G - Moonstone · Anmol Nayantara Gold
Nashik · RERA P51600002894
IDBLD_01115713 floorsCompleted
13Sanctioned habitable floorsregistration certificate
31 Dec 2019Revised completionpromised 31 Dec 2018
Floors
13 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P51600002894 · registered 4 Aug 2017
- Promised completion
- 31 Dec 2018
- Revised completion
- 31 Dec 2019
- Sanctioned habitable floors
- 13
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 2bhk | 59.8 m² (643 sq.ft) | 2 | not published |
| 2bhk | 62.7 m² (674 sq.ft) | 1 | not published |
| 2bhk | 63.2 m² (680 sq.ft) | 3 | not published |
| 2bhk | 65.7 m² (707 sq.ft) | 5 | not published |
| 2bhk | 65.7 m² (707 sq.ft) | 2 | not published |
| 2bhk | 66.2 m² (712 sq.ft) | 2 | not published |
| 2bhk | 66.2 m² (712 sq.ft) | 2 | not published |
| 2bhk | 66.2 m² (713 sq.ft) | 2 | not published |
| 2bhk | 66.2 m² (713 sq.ft) | 1 | not published |
| 3bhk | 88.2 m² (950 sq.ft) | 1 | not published |
| 3bhk | 88.3 m² (950 sq.ft) | 5 | not published |
| 3bhk | 88.3 m² (950 sq.ft) | 3 | not published |
| 3bhk | 88.3 m² (950 sq.ft) | 1 | not published |
| 3bhk | 88.3 m² (950 sq.ft) | 2 | not published |
| 3bhk | 88.3 m² (950 sq.ft) | 7 | not published |
| 3bhk | 90.4 m² (973 sq.ft) | 1 | not published |
| Total | 40 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 35 |
| Open Space | 0 | 0 | 0 | 27 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)0%
- Podiums (if any)100%
- Plinth0%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises98%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks98%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.95%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology