Siddhivinayak Residency
CompletedNashik (M Corp.), Nashik 422012 |Promoter: M/S. Siddhi Vinayak Construction
Project summary
As registered with MahaRERA and published on its project page
- Project type
- Residential / Group Housing
- Status on MahaRERA
- Completed
- Buildings
- 1
- Unit types
- Residential16 units in all
- Land area for this project
- 363 sq m (3,905 sq ft)
- Permissible built-up area
- 581 sq m (6,251 sq ft)
- Sanctioned built-up area
- 581 sq m (6,251 sq ft)
- Recreational open space
- 50 sq m (538 sq ft)
- Address
- Plot No 31 Survey No 197/4/A, Mauje Pimpalgaon Bahula, Nashik Municipal CorporationPIN 422012
- Designated bank account
- Dombivli Nagari Sahakari Bank Limited
- Litigation declared by promoter
- None declared
- Financial encumbrance declared
- None declared
Location
Coordinates as published by MahaRERA
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Aug 2018
The latest completion date on record passed 8 years and 2 months ago.
- Registered
- 9 Apr 2018
- Promised
- 31 Aug 2018
RERA registration
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600015942 | 9 Apr 2018 | 31 Aug 2018 | — | M/S. Siddhi Vinayak Construction | Project page |
1 building
Buildings and wings named in the registration
| Building | Sanctioned floors | Units |
|---|---|---|
| Siddhivinayak Residency | 9 | 16 |
Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.
Units and parking
16 units registered
| Type | Carpet area | Units |
|---|---|---|
| Residential | 40.88 sq m · 440 sq ft | 16 |
Parking
| Type | Two-wheeler | Four-wheeler | Bus | Visitor | Total |
|---|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 | 8 |
| Open Space | 0 | 0 | 0 | 0 | 0 |
Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.
Construction progress
Work completed, as the promoter reported it to MahaRERA (Form 1)
Siddhivinayak Residency
Common areas and amenities
Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.
Documents
15 documents held by Deedo, 21 filings listed on MahaRERA's project page
Document library
- Proforma of Allotment letterAGREEMENT FOR SADE.pdf · uploaded 20 Mar 2018View
- Copy of the legal title reportTITLE CERTIFICATE.pdf · uploaded 20 Mar 2018View
- Copy of Layout Approval (in case of layout)SANCTION PLAN.pdf · uploaded 20 Mar 2018View
- Copy of Layout Approval (in case of layout)FLOOR PLANS.pdf · uploaded 20 Mar 2018View
- Certificates of Architect (Form 1)(Mandatory for only ongoing project)ARCHITECT CERTIFICATE FORM 1.pdf · uploaded 20 Mar 2018View
- Building Plan Approval (IOD)CONSTRUCTION PERMISION.pdf · uploaded 20 Mar 2018View
- Building Plan Approval (IOD)DEVELOPMENT RIGHT CERTIFICATE.pdf · uploaded 20 Mar 2018View
- Commencement Certificates / NA Order for plotted developmentCONSTRUCTION PERMISION.pdf · uploaded 20 Mar 2018View
- Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENGINEER CERTIFICATE FORM 2.pdf · uploaded 20 Mar 2018View
- Details of encumbrancesSALE DEED.pdf · uploaded 20 Mar 2018View
- Details of encumbrancesNon Encumbrance Declaration.pdf · uploaded 24 Mar 2018View
- Declaration in FORM BForm B Declaration.pdf · uploaded 24 Mar 2018View
- Architect’s Certificate on Completion of Project (Form 4)Architect Certificate.pdf · uploaded 25 Nov 2019View
- Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentArchitect Certificate.pdf · uploaded 25 Nov 2019View
Promoter documents
Technical documents
Proforma allotment letter
- Proforma allotment letterAGREEMENT FOR SADE.pdfView
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Nashik (M Corp.), Nashik taluka
Survey, CTS, gat or plot numbers
As published on MahaRERA's project page
PLOT NO 31 SURVEY NO 197/4/A
Boundaries
- North
- 30 Ft Road
- South
- Gut No 198
- East
- Gut No 196
- West
- Plot No 30
Source: registration certificates and MahaRERA's project page, as stated there.
Professionals
Architects, engineers, chartered accountants and agents named on the registration
| Role | Name | Registration no. |
|---|---|---|
| Architect | Deepak B Magar | — |
Source: MahaRERA project page. Contact details are not shown.