Arya Apartment · Arya Appartment
Nashik (M Corp.) · RERA P51600002981
IDBLD_0111416 floorsCompleted
6Sanctioned habitable floorsregistration certificate
31 Dec 2017Promised completion
Floors
6 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- Sanctioned habitable floors
- 6
Registered transactions
No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| FLAT TYPE 1 | 29.1 m² (313 sq.ft) | 1 | not published |
| FLAT TYPE 10 | 39 m² (420 sq.ft) | 2 | not published |
| FLAT TYPE 11 | 40.9 m² (440 sq.ft) | 1 | not published |
| FLAT TYPE 2 | 34.9 m² (376 sq.ft) | 1 | not published |
| FLAT TYPE 3 | 31.3 m² (337 sq.ft) | 1 | not published |
| FLAT TYPE 4 | 31.4 m² (338 sq.ft) | 4 | not published |
| FLAT TYPE 5 | 18.2 m² (196 sq.ft) | 1 | not published |
| FLAT TYPE 6 | 27.7 m² (298 sq.ft) | 1 | not published |
| FLAT TYPE 7 | 40 m² (431 sq.ft) | 1 | not published |
| FLAT TYPE 8 | 18.2 m² (195 sq.ft) | 1 | not published |
| FLAT TYPE 9 | 25.2 m² (271 sq.ft) | 1 | not published |
| Total | 15 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 9 |
| Open Space | 0 | 0 | 0 | 0 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)0%
- Podiums (if any)0%
- Plinth0%
- Stilt Floor100%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises93%
Show all 11 activitiesShow fewer activities
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.50%
Data through11 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology