Park House Holistic Row House No. 23 · Park House Holistic

Pipla · RERA P50500011398

IDBLD_0572512 floorsExtended 4 mo
2Sanctioned habitable floorsregistration certificate
30 Apr 2027Revised completionpromised 30 Dec 2026

Floors

2 sanctioned habitable floors, as registered. MahaRERA doesn't publish flat-by-flat records, so floors are shown without flats.

As registered

RERA registration
P50500011398 · registered 31 Aug 2017
Promised completion
30 Dec 2026
Revised completion
30 Apr 2027
Sanctioned habitable floors
2
ProjectId
1,441
ProjectName
Park House Holistic
TotalUnitCount
1
ProjectBuildingId
1,96,706
BuildingNameNumber
Park House Holistic Row House No. 23
FsiWithSanctionSqmts
2
ProjectCurrentStatus
Certificate Signed
ResidentialUnitCount
1
ProjectRegistartionNo
P50500011398
ProjectBuildingWingsId
2,03,919
BuildingWingsNameNumber
NA
NonResidentialUnitCount
0
AdvertisedBuildingNameNumber
Park House Holistic Row House No. 23
NoOfBuildingWingFloorProposed
2
NoOfBuildingWingFloorHabitable
2
NoOfBuildingWingFloorSanctioned
2

Registered transactions

No registered transactions placed in this tower yetDeeds land here when they name this tower; the project page lists the rest.

Unit inventory

Apartments and other units by type, from MahaRERA's project page.

TypeCarpet areaUnitsBooked
——1not published
Total1
Data through13 Oct 2026SourcesMahaRERA registration certificate · MahaRERA project pageFloors and units are as registered; a promoter can revise them in later filings.Methodology