Building No 10 · Ostwal Dream Land

Boisar · RERA P99000021182

IDBLD_0917616 floorsExtended 4 mo
6Sanctioned habitable floorsregistration certificate
30 Nov 2026Revised completionpromised 31 Jul 2026
0 of 16Units bookedMahaRERA project page

Floors

6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P99000021182 · registered 14 Jun 2019
Promised completion
31 Jul 2026
Revised completion
30 Nov 2026
Sanctioned habitable floors
6
ProjectId
20,375
ProjectName
OSTWAL DREAM LAND PHASE - II
TotalUnitCount
0
ProjectBuildingId
1,71,955
BuildingNameNumber
BUILDING NO 10
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P99000021182
ProjectBuildingWingsId
1,75,412
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
BUILDING NO 10
NoOfBuildingWingFloorProposed
6
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
6

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2BHK47.1 m² (507 sq.ft)160
Total160
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology