Palm Hills
Completion due Dec 2026Gondedumala, Nashik 422403 |Promoter: Sarvppratham Developers Pvt. Ltd..
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion promised for 31 Dec 2024
P51600032143The latest completion date on record passed 1 year and 10 months ago.
- Registered
- 14 Dec 2021
- Promised
- 31 Dec 2024
Completion promised for 31 Dec 2026
P51600054597- Registered
- 31 Jan 2024
- Promised
- 31 Dec 2026
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P51600032143 | 14 Dec 2021 | 31 Dec 2024 | — | Sarvppratham Developers Pvt. Ltd.. | Project page |
| P51600054597 | 31 Jan 2024 | 31 Dec 2026 | — | Sarvppratham Developers Pvt. Ltd.. | Project page |
Documents
2 documents held by Deedo
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Gondedumala
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.