Dange Chawre Crown B Wing

Certificate Signed

Vasaivirar City (M Corp), Palghar 401203 |Promoter: Dange Developers

Residential / Group HousingRERAP99000020884
16 May 2019Registered with MahaRERA
5 May 2025Promised completion
5 May 2027Revised completionPushed back 2 years
1Building
110Units registered24 booked (22%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK110 units in all
Address
13/1a, Hno 1 To 5, 1b/1 And Sno 14, Nil, NilPIN 401203
Designated bank account
19
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 2 years

Registered
16 May 2019
Promised
5 May 2025
Revised
5 May 2027

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P9900002088416 May 20195 May 20255 May 2027Dange DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Dange Chawre Crown B Wing16110

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

24 of 110 units booked (22%), as the promoter reported to MahaRERA

1BHK · 98 units2BHK · 12 units
TypeCarpet areaUnitsBooked
1BHK29.36 sq m · 316 sq ft136
1BHK29.79 sq m · 321 sq ft134
1BHK29.93 sq m · 322 sq ft10
1BHK29.97 sq m · 323 sq ft164
1BHK29.98 sq m · 323 sq ft90
1BHK31.14 sq m · 335 sq ft71
1BHK39.64 sq m · 427 sq ft92
1BHK39.76 sq m · 428 sq ft305
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK43.53 sq m · 469 sq ft10
2BHK49.42 sq m · 532 sq ft20
2BHK49.72 sq m · 535 sq ft92

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 126 filings listed on MahaRERA's project page

Extension certificate

Registration certificate

Finance

  • Other – FinanceJUSTIFICATION SIGNED.pdf · uploaded 2 Apr 2025Source
  • Other – FinanceWORK STATUS SIGNED.pdf · uploaded 2 Apr 2025Source

Legal

  • Legal Title reportlegal title report.pdf · uploaded 20 Mar 2019Source
  • Declaration Form BFORM B.pdf · uploaded 20 Mar 2019Source
  • Declaration Form BFORM B - AFFIDAVITE REVISED ON RS 500 SP.pdf · uploaded 30 Mar 2025Source

Migrated

  • 1 Copy of the legal title reportlegal title report.pdf · uploaded 20 Mar 2019Source
Show all 128 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesDECLARATION OF ENCUBRANCES.pdf · uploaded 20 Mar 2019Source
  • 1 Copy of Layout Approval (in case of layout)LAYOUT AND IOD.pdf · uploaded 20 Mar 2019Source
  • 1 Building Plan Approval (IOD)LAYOUT AND IOD.pdf · uploaded 20 Mar 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 20 Mar 2019Source
  • 1 Declaration in FORM BFORM B.pdf · uploaded 20 Mar 2019Source
  • 1 Certificates of CA (Form 3)DANGE T4B-FORM 3_OPT.pdf · uploaded 20 Mar 2019Source
  • 1 Proforma of Allotment letterLOAA.pdf · uploaded 20 Mar 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)BLDG 4B_FORM 2A.pdf · uploaded 10 Jul 2021Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD TOWER 4 B.pdf · uploaded 26 Jul 2021Source
  • 1 Declaration about Commencement CertificateDECLARATION FOR B WING T-4.pdf · uploaded 28 Jul 2021Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)BLDG 4B_FORM 1.pdf · uploaded 28 Jul 2021Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)BLDG 4B_FORM 2.pdf · uploaded 28 Jul 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentREVISED DEV PLAN opt.pdf · uploaded 29 Apr 2022Source
  • 2 Disclosure of sold/ booked inventorySOLD UNSOLD DECLARATION opt.pdf · uploaded 29 Apr 2022Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 5 2022.pdf · uploaded 25 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)FORM 5 2020.pdf · uploaded 25 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)FORM 5 2021.pdf · uploaded 25 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)FORM 5 2022.pdf · uploaded 25 Apr 2023Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)architect certificate.pdf · uploaded 17 Oct 2023Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)engineer certificate.pdf · uploaded 17 Oct 2023Source
  • 2 Certificates of CA (Form 3)DD RARA FORM 3 CERTIFICATE Q-1 signed.pdf · uploaded 20 Oct 2023Source
  • 3 Certificates of CA (Form 3)DD RERA CA CERTIFICATE Q-2.pdf · uploaded 20 Oct 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)SCAN COPY OF FORM 5 DANGE CHAWRE.pdf · uploaded 8 Mar 2024Source
  • 1 Certificates of CA (Form 3)FORM 3- DANGE DEV Q3 signed.pdf · uploaded 7 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Bldg 4 Wing B.pdf · uploaded 7 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Bldg 4 Wing B Dange Complex.pdf · uploaded 7 Oct 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 7 Oct 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Bldg 4 Wing B.pdf · uploaded 7 Oct 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Bldg 4 Wing B Dange Complex.pdf · uploaded 7 Oct 2024Source
  • 2 Certificates of CA (Form 3)FORM 3- DANGE DEV Q3 signed.pdf · uploaded 7 Oct 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 7 Oct 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 11 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 11 Dec 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 11 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 12 Dec 2024Source
  • 1 Certificates of CA (Form 3)FORM 3 Q4-DANG DEV.pdf · uploaded 12 Dec 2024Source
  • 1 Certificates of CA (Form 3)FORM 3_Tower 4B wing_June 2024(SIGNED).pdf · uploaded 12 Dec 2024Source
  • 1 Certificates of CA (Form 3)FORM 3_Tower 4B wing_SEP 2024(for sign).pdf · uploaded 12 Dec 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 12 Dec 2024Source
  • 1 Certificates of CA (Form 3)FORM 3 Q4-DANG DEV.pdf · uploaded 12 Dec 2024Source
  • 1 Certificates of CA (Form 3)FORM 3_Tower 4B wing_June 2024(SIGNED).pdf · uploaded 12 Dec 2024Source
  • 1 Certificates of CA (Form 3)FORM 3_Tower 4B wing_SEP 2024(for sign).pdf · uploaded 12 Dec 2024Source
  • 3 Certificates of CA (Form 3)FORM 3 Q4-DANG DEV.pdf · uploaded 12 Dec 2024Source
  • 4 Certificates of CA (Form 3)FORM 3_Tower 4B wing_June 2024(SIGNED).pdf · uploaded 12 Dec 2024Source
  • 5 Certificates of CA (Form 3)FORM 3_Tower 4B wing_SEP 2024(for sign).pdf · uploaded 12 Dec 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 12 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Oct-Dec 2024 Bldg 4 Wing B.pdf · uploaded 25 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FOR Q-3.pdf · uploaded 25 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Oct-Dec 2024 Bldg 4 Wing B.pdf · uploaded 25 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FOR Q-3.pdf · uploaded 25 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Oct-Dec 2024 Bldg 4 Wing B.pdf · uploaded 25 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE FOR Q-3.pdf · uploaded 25 Jan 2025Source
  • 1 Certificates of CA (Form 3)FORM 3_DANGE DEV 4B_QE DEC 24-SIGNED.pdf · uploaded 3 Feb 2025Source
  • 1 Certificates of CA (Form 3)FORM 3_DANGE DEV 4B_QE DEC 24-SIGNED.pdf · uploaded 3 Feb 2025Source
  • 1 Certificates of CA (Form 3)FORM 3_DANGE DEV 4B_QE DEC 24-SIGNED.pdf · uploaded 3 Feb 2025Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM-1 DEC 2024 CR.pdf · uploaded 13 Feb 2025Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM-2 MARCH 2024 CR.pdf · uploaded 13 Feb 2025Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 2024 SIGNED.pdf · uploaded 14 Feb 2025Source
  • 1 Declaration in FORM BFORM B - AFFIDAVITE REVISED ON RS 500 SP.pdf · uploaded 30 Mar 2025Source
  • 1 Declaration about Commencement CertificateRDP 31032023 NEW optimized.pdf · uploaded 30 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FORM 2A FY21 22.pdf · uploaded 30 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)FORM 2A FY22 23.pdf · uploaded 30 Mar 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2A FY23 24.pdf · uploaded 30 Mar 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD INVENTORY AS ON 31 12 24 SIGNED.pdf · uploaded 2 Apr 2025Source
  • 1 Other – FinanceJUSTIFICATION SIGNED.pdf · uploaded 2 Apr 2025Source
  • 2 Other – FinanceWORK STATUS SIGNED.pdf · uploaded 2 Apr 2025Source
  • 1 Copy of Layout Approval (in case of layout)PLAN HL.pdf · uploaded 13 Jun 2025Source
  • 1 Certificates of CA (Form 3)FORM 3_DANGE DEV 4B_QE MAR 25-SIGNED.pdf · uploaded 13 Jun 2025Source
  • 1 Commencement Certificates / NA Order for plotted developmentRDP 31032023 NEW optimized.pdf · uploaded 13 Jun 2025Source
  • 1 Building Plan Approval (IOD)BLDG PLAN.pdf · uploaded 13 Jun 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Arch Cft Form I Jan-March Bldg 4 Wing B.pdf · uploaded 16 Jun 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.pdf · uploaded 16 Jun 2025Source
  • 1 Disclosure of sold/ booked inventorySOLD UNSOLD DETAIL DTD 31 03 25.pdf · uploaded 16 Jun 2025Source
  • Form 1FORM 1 - JUNE 2025.pdf · uploaded 11 Nov 2025Source
  • Form 1FORM 1 - SEP 2025.pdf · uploaded 11 Nov 2025Source
  • Form 2FORM 2 - JUNE 2025.pdf · uploaded 11 Nov 2025Source
  • Form 2FORM 2 - SEP 2025.pdf · uploaded 11 Nov 2025Source
  • Form 3FORM 3_DANGE DEV 4B_QE JUNE 25-SIGNED.pdf · uploaded 11 Nov 2025Source
  • Form 3FORM 3_DANGE DEV 4B_QE SEP 25-SIGNED.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY - JUNE 2025.pdf · uploaded 11 Nov 2025Source
  • Disclosure of Sold and Booked InventorySOLD BOOKED INVENTORY - SEP 2025.pdf · uploaded 11 Nov 2025Source
  • Withdrawal Update Form 1FORM 1 - DEC 2025.pdf · uploaded 10 Feb 2026Source
  • Withdrawal Update Form 2FORM 2 - DEC 2025.pdf · uploaded 10 Feb 2026Source
  • Withdrawal Update Form 3FORM 3_DANGE DEV 4B_QE DEC 25-SIGNED.pdf · uploaded 10 Feb 2026Source
  • Form 5 (FY 2024-2025)FORM 5_FY 2024-2025-SIGNED.pdf · uploaded 10 Mar 2026Source
  • Withdrawal Update Form 1FORM 1 - MAR 2026.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 2FORM 2 - MAR 2026.pdf · uploaded 29 May 2026Source
  • Withdrawal Update Form 3FORM 3_DANGE DEV 4B_Q4 MAR 2026- SIGNED.pdf · uploaded 29 May 2026Source
  • Form 5 (FY 2023-2024)FORM 5 FY_2023-24.pdf · uploaded 26 Jun 2026Source
  • Withdrawal Update Form 1FORM 1_Q1 APRIL - JUNE 2026.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 2FORM 2_Q1 APRIL - JUNE 2026.pdf · uploaded 5 Aug 2026Source
  • Withdrawal Update Form 3FORM 3_DANGE DEV 4B_Q1 APRIL - JUNE 2026- SIGNED.pdf · uploaded 5 Aug 2026Source

Technical

  • DocumentLAYOUT AND IOD.pdf · uploaded 20 Mar 2019Source
  • DocumentLAYOUT AND IOD.pdf · uploaded 20 Mar 2019Source
  • DocumentPLAN HL.pdf · uploaded 13 Jun 2025Source
  • DocumentBLDG PLAN.pdf · uploaded 13 Jun 2025Source

Technical (Architect)

  • DocumentArch Cft Form I Bldg 4 Wing B.pdf · uploaded 7 Oct 2024Source
  • DocumentArch Cft Form I Bldg 4 Wing B Dange Complex.pdf · uploaded 7 Oct 2024Source
  • DocumentArch Cft Form I Bldg 4 Wing B.pdf · uploaded 7 Oct 2024Source
  • DocumentArch Cft Form I Bldg 4 Wing B Dange Complex.pdf · uploaded 7 Oct 2024Source
  • DocumentArch Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 11 Dec 2024Source
  • DocumentArch Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 11 Dec 2024Source
  • DocumentArch Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 11 Dec 2024Source
  • DocumentArch Cft Form I Oct-Dec 2024 Bldg 4 Wing B.pdf · uploaded 25 Jan 2025Source
  • DocumentArch Cft Form I Oct-Dec 2024 Bldg 4 Wing B.pdf · uploaded 25 Jan 2025Source
  • DocumentArch Cft Form I Oct-Dec 2024 Bldg 4 Wing B.pdf · uploaded 25 Jan 2025Source
  • DocumentFORM-1 DEC 2024 CR.pdf · uploaded 13 Feb 2025Source
  • DocumentArch Cft Form I Jan-March Bldg 4 Wing B.pdf · uploaded 16 Jun 2025Source
  • DocumentFORM 1_Q1 APRIL - JUNE 2026.pdf · uploaded 5 Aug 2026Source

Technical (Engineer)

  • DocumentFORM 2.pdf · uploaded 7 Oct 2024Source
  • DocumentFORM 2.pdf · uploaded 7 Oct 2024Source
  • DocumentEngineer Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 12 Dec 2024Source
  • DocumentEngineer Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 12 Dec 2024Source
  • DocumentEngineer Cft Form I July-Sept 2024 Bldg 4 Wing B Dange Complex.pdf · uploaded 12 Dec 2024Source
  • DocumentENGINEER CERTIFICATE FOR Q-3.pdf · uploaded 25 Jan 2025Source
  • DocumentENGINEER CERTIFICATE FOR Q-3.pdf · uploaded 25 Jan 2025Source
  • DocumentENGINEER CERTIFICATE FOR Q-3.pdf · uploaded 25 Jan 2025Source
  • DocumentFORM-2 MARCH 2024 CR.pdf · uploaded 13 Feb 2025Source
  • DocumentENGINEER CERTIFICATE.pdf · uploaded 16 Jun 2025Source
  • DocumentFORM 2_Q1 APRIL - JUNE 2026.pdf · uploaded 5 Aug 2026Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Vasai-Virar City (M Corp), Vasai taluka

Survey, CTS, gat or plot numbers

13/1A1B/1HNO 1 TO 5SNO 14

Boundaries

North
Sno 12 Hno 2
South
Dange Complex Tower No 1
East
Seagull Bldg No 3
West
20 M Wide Dp Road

Source: registration certificates and MahaRERA's project page, as stated there.