Skip to content
Deedo home
Menu

Shriram Heights Apartment

Completed

Nashik (M Corp.), Nashik 422003 |Promoter: Rudra Builders and Developers

23 Jul 2018Registered with MahaRERA
2 Apr 2025Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Completed
Buildings
1
Land area for this project
1,258 sq m (13,546 sq ft)
Permissible built-up area
4,797 sq m (51,637 sq ft)
Sanctioned built-up area
1,966 sq m (21,163 sq ft)
Address
Survey no 277/1/2 plus 277/2/1 plus 278/2/1/2, Aurangabad Road, PanchavatiPIN 422003
Designated bank account
Punjab National Bank
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 2 Apr 2025

The latest completion date on record passed 1 year and 6 months ago.

Registered
23 Jul 2018
Promised
2 Apr 2025

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160001719823 Jul 20182 Apr 2025—Rudra Builders and DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shriram Heights Apartment10—

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

0 units registered

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00001
Open Space000032

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shriram Heights Apartment

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyTo be joined to NMC line0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)To be joined to NMC line0%
  • Storm Water DrainsTo be joined to NMC line0%
  • Landscaping & Tree PlantingNot applicable
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRain water harvesting pit to be joined to borewell0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsTo be completed at final stage30%
  • Electrical meter room, sub-station, receiving stationNot applicable
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingTo be completed at final stage0%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

13 documents held by Deedo, 15 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Occupancy / completion certificate

  • Occupancy / completion certificate3 Dec 2020ViewSource

Registration certificate

Form 5

Form 4

Show all 28 documentsShow fewer documents

Other (2)

Layout plan

Building plan

Allotment letter

Document library

  • Details of encumbrancesEMC.pdf · uploaded 13 Jul 2018View
  • Copy of the legal title reporttitle.pdf · uploaded 13 Jul 2018View
  • Building Plan Approval (IOD)PLAN.pdf · uploaded 13 Jul 2018View
  • Proforma of Allotment letterAgreement.pdf · uploaded 13 Jul 2018View
  • Commencement Certificates / NA Order for plotted developmentCC.pdf · uploaded 13 Jul 2018View
  • Copy of Layout Approval (in case of layout)layout.pdf · uploaded 13 Jul 2018View
  • Declaration in FORM Baffidavit.pdf · uploaded 13 Jul 2018View
  • Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentShriram Completion certificate.pdf · uploaded 3 Dec 2020View
  • Architect’s Certificate on Completion of Project (Form 4)RBD Arch Form 4.pdf · uploaded 4 Jun 2022View
  • Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)RBD CA Form 5.pdf · uploaded 4 Jun 2022View

Promoter documents

  • Legal Title reporttitle.pdf · uploaded 13 Jul 2018View
  • Declaration Form Baffidavit.pdf · uploaded 13 Jul 2018View

Technical documents

  • Layout Approvallayout.pdfView
  • Building Plan ApprovalPLAN.pdfView

Proforma allotment letter

  • Proforma allotment letterAgreement.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik (M Corp.), Nashik taluka

Survey, CTS, gat or plot numbers

Survey no 277/1/2 plus 277/2/1 plus 278/2/1/2

As published on MahaRERA's project page

Survey no 277/1/2 plus 277/2/1 plus 278/2/1/2

Boundaries

North
plot no 17
South
plot no 14
East
Plot no 15
West
12 meter road

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPankaj Jadhav—
EngineerBhavesh Patel—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology