Skip to content
Deedo home
Menu

A - Aquamarine · Anmol Nayantara Gold

Nashik · RERA P51600002894

IDBLD_01115112 floorsCompleted
12Sanctioned habitable floorsregistration certificate
31 Dec 2019Revised completionpromised 31 Dec 2018

Floors

12 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P51600002894 · registered 4 Aug 2017
Promised completion
31 Dec 2018
Revised completion
31 Dec 2019
Sanctioned habitable floors
12

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1bhk42.9 m² (462 sq.ft)1not published
1bhk42.9 m² (462 sq.ft)2not published
1bhk46.2 m² (498 sq.ft)2not published
1bhk46.3 m² (498 sq.ft)2not published
1bhk46.3 m² (498 sq.ft)1not published
1bhk46.3 m² (499 sq.ft)2not published
2bhk63.4 m² (683 sq.ft)1not published
2bhk66 m² (711 sq.ft)10not published
2bhk66.2 m² (712 sq.ft)9not published
2bhk69.1 m² (743 sq.ft)1not published
Show all 15 unit typesShow fewer unit types
TypeCarpet areaUnitsBooked
2bhk69.1 m² (744 sq.ft)1not published
2bhk69.1 m² (744 sq.ft)2not published
2bhk69.2 m² (745 sq.ft)3not published
2bhk70.1 m² (754 sq.ft)2not published
2bhk70.1 m² (755 sq.ft)1not published
Total40

Parking

Spaces as declared on MahaRERA's project page.

TypeTwo-wheelerFour-wheelerVisitorTotal
Closed/Covered00010
Open Space00020

Construction progress

Work completed on this building, as the promoter reported it to MahaRERA (Form 1).

  • Excavation100%
  • Basement (if any)0%
  • Podiums (if any)0%
  • Plinth0%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises95%
Show all 11 activitiesShow fewer activities
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology