Kulashree Nest

Completed

Nashik (M Corp.), Nashik 422010 |Promoter: Kulshree Developers

Residential / Group HousingRERAP51600013530
9 Oct 2017Registered with MahaRERA
31 Dec 2017Promised completion
1Building
15Units registered
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Completed
Buildings
1
Unit types
Residencial15 units in all
Land area for this project
419 sq m (4,513 sq ft)
Permissible built-up area
579 sq m (6,234 sq ft)
Sanctioned built-up area
579 sq m (6,234 sq ft)
Address
Plot No 40, 41 S.no.7/1-8PIN 422010
Designated bank account
Tjsb Sahakari Bank Ltd
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 19.07935, 72.99920
Kulashree Nest is at latitude 19.07935, longitude 72.99920.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2017

The latest completion date on record passed 8 years and 10 months ago.

Registered
9 Oct 2017
Promised
31 Dec 2017

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000135309 Oct 201731 Dec 2017—Kulshree DevelopersProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Kulashree Nest415

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

15 units registered

Residencial · 15 units
TypeCarpet areaUnits
Residencial356.59 sq m · 3,838 sq ft15

Parking

TypeTwo-wheelerFour-wheelerBusVisitorTotal
Closed/Covered00004
Open Space00005

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Kulashree Nest

  • Excavation100%
  • Basement (if any)100%
  • Podiums (if any)0%
  • Plinth100%
  • Stilt Floor100%
  • Slabs of Super Structure0%
Show all 11 activitiesShow fewer activities
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises90%
  • Sanitary Fittings within the flats / premises75%
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks85%
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.90%
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.70%

Common areas and amenities

  • Internal Roads & FootpathsNot applicable
  • Water SupplyNMC WATER CONNECTION80%
  • Sewerage (Chamber, Lines, Septic Tank , STP)WILL BE COMPLETED BEFORE COMPLETION80%
  • Storm Water DrainsNot applicable
  • Landscaping & Tree PlantingAS PER NMC RULE100%
  • Street LightingNot applicable
Show all 15 activitiesShow fewer activities
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterNot applicable
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingRAIN WATER HARWESTING85%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationELECTRICAL METER BOX75%
  • Aggregate area of recreational Open SpaceNot applicable
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

15 documents held by Deedo, 16 filings listed on MahaRERA's project page

Title report

Encumbrance details

Commencement certificate

Form B

Form 1

Form 2

Allotment letter (2)

Show all 31 documentsShow fewer documents

Registration certificate

Form 4

Other (4)

Layout plan

Document library

  • Declaration in FORM BDeclaration in Form B.pdf · uploaded 28 Sep 2017View
  • Details of encumbrancesCertificate of Encumbrances.pdf · uploaded 28 Sep 2017View
  • Certificates of Architect (Form 1)(Mandatory for only ongoing project)Architect Certificate Form 1.pdf · uploaded 28 Sep 2017View
  • Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Certificate of Engineer form 2.pdf · uploaded 28 Sep 2017View
  • Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 28 Sep 2017View
  • Copy of the legal title reportTitle Search.pdf · uploaded 28 Sep 2017View
  • Building Plan Approval (IOD)Building Plan.pdf · uploaded 28 Sep 2017View
  • Proforma of Allotment letterAllotment Letter.pdf · uploaded 28 Sep 2017View
  • Proforma of Allotment letterAgreement (1).pdf · uploaded 28 Sep 2017View
  • Copy of Layout Approval (in case of layout)Building Plan.pdf · uploaded 28 Sep 2017View
  • Certificates of Architect (Form 4)Form 4.pdf · uploaded 24 Jun 2019View

Promoter documents

  • Declaration Form BDeclaration in Form B.pdf · uploaded 28 Sep 2017View
  • Legal Title reportTitle Search.pdf · uploaded 28 Sep 2017View

Technical documents

  • Building Plan ApprovalBuilding Plan.pdfView
  • Layout ApprovalBuilding Plan.pdfView

Proforma allotment letter

  • Proforma allotment letterAllotment Letter.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik (M Corp.), Nashik taluka

Survey, CTS, gat or plot numbers

404141 S.NO.7/18PLOT NO 40

As published on MahaRERA's project page

PLOT NO 40,41 S.NO.7/1-8

Boundaries

North
Nala
South
Colony Road
East
Colony Road
West
Nala

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAshok N Jamdar—

Source: MahaRERA project page. Contact details are not shown.

Data through11 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology