Skip to content
Deedo home
Menu

Maya Nagari Park 2

Active

Karli, Nagpur 441501 |Promoter: Pravin Wamanrao Bhoyar

4 Jun 2025Registered with MahaRERA
31 Dec 2028Promised completion
1Building
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Plotted
Status on MahaRERA
Active
Buildings
1
Land area for this project
74,791 sq m (8,05,048 sq ft)
Permissible built-up area
0 sq m (0 sq ft)
Sanctioned built-up area
0 sq m (0 sq ft)
Recreational open space
14,266 sq m (1,53,558 sq ft)
Planning authority
Nagpur Metropolitan Region Development Authority (NMRDA)
Address
KH NO 104, 109, 110/1, 117, 118, 120(Part), KH NO 104, 109, 110/1, 117, 118, 120, PH NO 24, GRAMPANCHAYAT KALMESHWAR, MOUZA- KARLI(WANERI)PIN 441501
Designated bank account
State Bank Of India
Litigation declared by promoter
None declared
Financial encumbrance declared
None declared

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 21.17471, 78.90989
Maya Nagari Park 2 is at latitude 21.17471, longitude 78.90989.

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2028

Registered
4 Jun 2025
Promised
31 Dec 2028

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P505000804254 Jun 202531 Dec 2028—Pravin Wamanrao BhoyarProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Building (P50500080425)——

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Construction progress

Work completed, as the promoter reported it to MahaRERA (Form 1)

Building

  • ExcavationNot applicable
  • Basement (if any)Not applicable
  • Podiums (if any)Not applicable
  • PlinthNot applicable
  • Stilt FloorNot applicable
  • Slabs of Super StructureNot applicable
  • Internal walls, Intemal Plaster, Floorings, Floors and windows within Flats/PremisesNot applicable
  • Sanitary Fittings within the flats / premisesNot applicable
  • Staircases, Lifts Wells and Lobbies at each Floor level Overhead and Underground Water TanksNot applicable
  • External plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building / wing.Not applicable
  • Installation of Lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings, mechanical equipment, compliance to conditions ofenvironment/CRZ NOC, Finishing to entrance lobby/s, plinth protection. paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to complete project as per specifications in agreement of Sale.Not applicable

Common areas and amenities

  • Internal Roads & FootpathsAS PER PLAN0%
  • Water SupplyAS PER PLAN0%
  • Sewerage (Chamber, Lines, Septic Tank , STP)AS PER PLAN0%
  • Storm Water DrainsAS PER PLAN0%
  • Landscaping & Tree PlantingAS PER PLAN0%
  • Street LightingAS PER PLAN0%
  • Community BuildingsNot applicable
  • Treatment And Disposal Of Sewage And Sullage WaterAS PER PLAN0%
  • Solid Waste Management And DisposalNot applicable
  • Water conservation /Rain water harvestingAS PER PLAN0%
  • Energy managemcntNot applicable
  • Fire protection and fire safety requirementsNot applicable
  • Electrical meter room, sub-station, receiving stationAS PER PLAN0%
  • Aggregate area of recreational Open SpaceAS PER PLAN0%
  • Open ParkingNot applicable

Source: MahaRERA project page. Percentages are the promoter's own declaration, not an inspection.

Documents

50 documents held by Deedo, 65 filings listed on MahaRERA's project page

Commencement certificates

Others

Encumbrances

Allotment letters

Form b

Title

Form 1s

Form 2s

Registration certificate

Layout plan

Document library

  • Copy of Layout Approval (in case of layout)SANCTION PLAN.pdf · uploaded 6 Aug 2024View
  • Building Plan Approval / NA Order for plotted developmentSANCTION PLAN.pdf · uploaded 6 Aug 2024View
  • Commencement Certificates / NA Order for plotted developmentrevalidated cc 1.pdf · uploaded 18 Oct 2024View
  • Commencement Certificates / NA Order for plotted developmentna order.pdf · uploaded 18 Oct 2024View
  • Other – Technicalcommencement certificate.pdf · uploaded 18 Oct 2024View
  • Proforma of Agreement for saleAGREEMENT TO SELL.pdf · uploaded 18 Oct 2024View
  • Letter from the bank regarding the opening of RERA Designated Bank Accounts (Format B)FORMAT B.pdf · uploaded 18 Oct 2024View
  • a Details of encumbrances concerned to FinanceFINANCIAL ENCUMBRANCE.pdf · uploaded 21 Oct 2024View
  • Declaration about Commencement CertificateDECLARATION ABOUT COMMENCEMENT CERTIFICATE-1.pdf · uploaded 21 Oct 2024View
  • Declaration about all RERA Designated Bank Accounts (Format A)Format A.pdf · uploaded 21 Oct 2024View
  • b Details of encumbrances concerned to LegalFINANCIAL ENCUMBRANCE.pdf · uploaded 21 Oct 2024View
  • Other – TechnicalORDER 50.pdf · uploaded 21 Oct 2024View
  • Deviation Report with respect to model copy of AgreementDEVIATION IN AFS.pdf · uploaded 21 Oct 2024View
  • Deviation Report with respect to Allotment letterDEVIATION IN ALLOTMENT LETTER.pdf · uploaded 25 Oct 2024View
  • Disclosure of Interest in Other Real Estate Organizationsannexure a.pdf · uploaded 25 Oct 2024View
  • Disclosure for secured/unsecured finance availed for the projectDISCLOSURE OF FINANCE.pdf · uploaded 25 Oct 2024View
  • Declaration in FORM Bform b.pdf · uploaded 29 Oct 2024View
  • CERSAI detailsCERSAI DECLARATION.pdf · uploaded 29 Oct 2024View
  • Copy of the legal title reportTITLE REPORT.pdf · uploaded 4 Nov 2024View
  • a Details of encumbrances concerned to FinanceLEGAL ENCUMBRANCE.pdf · uploaded 9 Nov 2024View
  • b Details of encumbrances concerned to LegalLEGAL ENCUMBRANCE.pdf · uploaded 9 Nov 2024View
  • Proforma of Allotment letterALLOTMENT LETTER.pdf · uploaded 9 Nov 2024View
  • Engineer’s Certificate on Cost Incurred on Project (Form 2)form 2.pdf · uploaded 18 Dec 2024View
  • Architect’s Certificate of Percentage of Completion of Work (Form 1)form 1.pdf · uploaded 18 Dec 2024View
  • Other – LegalPAN DECLARATION.pdf · uploaded 11 Jan 2025View
  • Other – TechnicalPAN DECLARATION.pdf · uploaded 11 Jan 2025View
  • Other – TechnicalNAREDCO CERTIFICATE.pdf · uploaded 4 Feb 2025View
  • Other – LegalSALE DEED 110-1.pdf · uploaded 7 Feb 2025View
  • Other – LegalSALE DEED 109.pdf · uploaded 7 Feb 2025View
  • Other – LegalSALE DEED 104.pdf · uploaded 7 Feb 2025View
  • Other – LegalSALE DEED 109-1.pdf · uploaded 7 Feb 2025View
  • Other – LegalSALE DEED 118.pdf · uploaded 7 Feb 2025View
  • Other – LegalSALE DEED 117.pdf · uploaded 7 Feb 2025View
  • Other – FinancePAN DECLARATION (1).pdf · uploaded 17 Feb 2025View
  • Other – LegalPravin Wamanrao bhoyar (120)_0001.pdf · uploaded 17 Feb 2025View
  • Other – TechnicalDeclaration About Plot Area.pdf · uploaded 30 Apr 2025View
  • Other – TechnicalFORM D.pdf · uploaded 1 May 2025View
  • Other – Technical1000969516 (1).pdf · uploaded 2 May 2025View
  • Other – TechnicalDeclaration_0001.pdf · uploaded 29 May 2025View
  • Form 1Form 1 Architects Certificate Sept 2025.pdf · uploaded 15 Dec 2025View
  • Form 2Form 2 Engineers Certificate Sept 2025.pdf · uploaded 15 Dec 2025View
  • Disclosure of Sold and Booked InventoryDisclousure Of Sold & Booked Inventory Sept 25.pdf · uploaded 15 Dec 2025View
  • Form 1Form 1 Architects Certificate Dec 25.pdf · uploaded 20 Mar 2026View
  • Form 2Form 2 Engineer Certificate Dec 25.pdf · uploaded 20 Mar 2026View
  • Disclosure of Sold and Booked InventoryDisclosure Of Sold Booked Inventory Dec 25.pdf · uploaded 20 Mar 2026View
  • Form 1Form 1 Architect Certificate March 26.pdf · uploaded 20 May 2026View
  • Form 2Form 2 Engineer Certificate March 26.pdf · uploaded 20 May 2026View
  • Disclosure of Sold and Booked InventoryDisclousure Of Sold and Booked Inventory March 26.pdf · uploaded 20 May 2026View
  • Form 1Form 1 Architect Certificate June 2026.pdf · uploaded 6 Aug 2026View
  • Form 2Form 2 Engineer Certificate June 2026.pdf · uploaded 6 Aug 2026View
  • Disclosure of Sold and Booked InventoryDisclousure Of Sold Booked Inventory June 2026.pdf · uploaded 6 Aug 2026View

Promoter documents

  • Declaration Form Bform b.pdf · uploaded 29 Oct 2024View
  • Legal Title reportTITLE REPORT.pdf · uploaded 4 Nov 2024View

Technical documents

  • Layout ApprovalSANCTION PLAN.pdfView
  • NA Order for Plotted DevelopmentSANCTION PLAN.pdfView

Other legal documents

  • Other – LegalPAN DECLARATION.pdfView
  • Other – LegalSALE DEED 104.pdfView
  • Other – LegalSALE DEED 109.pdfView
  • Other – LegalSALE DEED 109-1.pdfView
  • Other – LegalSALE DEED 110-1.pdfView
  • Other – LegalSALE DEED 117.pdfView
  • Other – LegalSALE DEED 118.pdfView
  • Other – LegalPravin Wamanrao bhoyar (120)_0001.pdfView

Financial documents

  • Other – FinancePAN DECLARATION (1).pdf · uploaded 17 Feb 2025View

Proforma allotment letter

  • Proforma allotment letterALLOTMENT LETTER.pdfView

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Karli, Kalameshwar taluka

Survey, CTS, gat or plot numbers

109110/1117118120(Part)KH NO 104

As published on MahaRERA's project page

KH NO 104,109,110/1, 117,118,120(Part)

Boundaries

North
Kh No 106 123 118 109 110 121
South
Kh No 101 102 109 110-1 111 117 119
East
Nallah Kh No 110 111 117 119 120 Pandhan Ketapar K
West
Kh No 105 124 98 110 123

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectManoj K Kukde—
Chartered accountantAshish Agarwal—
Chartered accountantCa Sumit Chandwani—
EngineerManoj K Kukde—

Source: MahaRERA project page. Contact details are not shown.

Data through10 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology