Certificate Signed

Nashik (M Corp.), Nashik 422007 |Promoter: Sanjay Kashinath Sayankar

3 May 2023Registered with MahaRERA
31 Dec 2027Promised completion
30 Apr 2028Revised completionPushed back 4 months
2Buildings
105Units registered26 booked (25%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
2
Unit types
1BHK, 2BHK, Shop105 units in all
Address
Survey No.365, CTS No.6886, Satpur Shivar, Nashik, Old Panvat Road, Sant Savtamali Marg, SatpurPIN 422007
Designated bank account
154
Developed in phases
Yes

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.98599, 73.73230
Laxman Complex is at latitude 19.98599, longitude 73.73230.

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 4 months

Registered
3 May 2023
Promised
31 Dec 2027
Revised
30 Apr 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000508103 May 202331 Dec 202730 Apr 2028Sanjay Kashinath SayankarProject page

2 buildings

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Laxman Complex Wing A758
Laxman Complex Wing B747

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

26 of 105 units booked (25%), as the promoter reported to MahaRERA

1BHK · 42 units2BHK · 48 unitsShop · 15 units
BuildingTypeCarpet areaUnitsBooked
Laxman Complex Wing A1BHK29.54 sq m · 318 sq ft75
Laxman Complex Wing A1BHK36.02 sq m · 388 sq ft65
Laxman Complex Wing A1BHK36.03 sq m · 388 sq ft11
Laxman Complex Wing A2BHK49.69 sq m · 535 sq ft60
Laxman Complex Wing A2BHK51.47 sq m · 554 sq ft63
Laxman Complex Wing A2BHK51.65 sq m · 556 sq ft10
Laxman Complex Wing A2BHK51.96 sq m · 559 sq ft10
Laxman Complex Wing A2BHK52.02 sq m · 560 sq ft63
Show all 31 unit rowsShow fewer unit rows
BuildingTypeCarpet areaUnitsBooked
Laxman Complex Wing A2BHK53.5 sq m · 576 sq ft64
Laxman Complex Wing A2BHK53.65 sq m · 577 sq ft11
Laxman Complex Wing A2BHK55.69 sq m · 599 sq ft10
Laxman Complex Wing A2BHK55.7 sq m · 600 sq ft62
Laxman Complex Wing AShop8.5 sq m · 91 sq ft11
Laxman Complex Wing AShop10.16 sq m · 109 sq ft10
Laxman Complex Wing AShop12.73 sq m · 137 sq ft10
Laxman Complex Wing AShop13.13 sq m · 141 sq ft10
Laxman Complex Wing AShop13.23 sq m · 142 sq ft10
Laxman Complex Wing AShop13.72 sq m · 148 sq ft10
Laxman Complex Wing AShop13.85 sq m · 149 sq ft10
Laxman Complex Wing AShop14.65 sq m · 158 sq ft10
Laxman Complex Wing AShop15.14 sq m · 163 sq ft10
Laxman Complex Wing AShop15.15 sq m · 163 sq ft10
Laxman Complex Wing B1BHK29.92 sq m · 322 sq ft140
Laxman Complex Wing B1BHK29.95 sq m · 322 sq ft140
Laxman Complex Wing B2BHK48.91 sq m · 526 sq ft71
Laxman Complex Wing B2BHK48.98 sq m · 527 sq ft70
Laxman Complex Wing BShop8.63 sq m · 93 sq ft10
Laxman Complex Wing BShop11.02 sq m · 119 sq ft10
Laxman Complex Wing BShop11.31 sq m · 122 sq ft10
Laxman Complex Wing BShop13.6 sq m · 146 sq ft10
Laxman Complex Wing BShop14.47 sq m · 156 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 97 filings listed on MahaRERA's project page

Registration certificate

Finance

  • PAN CardPAN.pdf · uploaded 16 Apr 2023Source

Legal

  • Legal Title reportTitle Report.pdf · uploaded 16 Apr 2023Source
  • Declaration Form BForm-B-Builder.pdf · uploaded 16 Apr 2023Source

Migrated

  • 1 PAN CardPAN.pdf · uploaded 16 Apr 2023Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 16 Apr 2023Source
  • 1 a Details of encumbrances concerned to FinanceEC-Finance.pdf · uploaded 16 Apr 2023Source
  • 2 a Details of encumbrances concerned to FinanceEC-Legal.pdf · uploaded 16 Apr 2023Source
Show all 98 documentsShow fewer documents

Migrated

  • 1 b Details of encumbrances concerned to LegalEC-Finance.pdf · uploaded 16 Apr 2023Source
  • 2 b Details of encumbrances concerned to LegalEC-Legal.pdf · uploaded 16 Apr 2023Source
  • 1 Copy of Layout Approval (in case of layout)Building Pla n.pdf · uploaded 16 Apr 2023Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Pla n.pdf · uploaded 16 Apr 2023Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 16 Apr 2023Source
  • 1 Declaration in FORM BForm-B-Builder.pdf · uploaded 16 Apr 2023Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 16 Apr 2023Source
  • 1 Disclosure of Interest in Other Real Estate OrganizationsSanjay Sayankar-Annexure A-Disclosure of Interest.pdf · uploaded 16 Apr 2023Source
  • 1 Proforma of Allotment letterAllotment Letter.pdf · uploaded 16 Apr 2023Source
  • 1 Separate Bank Account details including no encumbrances on the Bank Account or no escrow on the sameSeparate Bank Account Declaration.pdf · uploaded 16 Apr 2023Source
  • 1 Deviation Report with respect to Allotment letterDeviation-Allotment Letter.pdf · uploaded 16 Apr 2023Source
  • 1 Deviation Report with respect to model copy of AgreementDeviation-Agreement for Sale.pdf · uploaded 16 Apr 2023Source
  • 1 Declaration about Commencement CertificateDeclaration for Commencement.pdf · uploaded 21 Apr 2023Source
  • 1 CERSAI detailsCERSAI.pdf · uploaded 25 Apr 2023Source
  • 1 Proforma of Agreement for saleAFS.pdf · uploaded 25 Apr 2023Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Laxman Architect Certificate September 2023.pdf · uploaded 20 Jan 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Laxman Architect Certificate June 2023.pdf · uploaded 20 Jan 2024Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Laxman Complex-Form-1-Dec 2023.pdf · uploaded 20 Jan 2024Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Laxman Complex-Engineer Certificate-Sept 23.pdf · uploaded 20 Jan 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Laxman Engineer Certificate June 2023.pdf · uploaded 20 Jan 2024Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Laxman Complex-Form-2-Dec 2023.pdf · uploaded 20 Jan 2024Source
  • 1 Disclosure of sold/ booked inventoryLaxman Complex-Disclosure-Sept 2023.pdf · uploaded 20 Jan 2024Source
  • 2 Disclosure of sold/ booked inventoryLaxman Complex-Disclosure-Dec 2023.pdf · uploaded 20 Jan 2024Source
  • 3 Disclosure of sold/ booked inventoryLaxman Complex-Disclosure-June 2023.pdf · uploaded 20 Jan 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Laxman Complex-CA Certificate-Sept 2023.pdf · uploaded 20 Jan 2024Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Laxman Complex-CA Certificate-June 2023.pdf · uploaded 20 Jan 2024Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Laxman Complex-CA certificate-Dec 2023.pdf · uploaded 20 Jan 2024Source
  • 2 Copy of Layout Approval (in case of layout)Laxman Complex Revised Sanction Plan 1.pdf · uploaded 10 Feb 2024Source
  • 3 Copy of Layout Approval (in case of layout)Laxman Complex Revised Sanction Plan 2.pdf · uploaded 10 Feb 2024Source
  • 2 Building Plan Approval / NA Order for plotted developmentLaxman Complex Revised Sanction Plan 1.pdf · uploaded 10 Feb 2024Source
  • 3 Building Plan Approval / NA Order for plotted developmentLaxman Complex Revised Sanction Plan 2.pdf · uploaded 10 Feb 2024Source
  • 2 Commencement Certificates / NA Order for plotted developmentRevised Commencement Laxman Complex.pdf · uploaded 10 Feb 2024Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architects Certificate-Laxman Complex.pdf · uploaded 20 Apr 2024Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Engineer Certificate Laxman Complex.pdf · uploaded 20 Apr 2024Source
  • 4 Disclosure of sold/ booked inventoryDisclosure of Units.pdf · uploaded 20 Apr 2024Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)Laxman Complex CA certificate.pdf · uploaded 20 Apr 2024Source
  • 1 Other – TechnicalEngineer certificate for quality.pdf · uploaded 20 Apr 2024Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate laxman .pdf · uploaded 20 Jul 2024Source
  • 5 Disclosure of sold/ booked inventoryDisclosure of inventory laxman.pdf · uploaded 20 Jul 2024Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Laxman Engineer Certificate.pdf · uploaded 13 Aug 2024Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 13 Aug 2024Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 21 Oct 2024Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 21 Oct 2024Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 21 Oct 2024Source
  • 2 Disclosure of sold/ booked inventoryDisclosure of Units.pdf · uploaded 21 Oct 2024Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2023-24)Laxman Complex RA F Y 23-24.pdf · uploaded 6 Dec 2024Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 20 Jan 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 20 Jan 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 20 Jan 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Units.pdf · uploaded 20 Jan 2025Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2023-24)Form 2A Laxman Complex.pdf · uploaded 20 Jan 2025Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 19 Apr 2025Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Laxman Complex.pdf · uploaded 19 Apr 2025Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 19 Apr 2025Source
  • 1 Disclosure of sold/ booked inventoryDisclosure of Units.pdf · uploaded 19 Apr 2025Source
  • Form 1Architect Certificate Laxman.pdf · uploaded 27 Sep 2025Source
  • Form 2Engineer Certificate Laxman.pdf · uploaded 27 Sep 2025Source
  • Form 3CA Certificate-Laxman Complex.pdf · uploaded 27 Sep 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Inventory Laxman.pdf · uploaded 27 Sep 2025Source
  • Form 1Form-1-Laxman Complex.pdf · uploaded 31 Dec 2025Source
  • Form 2Form-2-Laxman Complex.pdf · uploaded 31 Dec 2025Source
  • Form 3Form-3-Laxman Complex.pdf · uploaded 31 Dec 2025Source
  • Disclosure of Sold and Booked InventoryDisclosure of Units-Laxman Complex.pdf · uploaded 31 Dec 2025Source
  • Form 5 (FY 2024-2025)Form 5 F Y 24-25.pdf · uploaded 1 Feb 2026Source
  • Form 1Form 1-Dec 2025.pdf · uploaded 8 Mar 2026Source
  • Form 2Form 2-Dec 2025.pdf · uploaded 8 Mar 2026Source
  • Form 3Form 3-Dec 2025.pdf · uploaded 8 Mar 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Units-Dec 2025.pdf · uploaded 8 Mar 2026Source
  • Form 2A (FY 2023-2024)Form 2A-March 2024.pdf · uploaded 26 May 2026Source
  • Form 2A (FY 2024-2025)Form 2A-March 2025.pdf · uploaded 26 May 2026Source
  • Form 2A (FY 2025-2026)Form 2A-March 2026.pdf · uploaded 26 May 2026Source
  • Form 1Form 1 March 2026.pdf · uploaded 22 Jun 2026Source
  • Form 2Form 2 March 2026.pdf · uploaded 22 Jun 2026Source
  • Form 3Form 3 March 2026.pdf · uploaded 22 Jun 2026Source
  • Disclosure of Sold and Booked InventoryDisclosure of Units-March 2026.pdf · uploaded 22 Jun 2026Source

