Skip to content

Building No 3 · Tulip

Saravali · RERA P99000012111

IDBLD_0825784 floorsPromised date passed
4Sanctioned habitable floorsregistration certificate
31 Jul 2019Revised completionpromised 31 Jul 2019
25 of 35Units bookedMahaRERA project page

Floors

4 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P99000012111 · registered 1 Sep 2017
Promised completion
31 Jul 2019
Revised completion
31 Jul 2019
Sanctioned habitable floors
4
ProjectId
14,047
ProjectName
TULIP
TotalUnitCount
0
ProjectBuildingId
13,583
BuildingNameNumber
BUILDING NO 3
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P99000012111
ProjectBuildingWingsId
13,583
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
BUILDING NO 3
NoOfBuildingWingFloorProposed
4
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
4

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
FLAT31.7 m² (341 sq.ft)2317
FLAT33.2 m² (358 sq.ft)65
FLAT47.8 m² (514 sq.ft)63
Total3525
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology