N- Jasper · Anmol Nayantara Gold

Nashik · RERA P51600002894

IDBLD_01116212 floorsCompleted
12Sanctioned habitable floorsregistration certificate
31 Dec 2019Revised completionpromised 31 Dec 2018

Floors

12 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51600002894 · registered 4 Aug 2017
Promised completion
31 Dec 2018
Revised completion
31 Dec 2019
Sanctioned habitable floors
12

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
2bhk71.4 m² (769 sq.ft)5not published
2bhk71.6 m² (771 sq.ft)5not published
2bhk72 m² (774 sq.ft)5not published
2bhk72.1 m² (777 sq.ft)5not published
3bhk97.6 m² (1,051 sq.ft)10not published
3bhk97.8 m² (1,053 sq.ft)10not published
Total40

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00012
Open Space00020

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises95%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology