Shyam Plaza

Completed

Nashik (M Corp.), Nashik 422003 |Promoter: Ramdev Construction

Residential / Group HousingRERAP51600023180
5 Dec 2019Registered with MahaRERA
1 Nov 2023Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Land area for this project
603 sq m (6,488 sq ft)
Permissible built-up area
961 sq m (10,346 sq ft)
Sanctioned built-up area
961 sq m (10,346 sq ft)
Address
Plot No 1 S No 52/7 Makhamalabad, Makhamalabad Shiwar, Makhamalabad RoadPIN 422003
Designated bank account
Hdfc Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.86430, 74.93490
Shyam Plaza is at latitude 20.86430, longitude 74.93490.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 1 Nov 2023

The latest completion date on record passed 2 years and 11 months ago.

Registered
5 Dec 2019
Promised
1 Nov 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000231805 Dec 20191 Nov 2023—Ramdev ConstructionProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shyam Plaza5—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00006
Open Space00004

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shyam Plaza

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)100%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyTAKEN FROM NMC AFTER COMPLETION CERTIFICAT100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)CONNECT TO NMC DRAINAGE LINE100%
  • Storm Water DrainsAS PER NMC RULES100%
  • Landscaping & Tree PlantingAS PER NMC RULES100%
  • Street LightingPROVIDE BY NMC100%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterAS PER NMC RULES100%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER NMC RULES100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER MSEDCL RULES100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingOPEN100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

17 documents held by Deedo, 20 filings listed on MahaRERA's project page

Others

Registration certificate

Document library

  • Building Plan Approval / NA Order for plotted developmentbuilding plan.pdf · uploaded 25 Nov 2019View
  • Commencement Certificates / NA Order for plotted developmentCOMMENCEMENT.pdf · uploaded 25 Nov 2019View
  • Proforma of Allotment letterSHYAM PLAZA AGREEMENT PG NO 1 TO 6.pdf · uploaded 25 Nov 2019View
  • Proforma of Allotment letterSHYAM PLAZA AGREEMENT PG NO 7 TO 10.pdf · uploaded 25 Nov 2019View
  • Proforma of Allotment letterSHYAM PLAZA AGREEMENT PG NO 11 TO 14.pdf · uploaded 25 Nov 2019View
  • Copy of Layout Approval (in case of layout)LAYOUT.pdf · uploaded 25 Nov 2019View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)FORM 1 ARCHITECT.pdf · uploaded 26 Nov 2019View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2 ENGINEER CERTIFICATE.pdf · uploaded 26 Nov 2019View
  • Engineers Certificate on Quality Assurance (Form 2A FY 2019-20)FORM 2 a ENGINEER.pdf · uploaded 26 Nov 2019View
  • Details of encumbrancesNo Encumbrance Certificate.pdf · uploaded 26 Nov 2019View
  • Declaration in FORM BFORM B DECLARATION.pdf · uploaded 3 Dec 2019View
  • Copy of the legal title reporttitle report.pdf · uploaded 3 Dec 2019View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 3 Dec 2019View
  • Architect’s Certificate on Completion of Project (Form 4)FORM 4 SHYAM PLAZA.pdf · uploaded 11 Oct 2021View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCOMPLETION SHYAM PLAZA.pdf · uploaded 11 Oct 2021View

Promoter documents

  • Declaration Form BFORM B DECLARATION.pdf · uploaded 3 Dec 2019View
  • Legal Title reporttitle report.pdf · uploaded 3 Dec 2019View

Technical documents

  • Building Plan Approvalbuilding plan.pdfView
  • Layout ApprovalLAYOUT.pdfView

Proforma allotment letter

  • Proforma allotment letterSHYAM PLAZA AGREEMENT PG NO 7 TO 10.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik (M Corp.), Nashik taluka

Survey, CTS, gat or plot numbers

1PLOT NO 1 S NO 52/7 MAKHAMALABAD

As published on MahaRERA's project page

PLOT NO 1 S NO 52/7 MAKHAMALABAD

Boundaries

North
S No 52 Part
South
Colony Road
East
100 Feet Road
West
Plot No 2

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSwapnil Eknath Bhanage—
Chartered accountantShreyas S Ware—
EngineerRamesh B Wagh—
OtherAshok M Velani—

Source: MahaRERA project page. Contact details are not shown.