RERA projects in Osmanabad
12 projects under 12 MahaRERA registrations, registered 2017–2025. None has an extended completion date on record.
12RERA projects
12Registrations
4Completion still due8 past their completion date
—Median extension beyond promised date0% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2017 | 1 |
| 2018 | 1 |
| 2019 | 1 |
| 2020 | 3 |
| 2021 | 2 |
| 2022 | 2 |
| 2023 | 0 |
| 2024 | 1 |
| 2025 | 1 |
Projects in Osmanabad
12 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Dhaneshwar HeightsRamchandra Nanabhau Sangle | P52500079870 | 28 Mar 2025 | 31 Mar 2027 | — | Not yet due | 0 |
| Dhaneshwar TowerS . P. Construction | P52500055906 | 29 Apr 2024 | 30 May 2027 | — | Not yet due | 0 |
| Manjiri PrathamShri Developers | P52500047191 | 11 Oct 2022 | 14 Oct 2025 | — | Promised date passed | 0 |
| Sudarshan TowerS . P. Construction | P52500032588 | 14 Jan 2022 | 30 May 2024 | — | Promised date passed | 0 |
| The Grand Padmaksh Phase 3M/S Padmaja Developers | P52500032012 | 3 Dec 2021 | 31 Dec 2025 | — | Promised date passed | 0 |
| Rsm Dharashiv Shelters- Osmanabad ProjectRsm Dharashiv Shelters | P52500029666 | 26 Jun 2021 | 31 Dec 2027 | — | Not yet due | 0 |
| Nakshatra HightsDigvijay Ramesh Ghute Patil | P52500024596 | 24 Feb 2020 | 30 Dec 2021 | — | Promised date passed | 0 |
| Shivrai SocietyBalasaheb Budruk Satish Patil | P52500024005 | 14 Jan 2020 | 31 Jan 2020 | — | Promised date passed | 0 |
| Shri Samarth SocietyShri Developers | P52500024010 | 14 Jan 2020 | 31 Jan 2020 | — | Promised date passed | 0 |
| The Grand Padmaksh Phase 1M/S Padmaja Developers | P52500022520 | 30 Sep 2019 | 30 Mar 2027 | — | Not yet due | 0 |
| Empire EstateChhatrapati Samrajya | P52500015208 | 8 Feb 2018 | 30 Dec 2022 | — | Promised date passed | 0 |
| Nakshatra ResidencyChetan Rangnathrao Wathwade | P52500011272 | 31 Aug 2017 | 31 May 2019 | — | Promised date passed | 0 |
Most active promoters
By projects registered here, as named on MahaRERA.
- M/S Padmaja Developers2 projects
- Shri Developers2 projects
- S . P. Construction2 projects
- Balasaheb Budruk Satish Patil1 project
- Chetan Rangnathrao Wathwade1 project
- Chhatrapati Samrajya1 project
- Digvijay Ramesh Ghute Patil1 project
- Ramchandra Nanabhau Sangle1 project
- Rsm Dharashiv Shelters1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology