000116

The latest completion date on record passed 3 years and 3 months ago.

Registered
4 Jul 2017
Promised
31 Dec 2019
Revised
27 Jul 2023

Completion promised for 31 Dec 2026

P99000000115
Registered
4 Jul 2017
Promised
31 Dec 2026

Completion promised for 31 Dec 2028

P99000015239
Registered
8 Feb 2018
Promised
31 Dec 2028

4 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P990000001093 Jul 201730 Dec 202030 Dec 2023Ekta Parksville Homes Pvt. Ltd.Project page
P990000001164 Jul 201731 Dec 201927 Jul 2023Ekta Parksville Homes Pvt. Ltd.Project page
P990000001154 Jul 201731 Dec 2026—Ekta Parksville Homes Pvt. Ltd.Project page
P990000152398 Feb 201831 Dec 2028—Ekta Parksville Homes Pvt. Ltd.Project page

Documents

6 documents held by Deedo

Registration certificates

  • Registration certificateP99000000116 · 4 Jul 2017ViewSource
  • Registration certificateP99000000109 · 18 May 2020ViewSource
  • Registration certificateP99000000115 · 8 Oct 2024ViewSource
  • Registration certificateP99000015239 · 8 Oct 2024ViewSource

Extension certificates

  • Extension certificateP99000000109 · 12 Apr 2023ViewSource
  • Extension certificateP99000000116 · 25 Jul 2025ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

What MahaRERA has published about this project. A listing records what the authority published; it is not a judgment of the project.

  • Regulatory order16 Sep 2024Matched by RERA number

    Regulatory order: PROJECT NAME: EKTA PARKSVILLE PHASE IV (Regulatory Case No. 298 OF 2024) dated 16 Sept 2024.

  • Regulatory order24 Mar 2023Matched by RERA number

    Regulatory order: PROJECT NAME: EKTA PARKSVILLE PHASE III (Regulatory Case No. 06 of 2023) dated 21 March 2023.

  • Regulatory order24 Mar 2023Matched by RERA number

    Regulatory order: PROJECT NAME: EKTA PARKSVILLE PHASE II (Regulatory Case No. 04 of 2023) dated 21 March 2023.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

Survey, CTS, gat or plot numbers

2PT7A PT/7B PT88/185PT89/184 PT90/183 7/4 7/5PT91/17691/176 1/2Pt91/176 1PT91/176 2Pt91/176 3Pt91/176 3Pt at 91/176 1/2Pt91/183 PT93/17793/177/1/2 PT93/177 2 PT 90/183 4PT 7PT93/177 2 PT 90/183 4PT 7PT at 90/183 7/4 7/5PT94/182 7A PT / 7B PT94/185 PT96/17896/178 PT

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificates · MahaRERA regulatory lists and ordersMethodology