A5 · Swapna-Niketan by NMC

Wanjara · RERA P50500050570

IDBLD_0578658 floorsExtended 12 mo
8Sanctioned habitable floorsregistration certificate
30 Mar 2026Revised completionpromised 31 Mar 2025
39 of 60Units bookedMahaRERA project page

Floors

8 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50500050570 · registered 21 Apr 2023
Promised completion
31 Mar 2025
Revised completion
30 Mar 2026
Sanctioned habitable floors
8
ProjectId
37,961
ProjectName
Swapna-Niketan by NMC
TotalUnitCount
0
ProjectBuildingId
1,77,143
BuildingNameNumber
A5
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
0
ProjectRegistartionNo
P50500050570
ProjectBuildingWingsId
1,80,600
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
A5
NoOfBuildingWingFloorProposed
8
NoOfBuildingWingFloorHabitable
0
NoOfBuildingWingFloorSanctioned
8

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
1BHK28.1 m² (302 sq.ft)6039
Total6039
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology