B Wing · Aditi Empire
Vasaivirar City (M Corp) · RERA P99000010761
IDBLD_0915476 floorsPromised date passed
6Sanctioned habitable floorsregistration certificate
10 Apr 2022Revised completionpromised 10 Apr 2022
7 of 28Units bookedMahaRERA project page
Floors
6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P99000010761 · registered 31 Aug 2017
- Promised completion
- 10 Apr 2022
- Revised completion
- 10 Apr 2022
- Sanctioned habitable floors
- 6
- ProjectId
- 14,872
- ProjectName
- Aditi Empire
- TotalUnitCount
- 0
- ProjectBuildingId
- 15,529
- BuildingNameNumber
- B Wing
- ProjectCurrentStatus
- Certificate Signed
- ResidentialUnitCount
- 0
- ProjectRegistartionNo
- P99000010761
- ProjectBuildingWingsId
- 15,529
- BuildingWingsNameNumber
- NA
- NonResidentialUnitCount
- 0
- AdvertisedBuildingNameNumber
- B Wing
- NoOfBuildingWingFloorProposed
- 6
- NoOfBuildingWingFloorHabitable
- 0
- NoOfBuildingWingFloorSanctioned
- 6
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1 BHK | 31.2 m² (335 sq.ft) | 8 | 0 |
| 1 BHK | 32.3 m² (348 sq.ft) | 8 | 4 |
| 1 RK | 19.5 m² (210 sq.ft) | 2 | 1 |
| 1 RK | 26.5 m² (285 sq.ft) | 10 | 2 |
| Total | 28 | 7 |