Gajanan Annex

Certificate Signed

Nashik (M Corp.), Nashik 422003 |Promoter: Laxmi Associates

11 Aug 2017Registered with MahaRERA
31 Mar 2020Promised completion
1Building
42Units registered38 booked (90%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Shop, Shops42 units in all
Address
Plot no 02, Survey no 54/4/1, Makhmalabad road, MakhmalabadPIN 422003
Designated bank account
85
Developed in phases
No

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 18.52960, 73.87602
Gajanan Annex is at latitude 18.52960, longitude 73.87602.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Mar 2020

The latest completion date on record passed 6 years and 7 months ago.

Registered
11 Aug 2017
Promised
31 Mar 2020

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5160000539311 Aug 201731 Mar 202031 Mar 2020Laxmi AssociatesProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Gajanan Annex842

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

38 of 42 units booked (90%), as the promoter reported to MahaRERA

1BHK · 24 units2BHK · 12 unitsShop · 4 unitsShops · 2 units
TypeCarpet areaUnitsBooked
1BHK41.73 sq m · 449 sq ft22
1BHK42.29 sq m · 455 sq ft1010
1BHK42.52 sq m · 458 sq ft22
1BHK45.23 sq m · 487 sq ft1010
2BHK63.67 sq m · 685 sq ft62
2BHK64.63 sq m · 696 sq ft66
Shop11.7 sq m · 126 sq ft11
Shop13.66 sq m · 147 sq ft11
Show all 11 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
Shop16.46 sq m · 177 sq ft11
Shop18.49 sq m · 199 sq ft11
Shops21 sq m · 226 sq ft22

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

1 document held by Deedo, 25 filings listed on MahaRERA's project page

Registration certificate

Legal

  • Legal Title reportTitle certificate.pdf · uploaded 30 Jul 2017Source
  • Declaration Form BAffidevit.pdf · uploaded 31 Jul 2017Source

Migrated

  • 1 Copy of the legal title reportTitle certificate.pdf · uploaded 30 Jul 2017Source
  • 1 Commencement Certificates / NA Order for plotted developmentC C.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Laxmi PAN.pdf · uploaded 30 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)ENG CER.pdf · uploaded 30 Jul 2017Source
  • 1 Proforma of Allotment letterCCF31072017.pdf · uploaded 30 Jul 2017Source
Show all 26 documentsShow fewer documents

Migrated

  • 1 Details of encumbrancesCCF31072017_0027.pdf · uploaded 31 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout compressed.pdf · uploaded 31 Jul 2017Source
  • 1 Building Plan Approval (IOD)sanctioned plan.pdf · uploaded 31 Jul 2017Source
  • 1 Declaration in FORM BAffidevit.pdf · uploaded 31 Jul 2017Source
  • 1 Certificates of CA (Form 3)CA CER F3.pdf · uploaded 31 Jul 2017Source
  • 2 Details of encumbrancesEmcumbrance letter.pdf · uploaded 17 Nov 2017Source
  • 2 Commencement Certificates / NA Order for plotted developmentNew C C.pdf · uploaded 26 Dec 2017Source
  • 2 Building Plan Approval (IOD)Revised Plan.pdf · uploaded 28 Dec 2017Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion certificate.pdf · uploaded 3 Nov 2020Source
  • 1 Status of ConveyanceApartment dec part 1.pdf · uploaded 3 Nov 2020Source
  • 2 Status of ConveyanceApartment dec part 2.pdf · uploaded 3 Nov 2020Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)FORM 4.pdf · uploaded 7 Feb 2025Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentFull C C.pdf · uploaded 7 Feb 2025Source

Technical

  • Documentsanctioned plan.pdf · uploaded 31 Jul 2017Source
  • DocumentLayout compressed.pdf · uploaded 31 Jul 2017Source
  • DocumentRevised Plan.pdf · uploaded 28 Dec 2017Source

Technical (Architect)

  • DocumentLaxmi PAN.pdf · uploaded 30 Jul 2017Source

Technical (Engineer)

  • DocumentENG CER.pdf · uploaded 30 Jul 2017Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Nashik (M Corp.), Nashik taluka

Survey, CTS, gat or plot numbers

Plot no 02Survey no 54/4/1

Boundaries

North
Plot no 4 and 5
South
30 meter D P road
East
Existing survey no 54 oblige 3
West
Plot no 01

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectPankaj Jadhav—
EngineerPrasana Bhore—
OtherShreeniwas Bijjaram—

Source: MahaRERA project page. Contact details are not shown.