BLD_006153Completed0 floors
Plot · K R Suncity
Khamgaon · RERA P49700013238
0Sanctioned habitable floorsregistration certificate
31 Jul 2019Revised completionpromised 31 Jul 2018
As registered
- RERA registration
- P49700013238 · registered 21 Sep 2017
- Promised completion
- 31 Jul 2018
- Revised completion
- 31 Jul 2019
- Sanctioned habitable floors
- 0
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| PLOT | 0 m² (0 sq.ft) | 0 | not published |
| Total | 0 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 0 |
| Open Space | 0 | 0 | 0 | 0 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation0%
- Basement (if any)0%
- Podiums (if any)0%
- Plinth0%
- Stilt Floor0%
- Slabs of Super Structure0%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises0%
- Sanitary Fittings within the flats / premises0%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks0%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.0%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.0%
Data through8 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology