Skip to content

Shreeram Castle

Completed

Nashik (M Corp.), Nashik 422002 |Promoter: Shreeram Builders And Developers

Residential / Group HousingRERAP51600006998
17 Aug 2017Registered with MahaRERA
31 Jul 2018Promised completion
1Building
18Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
2BHK, 3BHK18 units in all
Land area for this project
932 sq m (10,037 sq ft)
Permissible built-up area
1,305 sq m (14,052 sq ft)
Sanctioned built-up area
1,106 sq m (11,910 sq ft)
Address
Plot 5, 9, 10 S No 599/ 1 C /1 D / 1 E/2/1/2 And 2/1/3/9PIN 422002
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.05517, 72.82995
Shreeram Castle is at latitude 19.05517, longitude 72.82995.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Jul 2018

The latest completion date on record passed 8 years and 3 months ago.

Registered
17 Aug 2017
Promised
31 Jul 2018

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160000699817 Aug 201731 Jul 2018—Shreeram Builders And DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Shreeram Castle618

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

18 units registered

2BHK · 9 units3BHK · 9 units
TypeCarpet areaUnits
2BHK38.61 sq m · 416 sq ft1
2BHK42.71 sq m · 460 sq ft1
2BHK42.92 sq m · 462 sq ft1
2BHK52.04 sq m · 560 sq ft3
2BHK52.25 sq m · 562 sq ft3
3BHK62.78 sq m · 676 sq ft3
3BHK66.66 sq m · 718 sq ft3
3BHK66.84 sq m · 719 sq ft3

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered000045
Open Space00000

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Shreeram Castle

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure100%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
  • Sanitary Fittings within the flats / premises100%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyCOMPLETED100%
  • Sewerage (Chamber, Lines, Septic Tank , STP)COMPLETED100%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingCOMPLETED100%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingCOMPLETED100%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationCOMPLETED100%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingCOMPLETED100%

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

14 documents held by Deedo, 17 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Form 1

Form 2

Registration certificate

Form 4

Show all 31 documentsShow fewer documents

Other (3)

Layout plan

Building plan

Allotment letter

Document library

  • Building Plan Approval (IOD)Plan Certificate.pdf · uploaded 30 Jul 2017View
  • Copy of Layout Approval (in case of layout)Layout.pdf · uploaded 30 Jul 2017View
  • Declaration in FORM BForm b.pdf · uploaded 30 Jul 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1.pdf · uploaded 30 Jul 2017View
  • Commencement Certificates / NA Order for plotted developmentcommencement cert.pdf · uploaded 30 Jul 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2.pdf · uploaded 30 Jul 2017View
  • Copy of the legal title reportLegal Title certificate.pdf · uploaded 30 Jul 2017View
  • Proforma of Allotment letterPROFORMA ALLOTMENT LETTER.pdf · uploaded 30 Jul 2017View
  • Details of encumbrancesNo Encumbrances Certificate.pdf · uploaded 30 Jul 2017View
  • OtherOther submissions.pdf · uploaded 30 Jul 2017View
  • Architect’s Certificate on Completion of Project (Form 4)form4.pdf · uploaded 23 Dec 2019View

Promoter documents

  • Declaration Form BForm b.pdf · uploaded 30 Jul 2017View
  • Legal Title reportLegal Title certificate.pdf · uploaded 30 Jul 2017View

Technical documents

  • Layout ApprovalLayout.pdfView
  • Building Plan ApprovalPlan Certificate.pdfView

Other legal documents

  • OtherOther submissions.pdfView

Proforma allotment letter

  • Proforma allotment letterPROFORMA ALLOTMENT LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik (M Corp.), Nashik taluka

Survey, CTS, gat or plot numbers

1010 S NO 599/ 1 C /1 D / 1 E/2/1/22/1/3/9599PLOT 5

As published on MahaRERA's project page

PLOT 5, 9, 10 S NO 599/ 1 C /1 D / 1 E/2/1/2 AND 2/1/3/9

Boundaries

North
Plot No 3 S No 599 1 K 1 D 1 E 1
South
S No 599 Remaining Area
East
Plot No 4 And 8 And Road
West
Nasardi River

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectRavi Amrutkar—
EngineerVidyadhar Saraf—

Source: MahaRERA project page. Contact details are not shown.