BLD_009287Extended 57 mo12 floors
Wing C · Waman Nagari
Pipla · RERA P50500018406
12Sanctioned habitable floorsregistration certificate
31 Dec 2029Revised completionpromised 30 Mar 2025
Floors
12 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.
As registered
- RERA registration
- P50500018406 · registered 30 Oct 2018
- Promised completion
- 30 Mar 2025
- Revised completion
- 31 Dec 2029
- Sanctioned habitable floors
- 12
Unit inventory
Apartments and other units by type, from MahaRERA's project page.
| Type | Carpet area | Units | Booked |
|---|---|---|---|
| 1BHK | 28.9 m² (312 sq.ft) | 10 | not published |
| 2BHK | 42.5 m² (457 sq.ft) | 10 | not published |
| 2BHK | 44.4 m² (478 sq.ft) | 20 | not published |
| Total | 40 |
Parking
Spaces as declared on MahaRERA's project page.
| Type | Two-wheeler | Four-wheeler | Visitor | Total |
|---|---|---|---|---|
| Closed/Covered | 0 | 0 | 0 | 1 |
| Open Space | 0 | 0 | 0 | 1 |
Construction progress
Work completed on this building, as the promoter reported it to MahaRERA (Form 1).
- Excavation100%
- Basement (if any)100%
- Podiums (if any)100%
- Plinth100%
- Stilt Floor0%
- Slabs of Super Structure100%
- Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/Premises100%
- Sanitary Fittings within the flats / premises100%
- Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water Tanks100%
- External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.100%
- Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.100%
Data through9 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology