Vihan Galaxy
Certificate SignedNashik (M Corp.), Nashik 422003 |Promoter: Shree Uma Buildcon
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Others
- Status on MahaRERA
- Certificate Signed
- Buildings
- 1
- Unit types
- 1BHK, 2BHK, Shop35 units in all
- Address
- Plot No. 4, S.no. 241/2/A/1, Dhatrak Phata, Near Lokmanya HospitalPIN 422003
- Designated bank account
- 220
- Developed in phases
- No
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Mar 2026
The latest completion date on record passed 7 months ago.
- Registered
- 3 Jan 2023
- Promised
- 31 Mar 2026
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600048503 | 3 Jan 2023 | 31 Mar 2026 | 31 Mar 2026 | Shree Uma Buildcon | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Vihan Galaxy | 9 | 35 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
19 of 35 units booked (54%), as the promoter reported to MahaRERA
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 38.57 sq m · 415 sq ft | 6 | 5 |
| 2BHK | 46.77 sq m · 503 sq ft | 7 | 3 |
| 2BHK | 47.71 sq m · 514 sq ft | 7 | 3 |
| 2BHK | 54.27 sq m · 584 sq ft | 6 | 6 |
| Shop | 13.53 sq m · 146 sq ft | 1 | 1 |
| Shop | 16.29 sq m · 175 sq ft | 1 | 0 |
| Shop | 18.02 sq m · 194 sq ft | 1 | 0 |
| Shop | 20.41 sq m · 220 sq ft | 1 | 0 |
Show all 13 unit rowsShow fewer unit rows
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| Shop | 20.98 sq m · 226 sq ft | 1 | 1 |
| Shop | 24.43 sq m · 263 sq ft | 1 | 0 |
| Shop | 25 sq m · 269 sq ft | 1 | 0 |
| Shop | 26.57 sq m · 286 sq ft | 1 | 0 |
| Shop | 27.55 sq m · 297 sq ft | 1 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Documents
1 document held by Deedo, 51 filings listed on MahaRERA's project page
Finance
- PAN Cardpancard sub 1.pdf · uploaded 14 Nov 2022Source
Legal
Migrated
- 1 PAN Cardpancard sub 1.pdf · uploaded 14 Nov 2022Source
- 1 Copy of the legal title reportTITLE SEARCH_compressed.pdf · uploaded 14 Nov 2022Source
- 1 Copy of Layout Approval (in case of layout)LAYOUT (1)_rotated.pdf · uploaded 14 Nov 2022Source
- 1 Commencement Certificates / NA Order for plotted developmentSUB CC_compressed.pdf · uploaded 14 Nov 2022Source
Show all 52 documentsShow fewer documents
Migrated
- 1 Declaration about Commencement CertificateFORMAT D RERA.PDF · uploaded 14 Nov 2022Source
- 1 Declaration in FORM BFORM-B SHREE UMA BUILDCON - SCAN.PDF · uploaded 14 Nov 2022Source
- 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECT CERTIFICATE.PDF · uploaded 14 Nov 2022Source
- 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEER CERTIFICATE.PDF · uploaded 14 Nov 2022Source
- 1 CERSAI detailsCERSAI_Search_Report_200252094077_For_Asset_Based_Search_14_11_2022_19_03_16_815.pdf · uploaded 14 Nov 2022Source
- 1 Proforma of Agreement for saleagreement-vihan galaxy-1.pdf · uploaded 14 Nov 2022Source
- 1 Proforma of Allotment letterallotment letter-vihan galaxy.pdf · uploaded 14 Nov 2022Source
- 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameUNDERTAKING OF SEPERATE BANK AC-.PDF · uploaded 14 Nov 2022Source
- 1 Deviation Report with respect to Allotment letterUNDERTAKING ALLOTMENT LETTER.PDF · uploaded 14 Nov 2022Source
- 1 Deviation Report with respect to model copy of AgreementUNDERTAKING AGREEMENT TO SALE.PDF · uploaded 14 Nov 2022Source
- 1 a Details of encumbrances concerned to FinanceENCUMBRANCE CERTIFICATE - LEGAL.PDF · uploaded 15 Nov 2022Source
- 1 b Details of encumbrances concerned to LegalENCUMBRANCE CERTIFICATE - LEGAL.PDF · uploaded 15 Nov 2022Source
- 1 Building Plan Approval / NA Order for plotted developmentBUILDING PLAN_rotated.pdf · uploaded 15 Nov 2022Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA CERTIFICATE_compressed.pdf · uploaded 15 Nov 2022Source
- 2 a Details of encumbrances concerned to FinanceENCUMBRANCE CERTIFICATE - FINANCE - DONE.pdf · uploaded 25 Nov 2022Source
- 2 b Details of encumbrances concerned to LegalENCUMBRANCE CERTIFICATE - FINANCE - DONE.pdf · uploaded 25 Nov 2022Source
- 2 CERSAI detailsCERSAI - DONE LATEST.pdf · uploaded 16 Dec 2022Source
- 1 Disclosure of sold/ booked inventoryINVENTORY MARCH 23.pdf · uploaded 5 Aug 2023Source
- 2 Disclosure of sold/ booked inventoryDISCLOSER OF INVENTORY JUNE 23.pdf · uploaded 5 Aug 2023Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q4 FY 22-23.pdf · uploaded 12 Aug 2023Source
- 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q1 FY 23-24.pdf · uploaded 12 Aug 2023Source
- 3 Disclosure of sold/ booked inventoryDISCLOSER OF INVENTORY SEP 23.pdf · uploaded 19 Oct 2023Source
- 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q2 FY 23-24.pdf · uploaded 12 Nov 2023Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2022-23)FORM 5 FY 22-23 SHREE UMA BUILDCON.pdf · uploaded 17 Nov 2023Source
- 4 Disclosure of sold/ booked inventoryDISCLOSER OF INVENTORY DEC 23.pdf · uploaded 30 Jan 2024Source
- 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q3 FY 23-24.pdf · uploaded 30 Jan 2024Source
- 5 Disclosure of sold/ booked inventoryDISCLOSER OF INVENTORY MARCH 24.pdf · uploaded 18 Apr 2024Source
- 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q4 FY 23-24.pdf · uploaded 18 Apr 2024Source
- 6 Disclosure of sold/ booked inventoryDISCLOSER OF INVENTORY JUNE 24.pdf · uploaded 10 Aug 2024Source
- 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q1 FY 24-25.pdf · uploaded 10 Aug 2024Source
- 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q2 FY 24-25.pdf · uploaded 19 Oct 2024Source
- 2 Disclosure of sold/ booked inventoryDISCLOSER OF INVENTORY SEP 24.pdf · uploaded 19 Oct 2024Source
- 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)FORM 2 A NEW FY 2023-2024.pdf · uploaded 28 Nov 2024Source
- 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)FORM 5 FY 2023-2024 VIHAN GALAXY.pdf · uploaded 28 Nov 2024Source
- 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)SELF CLARIFICATION Q3 FY 24-25.pdf · uploaded 27 Jan 2025Source
- 1 Disclosure of sold/ booked inventoryDISCLOSER OF INVENTORY DEC 24.pdf · uploaded 28 Jan 2025Source
- Occupational CertificateCOMPLECTION SUB.pdf · uploaded 17 Jul 2025Source
- Occupational CertificateNMC MAIL.pdf · uploaded 17 Jul 2025Source
- Form 5 (FY 2024-2025)FORM 5 SHREE UMA BUILDCON.pdf · uploaded 7 Oct 2025Source
- Occupational CertificateNMC MAIL.pdf · uploaded 8 Oct 2025Source
Technical
Technical (Architect)
- DocumentARCHITECT CERTIFICATE.PDF · uploaded 14 Nov 2022Source
Technical (Engineer)
- DocumentENGINEER CERTIFICATE.PDF · uploaded 14 Nov 2022Source
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Nashik (M Corp.), Nashik taluka
Survey, CTS, gat or plot numbers
Boundaries
- North
- Plot No 3
- South
- Plot No 5
- East
- 18 Mtr Wide Road
- West
- Plot No 7 And 8
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Abhishek Kasliwal | — |
| Chartered accountant | Dilip Shantilal Patel | — |
| Chartered accountant | Maya Dixitkumar Ramani | — |
| Engineer | Rajendra Gokulnath Birla | — |
Source: MahaRERA project page. Contact details are not shown.