Technical

  • DocumentBuilding Pla n.pdf · uploaded 16 Apr 2023Source
  • DocumentBuilding Pla n.pdf · uploaded 16 Apr 2023Source
  • DocumentLaxman Complex Revised Sanction Plan 1.pdf · uploaded 10 Feb 2024Source
  • DocumentLaxman Complex Revised Sanction Plan 2.pdf · uploaded 10 Feb 2024Source
  • DocumentLaxman Complex Revised Sanction Plan 1.pdf · uploaded 10 Feb 2024Source
  • DocumentLaxman Complex Revised Sanction Plan 2.pdf · uploaded 10 Feb 2024Source
  • Other – TechnicalEngineer certificate for quality.pdf · uploaded 20 Apr 2024Source

Technical (Architect)

  • DocumentArchitect Certificate laxman .pdf · uploaded 20 Jul 2024Source
  • DocumentForm 1.pdf · uploaded 21 Oct 2024Source
  • DocumentForm 1.pdf · uploaded 20 Jan 2025Source
  • DocumentForm 1.pdf · uploaded 19 Apr 2025Source

Technical (Engineer)

  • DocumentLaxman Engineer Certificate.pdf · uploaded 13 Aug 2024Source
  • DocumentForm 2.pdf · uploaded 21 Oct 2024Source
  • DocumentForm 2.pdf · uploaded 20 Jan 2025Source
  • DocumentForm 2.pdf · uploaded 19 Apr 2025Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik (M Corp.), Nashik taluka

Survey, CTS, gat or plot numbers

CTS No.6886Survey No.365

Boundaries

North
Gat No 362
South
Gat No 366
East
18 Mtrs D P Road
West
Gat No 364

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectSanjay Sayankar—
Chartered accountantCA Jivan Sangle—
EngineerRohan Kiran Gumare—
EngineerSagar Ipar—
OtherSagar Kailash Ipar—
OtherSuresh Jadhav—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology