Sheetal Residency Building 1 · Sheetal Residency Building No 1

Palse · RERA P51600002772

IDBLD_0111406 floorsCompleted
6Sanctioned habitable floorsregistration certificate
15 Oct 2024Promised completion

Floors

6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51600002772 · registered 4 Aug 2017
Promised completion
15 Oct 2024
Sanctioned habitable floors
6

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK33 m² (355 sq.ft)4not published
1BHK33.1 m² (357 sq.ft)4not published
1BHK34.3 m² (369 sq.ft)4not published
1BHK34.4 m² (370 sq.ft)4not published
1RK22.4 m² (241 sq.ft)4not published
1RK25.2 m² (272 sq.ft)4not published
2BHK37.9 m² (407 sq.ft)4not published
2BHK41.7 m² (449 sq.ft)4not published
Total32

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00032
Open Space0000

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology