RERA projects in Lapaka
2 projects under 2 MahaRERA registrations, registered 2025–2025. 100% have a completion date extended beyond the one promised.
Locality
2RERA projects
2Registrations
2Completion still due0 past their completion date
4 monthsMedian extension beyond promised date100% of registrations extended
0Regulatory casesnone on MahaRERA's lists
0Buildings on recordfrom registration certificates
Registrations per year
New MahaRERA registrations by registration date.
| Year | Registrations |
|---|---|
| 2025 | 2 |
Projects in Lapaka
2 projects registered with MahaRERA.
| Project | RERA | Registered | Promised completion | Revised completion | Timing | Cases |
|---|---|---|---|---|---|---|
| Ekatmata Nagar Phase-IISURAJ DAMODHAR AWALE and RAJESH JAYWANT RAUT | P50500078983 | 28 Jan 2025 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
| Ekatmata Nagar Phase-ISuraj Damodhar Awale, Rajesh Jaywant Raut, Kishor Ramgopal Daga | P50500078868 | 17 Jan 2025 | 30 Jun 2028 | 30 Oct 2028 | Extended 4 mo | 0 |
Other localities in Nagpur
Most active promoters
By projects registered here, as named on MahaRERA.
- SURAJ DAMODHAR AWALE and RAJESH JAYWANT RAUT1 project
- Suraj Damodhar Awale, Rajesh Jaywant Raut, Kishor Ramgopal Daga1 project
Data through7 Oct 2026SourcesMahaRERA project search, registration and extension certificates, regulatory lists and ordersExtensions count where MahaRERA's extension certificate could be read; MahaRERA cannot serve some certificates, so the share extended may be understated.Methodology